Close-up of the construction of the Lo Te - Rach Soi route worth about 750 billion VND

Tạ Quang |

Can Tho - These days, on the Lo Te - Rach Soi route, there are about 200 technical staff, drivers and construction workers continuously to speed up the finish line.

Du an dau tu nang cap tuyen Lo Te – Rach Soi co tong muc dau tu khoang 750 ti dong. Tuyen dai 51,5km, di qua dia phan TP Can Tho va tinh Kien Giang (nay la tinh An Giang), den nay dat khoang 80% gia tri hop dong.
The investment project to upgrade the Lo Te - Rach Soi route has a total investment of about 750 billion VND. The 51.5km long route, passing through Can Tho city and Kien Giang province (now An Giang province), has so far reached about 80% of the contract value.
Ngay 6.8, thong tin den Bao Lao Dong, Ban Quan ly du an My Thuan cho biet, du an duoc khoi cong ngay 13.6.2024 va tien do hoan thanh theo hop dong la trong thang 9.2025. Hien nay, da hoan thanh cao boc tai che mong duong dat 100%.
On August 6, informing Lao Dong Newspaper, My Thuan Project Management Board said that the project started on June 13, 2024 and the completion schedule according to the contract is in September 2025. Currently, 100% of the road foundation recycling scraping has been completed.
Den nay, tuyen da tham BTN lop 1 (C19) dat 45,3/49,7km (dat 91%), du kien hoan thanh cung voi viec gia cuong 48 cong tren tuyen truoc ngay 15.8. Tham BTN lop 2 (C16 – lop tren cung) duoc 21,8/49,7km, dat 44%. Hoan thien he thong ATGT va khanh thanh trong thang 9.2025.
Up to now, the route has been paved with grade 1 BTN (C19) reaching 45.3/49.7km (reaching 91%), expected to be completed along with the reinforcement of 48 culverts on the route before August 15. BTN 2 (C16 - upper layer) is 21.8/49.7km, reaching 44%. Complete the traffic safety system and inaugurate it in September 2025.
Hien cac nha thau dang duy tri 22 mui thi cong dong loat tren cong truong voi hon 80 thiet bi, may thi cong; 200 can bo ky thuat, lai may va cong nhan thi cong lien tuc; to chuc thi cong tang ca nhieu mui de hoan thanh du an.
Currently, contractors are maintaining 22 simultaneous construction teams at the construction site with more than 80 construction equipment and machines; 200 technical staff, drivers and workers are continuously working; organizing overtime at many teams to complete the project.
Tranh thu thoi tiet thuan loi cac ky su, cong nhan tham nhua be tong.
Taking advantage of favorable weather, engineers and workers paved concrete.
Khong nhung vay, cac don vi thi cong lam viec ca buoi toi de dam bao tien do du an. Theo Ban QLDA My Thuan, don vi da chi dao nha thau dieu chinh tien do va phuong an thi cong de day nhanh tien do.
Not only that, construction units worked all evening to ensure project progress. According to the My Thuan Project Management Board, the unit has directed the contractor to adjust the progress and construction plan to speed up the progress.
Ban QLDA My Thuan cung cho biet, day la du an thuoc danh muc 3.000km duong cao toc phai hoan thanh trong nam 2025 theo chi dao cua Thu tuong Chinh phu va Bo Xay dung.
The My Thuan Project Management Board also said that this is a project on the list of 3,000km of expressways that must be completed in 2025 under the direction of the Prime Minister and the Ministry of Construction.
Tạ Quang
RELATED NEWS

The story of victims of "online kidnapping" in Can Tho

|

Can Tho - Subjects manipulate the victim's psychology combined with technology to carry out fraud.

Can Tho informs 2 projects worth over VND 28,500 billion to start construction on August 19

|

Can Tho - O Mon 4 Thermal Power Plant and Housing in the Trade Union Institution Area in An Nghiep Industrial Park are two projects that will start construction on August 19.

Day and night construction, completing the upgrading of the Lo Te - Rach Soi route in September 2025

|

Can Tho - Contractors are maintaining 22 simultaneous construction teams at the construction site with more than 80 construction equipment, machines, etc.

Container truck catches fire on My Phuoc - Tan Van road in Ho Chi Minh City

|

HCMC - A container truck caught fire on My Phuoc - Tan Van road. The authorities quickly put out the fire and regulated traffic.

20h News: People complain about the sudden increase in electricity bills in July despite being absent

|

People complain about the sudden increase in electricity bills in July despite being absent; The Ministry of Home Affairs responds to recommendations on the arrangement of concurrent commune accountants...

Early resignation is no longer a strategic move for Ms. Paetongtarn

|

August is considered a turning point in the political fortunes of Ms. Paetongtarn Shinawatra and Mr. Thaksin Shinawatra.

In the next 4 days, many streets in Hanoi will ban vehicles from circulating during certain time frames

|

Hanoi - Some routes will completely ban vehicles from circulating during certain time frames (from August 7 to August 10, 2025).

There are projects of thousands of hectares abandoned for 20 years but the State has not collected anything

|

According to Mr. Le Dinh Thang - Chief Auditor of the State Audit Office, Sector 2, there are projects of thousands of hectares that have been abandoned for 20 years but the State has not collected anything.

The story of victims of "online kidnapping" in Can Tho

Tạ Quang |

Can Tho - Subjects manipulate the victim's psychology combined with technology to carry out fraud.

Can Tho informs 2 projects worth over VND 28,500 billion to start construction on August 19

Tạ Quang |

Can Tho - O Mon 4 Thermal Power Plant and Housing in the Trade Union Institution Area in An Nghiep Industrial Park are two projects that will start construction on August 19.

Day and night construction, completing the upgrading of the Lo Te - Rach Soi route in September 2025

Tạ Quang |

Can Tho - Contractors are maintaining 22 simultaneous construction teams at the construction site with more than 80 construction equipment, machines, etc.