The laying of the first meters of asphalt marks the transition from the roadbed construction phase to the road surface completion phase of the Can Tho - Ca Mau expressway.







|
Can Tho - The deeper they dig, the more leachate is released from landfill No. 8, blocking the Can Tho - Ca Mau expressway, forcing the unit to dig temporary pits to contain it.
|
Prime Minister Pham Minh Chinh requested the Can Tho - Ca Mau expressway to be completed before December 31, 2025.
|
Can Tho - Following the Prime Minister's direction, the construction of the relocation of the landfill blocking the Can Tho - Ca Mau expressway is being accelerated by the units.
|
The meteorological agency forecasts that from the evening and night of June 25, the North will have widespread showers and thunderstorms. This is the reason for ending the heat wave in this area from June 26.
|
Apartment prices at many projects in Hanoi are decreasing from 8-15% compared to the peak period. The trend of adjustment is forecast to appear more often in the near future.
|
The workshop "Improving the efficiency of green credit capital flows, a driving force for economic growth" will be a forum to remove bottlenecks in accessing green credit.
Tạ Quang - Yến Phương |
Can Tho - The deeper they dig, the more leachate is released from landfill No. 8, blocking the Can Tho - Ca Mau expressway, forcing the unit to dig temporary pits to contain it.
PHẠM ĐÔNG |
Prime Minister Pham Minh Chinh requested the Can Tho - Ca Mau expressway to be completed before December 31, 2025.
TẠ QUANG - YẾN PHƯƠNG |
Can Tho - Following the Prime Minister's direction, the construction of the relocation of the landfill blocking the Can Tho - Ca Mau expressway is being accelerated by the units.