The bridge to relieve traffic jams at the southern gateway of Ho Chi Minh City has reached 70% progress

Anh Tú |

HCMC - The Rach Dia bridge project connecting District 7 and Nha Be district is being accelerated to complete by the end of 2024. Currently, the progress of the entire project has reached 70% of the volume.

As noted by the reporter, at the Rach Dia bridge construction site, in the middle of April 2024, there were busy machines, vehicles and many workers actively working despite the intense heat.
Rach Dia Bridge connects the two ends of Nha Be district - District 7 (HCMC), construction started in July 2023 with the Ho Chi Minh City Traffic Construction Investment Project Management Board (Transportation Board) as the investor. with a total cost of more than 500 billion VND. This bridge spans the canal of the same name, with the hope that after completion, it will become a lifeline bridge, increasing the connectivity of Nha Be district and District 7.
According to design, the new Rach Dia bridge is 318m long, 9-10.5m wide, including 9 spans. The two ends of the bridge are made of paths with a total length of 233m and width of 14-27m. Total investment is 513 billion VND.
According to design, the new Rach Dia bridge is 318m long, 9-10.5m wide, including 9 spans. The two ends of the bridge are made of paths with a total length of 233m and width of 14-27m. Total investment is 513 billion VND.
After many months of construction, the project to build a new bridge at the southern gateway of Ho Chi Minh City is currently at 70% progress. According to records at the construction site, up to this point, the project has completed 9/10 abutments and is working on the remaining bridge piers. 7/9 spans have been completed with beam installation and the bridge deck is under construction.
After many months of construction, the project to build a new bridge at the southern gateway of Ho Chi Minh City is currently at 70% progress. According to records at the construction site, up to this point, the project has completed 9/10 abutments and is working on the remaining bridge piers. 7/9 spans have been completed with beam installation and the bridge deck is under construction.
  According to the Management Board of Ho Chi Minh City Traffic Construction Investment Projects (Transportation Department), on the existing construction site, about 30 workers are divided into 4 construction sites, including 3 on land and 1 on the ground. water to speed up progress. It is expected that this project will be completed to traffic by the end of this year.
According to the Management Board of Ho Chi Minh City Traffic Construction Investment Projects, there are currently about 30 workers on the construction site divided into 4 construction sites, including 3 on land and 1 under water to speed up progress. It is expected that this project will be completed to traffic by the end of this year.
The residential roads on both sides have basically completed foundation treatment and load reduction floors, and 95% of sewers have been installed. The construction unit is continuing to build road foundations and retaining walls.
The residential roads on both sides have basically completed foundation treatment and load reduction floors, and 95% of sewers have been installed. The construction unit is continuing to build road foundations and retaining walls.
“From the day the old bridge was removed, it took me an extra 30 minutes to travel around the Nguyen Van Linh underpass intersection area. I just hope the project will be completed soon so people can travel more conveniently" - Mr. Le Huy Vinh (43 years old) expressed.
“Previously, the travel of people in Phuoc Kien commune (Nha Be district) and Tan Phong ward (District 7) had to depend on the (old) Rach Dia iron bridge built before 1975. Because the bridge was Seriously degraded and narrow, causing frequent traffic jams. I just hope the new bridge project will be completed soon so people can travel more conveniently," said Mr. Hoang, who lives near Rach Dia bridge.
According to the Traffic Department, the construction of the new Rach Dia bridge is important, contributing to improving the regional traffic situation and creating motivation for socio-economic development. In addition, Rach Dia bridge will increase traffic capacity, contribute to connecting with Long An province, and synchronously exploit traffic infrastructure south of Ho Chi Minh City.
When completed, the new Rach Dia Bridge will have important significance, contributing to improving the regional traffic situation and creating motivation for socio-economic development. In addition, Rach Dia bridge will increase traffic capacity, contribute to connecting with Long An province, and synchronously exploit traffic infrastructure in the south of Ho Chi Minh City.
Anh Tú
RELATED NEWS

2 hầm chui giải cứu kẹt xe cửa ngõ TPHCM thông xe tháng 8

Anh Tú |

TPHCM - 1 nhánh hầm chui trên đường Nguyễn Văn Linh và hầm chui Trần Quốc Hoàn – Phan Thúc Duyện sắp thông xe trong tháng 8 giúp giải cứu kẹt xe các cửa ngõ.

Một nhánh hầm chui nút giao Nguyễn Văn Linh sắp thông xe

Anh Tú |

TPHCM - Sau thời gian thi công, đến nay một nhánh hầm chui nút giao Nguyễn Văn Linh - Nguyễn Hữu Thọ đã gần hoàn thành, và dự kiến thông xe trong tháng 8.2024.

Tiến độ thi công cầu Rạch Đỉa hơn 500 tỉ đồng giải cứu kẹt xe cửa ngõ phía Nam

Anh Tú |

TPHCM - Dự án cầu Rạch Đỉa trên đường Lê Văn Lương (nối Quận 7 và huyện Nhà Bè) có tổng vốn đầu tư hơn 500 tỉ đồng đang được đẩy nhanh thi công để hoàn thành cuối năm nay, nhằm thay thế cầu sắt cũ hơn 50 tuổi đã được tháo dỡ trước đó và giúp giảm kẹt xe cho khu vực cửa ngõ phía Nam TPHCM. Hiện tiến độ toàn dự án đạt gần 50% khối lượng.

Vụ công trình làm nứt nhà dân ở Hà Nội, chính quyền nói gì?

NHÓM PV |

Theo chính quyền phường Quang Trung, hình ảnh công nhân đang làm việc tại công trình số nhà 19, ngõ 136/98 Tây Sơn là để hút nước phòng dịch sốt xuất huyết.

Triều Tiên cho nổ tung tuyến đường bộ nối với Hàn Quốc

Khánh Minh |

Triều Tiên cho nổ tung các tuyến đường nối với Hàn Quốc vốn từng được coi là biểu tượng của sự hợp tác liên Triều.

Thân tín của bà trùm ma túy Oanh "Hà" được trả công 15 tỉ

Việt Dũng |

Trong số hơn 626kg ma túy mua bán xuyên quốc gia do bà trùm Oanh "Hà" cầm đầu, Nguyễn Văn Nam có mặt hầu hết ở các chuyến hàng, nhận công hậu hĩnh.

Bất cập tiền công đức 2 đền ở Ninh Bình do nguồn thu quá lớn

NGUYỄN TRƯỜNG |

Ninh Bình - Những tồn tại, bất cập trong việc quản lý tiền công đức tại đền Dâu và đền Quán Cháo (thành phố Tam Điệp) là do nguồn thu quá lớn.

Chánh văn phòng hãng luật bị tố đe dọa, xúc phạm phụ nữ

TRÍ MINH |

Một chánh văn phòng hãng luật bị tố cáo có hành vi đe dọa, xúc phạm danh dự, nhân phẩm phụ nữ. Người dân đã trình báo sự việc tới cơ quan công an.

2 hầm chui giải cứu kẹt xe cửa ngõ TPHCM thông xe tháng 8

Anh Tú |

TPHCM - 1 nhánh hầm chui trên đường Nguyễn Văn Linh và hầm chui Trần Quốc Hoàn – Phan Thúc Duyện sắp thông xe trong tháng 8 giúp giải cứu kẹt xe các cửa ngõ.

Một nhánh hầm chui nút giao Nguyễn Văn Linh sắp thông xe

Anh Tú |

TPHCM - Sau thời gian thi công, đến nay một nhánh hầm chui nút giao Nguyễn Văn Linh - Nguyễn Hữu Thọ đã gần hoàn thành, và dự kiến thông xe trong tháng 8.2024.

Tiến độ thi công cầu Rạch Đỉa hơn 500 tỉ đồng giải cứu kẹt xe cửa ngõ phía Nam

Anh Tú |

TPHCM - Dự án cầu Rạch Đỉa trên đường Lê Văn Lương (nối Quận 7 và huyện Nhà Bè) có tổng vốn đầu tư hơn 500 tỉ đồng đang được đẩy nhanh thi công để hoàn thành cuối năm nay, nhằm thay thế cầu sắt cũ hơn 50 tuổi đã được tháo dỡ trước đó và giúp giảm kẹt xe cho khu vực cửa ngõ phía Nam TPHCM. Hiện tiến độ toàn dự án đạt gần 50% khối lượng.