Thao Long Dam in Hue deteriorates, struggling to regulate water

PHÚC ĐẠT - NGUYỄN LUÂN |

HUE - After nearly 20 years of operation, Thao Long dam clearly shows its deterioration, but the urgent repair project worth nearly 350 billion VND has not yet been implemented.

La cong trinh thuy loi trong yeu nam tai phuong Hoa Chau (TP Hue), dap Thao Long duoc xay dung voi ky vong ngan man, giu ngot, gop phan dieu tiet nguon nuoc phuc vu san xuat nong nghiep va sinh hoat cho vung ha du song Huong.
As an important irrigation project located in Hoa Chau ward (Hue city), Thao Long dam was built with the expectation of preventing salinity, keeping fresh water, contributing to regulating water resources for agricultural production and daily life in the downstream area of the Huong River.
Cong trinh duoc dua vao khai thac tu nam 2008 voi tong von dau tu thoi diem do len den 152 ti dong.
The project was put into operation in 2008 with a total investment of VND152 billion at that time.
Tong the dap dai 571m, gom 15 khoang cong voi cua van khau do lon 31,5m; he thong au thuyen co hai cua rong 8m giup dam bao giao thong thuy.
The overall dam is 571m long, including 15 culvert compartments with large valve gates of 31.5m; the boat dock system has two gates 8m wide to ensure waterway traffic.
Dap Thao Long con phoi hop voi cac ho chua lon trong vung nhu Ta Trach, Binh Dien de dieu tiet dong chay, dieu hoa muc nuoc trong mua kho lan mua mua lu.
Thao Long Dam also coordinates with large reservoirs in the area such as Ta Trach and Binh Dien to regulate the flow and regulate water levels during the dry season and flood season.
Tuy nhien, sau gan hai thap nien van hanh trong dieu kien khac nghiet, dac biet la thuong xuyen tiep xuc voi nuoc man, nhieu hang muc cua dap da boc lo dau hieu xuong cap nghiem trong.
However, after nearly two decades of operation in harsh conditions, especially frequent exposure to saltwater, many items of the dam have shown signs of deterioration.
Theo ghi nhan, he thong cua van bang thep CT3 da bi an mon, ri set nang.
According to records, the CT3 steel valve door system has been severely eroded and rusted.
Ket cau thiet bi ky thuat bi gi set nghiem trong.
Technical equipment structure is rusty.
Thiet bi dien, dien tu ngoai troi, thiet bi thuy luc da hu hong do tac dong cua thoi tiet va moi truong.
Electrical equipment, outdoor electronics, and hydraulic equipment have been damaged due to the impact of weather and the environment.
Cac sinh vat, bun lang bam day o tam ngan nuoc.
The creatures and mud were clinging to the water barrier.
Mot cua van cua dap Thao Long “oan minh” dieu tiet nuoc trong hien trang xuong cap.
A valve gate of Thao Long Dam is "struggling" to regulate water in a state of disrepair.
Nhieu nam truoc, Bo Nong nghiep & Phat trien nong thon (nay la Bo Nong nghiep va Moi truong) da phe duyet Du an sua chua cap bach dam bao an toan cong trinh dap Thao Long voi tong muc dau tu gan 350 ti dong.
Many years ago, the Ministry of Agriculture and Rural Development (now the Ministry of Agriculture and Environment) approved the Urgent Repair Project to ensure the safety of the Thao Long dam project with a total investment of nearly 350 billion VND.
Den nay, khi du an chua trien khai, dap ngan man, giu ngot nay van phai oan minh de lam tot nhiem vu trong hien trang ngay cang xuong cap.
Up to now, when the project has not been implemented, this dam to prevent salinity and keep the sweetness still has to struggle to do a good job in the increasingly degraded state.

The project will renovate the following items: Replace 6 valve doors and repair 9 valve doors, replace all the bottom water clusters and side water clusters at 15 gates; replace the doors and bulletproof bridges with stainless steel, waterproofing with rubber and garlic rubber.

Arrange a cluster with water on the sides and bottom to facilitate repair, replacement of gaskets and maintenance of valve doors. Replace the closed silinder system with the main valve and drainage valve.

In addition, the project will handle the dambed seepage, handle the cracks under the project valve beams, which will reinforce the erosion holes and downstream flows of the project. Upgrading and repairing the power system to control the valves at the project and the management house; repairing and upgrading the management house, embankment combined with the management road at both ends of Thao Long dam.

In addition, the project will renovate traffic bridges, lighting systems, and signs; build a monitoring system to serve the management and operation of the project.

PHÚC ĐẠT - NGUYỄN LUÂN
TIN LIÊN QUAN

The road to the Key Industrial Park in Gia Lai is seriously degraded

|

Gia Lai - The road to Tra Da Industrial Park, one of the vibrant industrial parks in Gia Lai, is currently degraded and severely damaged.

Will propose Quang Tri province to repair or rebuild the degraded Cho bridge

|

Quang Tri - Cho Bridge, a vital traffic route in Phu Trach commune, is at risk of being unsafe due to many items being severely degraded after more than 30 years of use.

The ship capsize in Ha Long Bay cannot leave the responsibility of related units unanswered

|

The ship capsize in Ha Long Bay caused dozens of casualties, shocked public opinion, and raised many questions about the responsibility of the parties involved.

The kiss of Phuong My Chi and the hundred-billion-dong beauty caused a stir

|

Phuong My Chi participated in the competition for the competition in Em xinh say hi. She had a surprising kiss with her co-star.

Ninh Binh Department of Tourism leaders talk about the ferry problem in Tam Coc

|

Ninh Binh - The leader of the provincial Department of Tourism informed about the boat problem in Tam Coc Tourist Area on the afternoon of July 19.

Securities continue to conquer new highs

|

The vibrant cash flow continues to spread and lead the stock market to new peaks of the year, especially testing the strong resistance level of 1,500 points.

Strongly spreading the patriotic emulation movement of the working class

|

During the resistance war against the US (1954 - 1975), the Vietnam General Confederation of Labor gathered, united, and promoted the pioneering role of the working class in overcoming countless difficulties, hardships, and sacrifices, contributing to the army and people of the whole country in the victory on April 30, 1975 .

Kiểm tra, xử lý thông tin phản ánh đường liên tỉnh ở Nghệ An xuống cấp nghiêm trọng

QUANG ĐẠI - PHẠM CHUNG |

Nghệ An – Sở Văn hóa – Thể thao và Du lịch đề nghị Sở Xây dựng kiểm tra thông tin Báo Lao Động phản ánh đường ĐH20 xuống cấp nghiêm trọng.

The road to the Key Industrial Park in Gia Lai is seriously degraded

THANH TUẤN |

Gia Lai - The road to Tra Da Industrial Park, one of the vibrant industrial parks in Gia Lai, is currently degraded and severely damaged.

Will propose Quang Tri province to repair or rebuild the degraded Cho bridge

CÔNG SÁNG - NGUYỄN LUÂN |

Quang Tri - Cho Bridge, a vital traffic route in Phu Trach commune, is at risk of being unsafe due to many items being severely degraded after more than 30 years of use.