Shape of Ring Road 3 through Cu Chi district after 14 months of construction

Anh Tú |

The atmosphere at the Ho Chi Minh City Ring Road 3 project passing through Cu Chi district is currently very bustling with the efforts of hundreds of workers working day and night to speed up the project's progress.

 Du an Vanh dai 3 TPHCM doan qua dia ban TPHCM (du an thanh phan 1) co tong chieu dai 47km, bao gom 10 goi thau xay lap chinh va 4 goi thau phuc vu van hanh khai thac. Hien tai, tong tien do thi cong da dat khoang gan 20% gia tri hop dong. Trong do, goi thau XL6 du an duong vanh dai 3 TPHCM doan qua huyen Cu Chi da dat hon 30% tong san luong.
The Ho Chi Minh City Ring Road 3 project through Ho Chi Minh City (component project 1) has a total length of 47km, including 10 main construction packages and 4 operation packages. Currently, the total construction progress has reached nearly 20% of the contract value. Of which, package XL6 of the Ho Chi Minh City Ring Road 3 project through Cu Chi district has reached more than 30% of the total volume.
 Goi thau XL6 co tong chieu dai 6,07km (diem dau tiep giap voi goi thau cau Binh Goi thuoc du an thanh phan 5 do Ban Quan ly xay dung Binh Duong lam chu dau tu, diem cuoi noi voi goi XL7 doan qua huyen Hoc Mon), gia tri khoang 2.200 ti dong, gom hang muc duong cao toc, duong song hanh, cau vuot song rach, cau vuot duong cao toc, ham chui Tinh lo 15 va he thong cong hop ngang duong.
Package XL6 has a total length of 6.07km (the starting point is adjacent to the Binh Goi Bridge package under component project 5 invested by Binh Duong Construction Management Board, the end point is connected to package XL7 through Hoc Mon district), worth about 2,200 billion VND, including expressway items, parallel roads, river overpasses, expressway overpasses, Provincial Road 15 underpasses and cross-road box culvert systems.
 Hien goi thau 5 don vi tham gia thuc hien (Truong Son - 319 - Dai Phong - CK4 - Quang Phuc), dang trien khai dong loat 12 mui thi cong voi hang tram cong nhan lam viec ngay dem de dam bao cho du an hoan thanh dung tien do.
Currently, the package has 5 participating units (Truong Son - 319 - Dai Phong - CK4 - Quang Phuc), simultaneously deploying 12 construction sites with hundreds of workers working day and night to ensure the project is completed on schedule.
 Cong tac dao khuon duong, thi cong coc khoan nhoi dang duoc cac nha thau tat bat trien khai
Road excavation and bored pile construction are being carried out by contractors.
 Rieng ham chui so 1 tren Tinh lo 15 da dat hon 50% so luong coc khoan nhoi, ham chui so 2 dat khoang 90% so luong coc khoan nhoi.
According to the representative of Truong Son contractor, the current progress at the underpass No. 1 of Provincial Road 15 has reached 489/535 bored piles, the Vo Van Bich bridge has reached 30/54 bored piles and is currently constructing 5 piers from pier T4 to pier M2.
aaa
At the Vo Van Bich bridge construction area, the contractor has also built a bypass to ensure traffic for people.
 Phan cau va phan duong tuyen vanh dai 3 TPHCM qua cau Cay Xanh (huyen Cu Chi), thuoc goi XL6 dang thi cong gac dam cau. Khong khi thi cong nhon nhip, hoi ha, khien cong trinh thay doi dien mao tung ngay.
The bridge section and the road section of Ho Chi Minh City's Ring Road 3 through Cay Xanh Bridge (Cu Chi District), part of Package XL6, are under construction with the bridge girder. The bustling and hurried construction atmosphere has caused the project to change its appearance every day.
Du thoi tiet anh huong nhieu nhung don vi van co gang thi cong 3 ca 4 kip, duy tri hon mot tram cong nhan cung hang chuc loai may moc, thiet bi.
Despite the weather's impact, the unit still tried to work in 3 shifts, maintaining more than 100 workers and dozens of types of machinery and equipment.
 Diem dau goi XL6 da len hinh hai cau, doan nay tiep giap voi goi thau cau Binh Goi dang thi cong thuoc du an thanh phan 5 do Ban Quan ly xay dung Binh Duong lam chu dau tu.
The starting point of the XL6 package has taken shape of a bridge, this section is adjacent to the Binh Goi bridge package under construction under component project 5 invested by Binh Duong Construction Management Board.
 Toan canh tuyen Vanh dai 3 bang qua dong ruong tren dia ban huyen Cu Chi.
Panoramic view of Ring Road 3 crossing rice fields in Cu Chi district.

The entire Ring Road 3 route passing through Ho Chi Minh City, Binh Duong, Dong Nai, Long An, phase 1 investment is over 76 km long, with a total investment of over 75,300 billion VND. The project is expected to be completed in 2026, in addition to connecting traffic, it also creates an urban and industrial corridor for not only the 4 provinces and cities through which the route passes but also impacts the entire key economic region of the South.

Anh Tú
TIN LIÊN QUAN

Ho Chi Minh City Ring Road 3 through Dong Nai clears 90% of land

|

Dong Nai - Component 3 project of Ho Chi Minh City Ring Road 3, section through Nhon Trach district, has cleared more than 90% of the land.

Viewing Ho Chi Minh City Ring Road 3 after more than 1 year of construction

|

HCMC - The Ho Chi Minh City Ring Road 3 project through Hoc Mon district has reached 15% progress after more than 1 year of construction.

Hanoi driver cleans up fallen bricks on elevated Ring Road 3

|

Hanoi - Seeing bricks scattered on the elevated Ring Road 3, the driver stopped the car in the emergency lane, turned on the warning signal, then carried the bricks and stacked them neatly inside.

What does the Department of Minerals say about the phenomenon of sudden high sand auction prices?

|

The Vietnam Minerals Department believes that there should be sanctions to prohibit units from bidding high prices for minerals and then abandoning deposits, causing market disruption.

Storm Tra Mi is forecast to move quickly and continuously strengthen in the East Sea

|

The meteorological agency forecasts that after entering the North East Sea, storm Tra Mi is likely to strengthen.

Nhan Dan Newspaper launches National Brands page

|

On the afternoon of October 22, Nhan Dan Newspaper in collaboration with the Ministry of Industry and Trade launched the National Brand page, providing comprehensive data on leading enterprises.

Import and export exceed 600 billion USD, forecast to have many more records

|

As of mid-October, the country's total import-export turnover reached 610.56 billion USD, with a trade surplus of 21.24 billion USD. It is forecasted that it could reach 800 billion USD by the end of the year.

Proposing China to properly handle the issue of fishing boats and fishermen

|

Vietnam requests that China properly handle the issue of fishing vessels and fishermen; respect each other's legitimate and legal rights and interests.

Ho Chi Minh City Ring Road 3 through Dong Nai clears 90% of land

HÀ ANH CHIẾN |

Dong Nai - Component 3 project of Ho Chi Minh City Ring Road 3, section through Nhon Trach district, has cleared more than 90% of the land.

Viewing Ho Chi Minh City Ring Road 3 after more than 1 year of construction

Minh Tâm - Anh Tú |

HCMC - The Ho Chi Minh City Ring Road 3 project through Hoc Mon district has reached 15% progress after more than 1 year of construction.

Hanoi driver cleans up fallen bricks on elevated Ring Road 3

KHÁNH AN |

Hanoi - Seeing bricks scattered on the elevated Ring Road 3, the driver stopped the car in the emergency lane, turned on the warning signal, then carried the bricks and stacked them neatly inside.