Long Thanh airport revealed after more than 1 year of rapid construction

HÀ ANH CHIẾN |

Dong Nai - After more than 1 year of rapid construction, the Long Thanh airport passenger terminal has gradually emerged, taking on the traditional lotus shape.

Goi thau 5.10 thi cong xay dung va lap dat thiet bi cong trinh nha ga hanh khach duoc khoi cong ngay 31.8.2023, den nay sau hon 1 nam thi cong cong trinh duoc vi nhu trai tim cua du an san bay Long Thanh da dan lo dien, mang dang hinh hoa sen truyen thong.
Package 5.10, construction and installation of equipment for the passenger terminal project, started on August 31, 2023. After more than 1 year of construction, the project, considered the heart of the Long Thanh airport project, has gradually emerged, taking on the traditional lotus shape.
Theo Tong Cong ty Cang hang khong Viet Nam (ACV), goi thau 5.10 thi cong nha ga hanh khach co gia tri hop dong 33.185 ti dong. Den nay, sau khi hoan thanh thi cong toan bo cong tac be tong cot thep phan ngam, tang 1F, 2F, 3F, 4F, cac nha thau dang tap trung nhan luc lap dung mai thep nha ga.
According to the Vietnam Airports Corporation (ACV), the contract value for the 5.10 package for the construction of the passenger terminal is 33,185 billion VND. Up to now, after completing the entire reinforced concrete work of the underground part, floors 1F, 2F, 3F, 4F, the contractors are focusing on the construction of the steel roof of the terminal.
Theo ghi nhan thuc te cua phong vien bao Lao Dong tai cong truong thi cong nha ga hanh khach, tai day cac can bo ky su va cong nhan dang thi cong voi khong khi soi noi cua nhung ngay dau nam 2025. Do thi cong tren cao, cong tac dam bao an toan lao dong duoc dac biet coi trong.
According to the actual records of Lao Dong newspaper reporters at the construction site of Long Thanh airport passenger terminal, officers, engineers and workers are working in the bustling atmosphere of the first days of 2025. Due to the construction at high altitudes, ensuring labor safety is especially important.
Ong Nguyen Duc Thuan - Pho giam doc dieu hanh lien danh goi thau 5.10 - san bay Long Thanh cho biet: De dam bao tien do cong trinh, lien danh nha thau da len ke hoach huy dong cong nhan va ky su lam viec xuyen Tet Nguyen dan 2025, duy tri toi thieu 70% nhan luc trong suot ky nghi.
Mr. Nguyen Duc Thuan - Deputy Executive Director of the Joint Venture for Package 5.10, Long Thanh Airport, said that to ensure the progress of the project, the Joint Venture has planned to mobilize workers and engineers to work through the 2025 Lunar New Year, maintaining at least 70% of the workforce during the holiday.
Theo ACV, doi voi ket cau thep, phan lap dung keo thep chinh khu canh dat 96% va doi voi khu trung tam dat 41%.
According to ACV, for steel structures, the main steel truss erection in the wing area reached 96% and in the central area reached 41%.
Ong Duong Quang Dien - Pho Giam doc Thuong truc Ban Quan ly du an san bay Long Thanh - cho biet: “Nam 2025 la nam tang toc, but pha tao tien de dua cong trinh san bay Long Thanh dat moc tien do som nhat“.
Mr. Duong Quang Dien - Permanent Deputy Director of Long Thanh Airport Project Management Board - said: "2025 is the year of acceleration and breakthrough, creating the premise to bring Long Thanh airport project to the earliest progress milestone".
Cong tac lap dung khung thep phu cung bat dau duoc trien khai o khu trung tam.
The erection of the secondary steel frame has also begun in the central area.
Ben canh goi thau 5.10, goi thau 4.6, thi cong duong cat ha canh, duong lan, san do tau bay, ACV quyet tam chi dao cac don vi thi cong hoan thanh va khai thac ky thuat duong cat ha canh truoc ngay 30.4.2025.
In addition to package 5.10, package 4.6, construction of runways, taxiways, and aircraft parking lots, ACV is determined to direct construction units to complete and technically exploit the runways before April 30, 2025.
Trung ta Le Van Tien - Chi huy truong Lien danh nha thau goi thau 4.6 thuoc Tong Cong ty Xay dung cong trinh hang khong ACC (giua anh) giam sat viec thi cong tai goi thau 4.6 - duong cat ha canh san bay Long Thanh.
Lieutenant Colonel Le Van Tien - Commander of the Joint Venture of Package 4.6 under ACC Aviation Construction Corporation (center of photo) supervises the construction of Package 4.6 - Long Thanh airport runway.
HÀ ANH CHIẾN
TIN LIÊN QUAN

Bidding for 1 package of Long Thanh airport connecting road project

|

Dong Nai - A consortium of two contractors won a bid worth over 200 billion VND for the project to build provincial road 25C connecting Long Thanh airport.

Dong Nai auctions 282-hectare land plot next to Long Thanh airport

|

Dong Nai Province Land Fund Development Center proposed to auction a 282-hectare land plot in Binh Son Commune, Long Thanh District, near Long Thanh Airport, worth VND7,400 billion.

Ho Chi Minh City builds a 78.2km long, 4-8 lane wide Saigon River road

|

Ho Chi Minh City will build a 78.2km long Saigon River road, from the Ben Luc - Long Thanh expressway intersection with Rung Sac road to the Tay Ninh province border, with 4 - 8 lanes wide.

Waste classification is difficult due to lack of infrastructure and collection mechanism

|

According to the Law on Environmental Protection 2020 and Decree 45/2022 effective from January 1, 2025, people must classify waste at source (PLRTN) into 3 groups: Reusable and recyclable waste; food waste; other household waste. Failure to comply will result in a fine of VND 500,000 - VND 1,000,000. However, in reality, PLRTN in both Hanoi and Ho Chi Minh City has not been implemented due to many difficulties.

Vietnam team was awarded more than 20 billion VND after winning the ASEAN Cup

|

Vietnam team received a bonus after winning the 2024 ASEAN Cup.

Hanoi is still among the top polluted places in the world. Where is the most fine dust this morning?

|

On the morning of January 6, Hanoi continued to be in the top of the most polluted cities in the world.

What did the referee say to the Thai team after Supachok scored?

|

The referee spent more than 10 minutes talking with the players and coaching staff of the Thai team after Supachok's goal.

Rice prices plummet, farmers' income drops as Tet approaches

|

Soc Trang - Rice prices continue to fall, farmers' profits are getting lower and lower while the Lunar New Year 2025 is approaching.

Bidding for 1 package of Long Thanh airport connecting road project

HÀ ANH CHIẾN |

Dong Nai - A consortium of two contractors won a bid worth over 200 billion VND for the project to build provincial road 25C connecting Long Thanh airport.

Dong Nai auctions 282-hectare land plot next to Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai Province Land Fund Development Center proposed to auction a 282-hectare land plot in Binh Son Commune, Long Thanh District, near Long Thanh Airport, worth VND7,400 billion.

Cận cảnh 2 tuyến đường kết nối sân bay Long Thành với TPHCM sau 1 năm thi công

HÀ ANH CHIẾN |

Đồng Nai - 1 năm sau khi khởi công, gói thầu 6.12 thi công 2 tuyến giao thông kết nối sân bay Long Thành (tuyến số 1 và tuyến số 2) với đường cao tốc TP Hồ Chí Minh - Long Thành - Dầu Giây, Quốc lộ 51 và đường tỉnh lộ 25C đã dần lộ diện.