On the construction site of a hundred billion dong road in a mountainous district of Thai Nguyen

NGUYỄN HOÀN |

Thai Nguyen - Right in the first days of 2025, at the construction site of the hundred-billion-dong road connecting National Highway 37 and Provincial Road 269B, contractors are rushing to construct and speed up the progress.

1
The project connecting National Highway 37 and Provincial Road (DT) 269B has a total investment of 222 billion VND, invested by the Thai Nguyen Provincial Traffic Construction Investment Project Management Board, and will be implemented in December 2023.
2
The project is designed according to the standards of a grade III mountain road. The total length of the route is 6.1 km through the communes of Xuan Phuong, Tan Kim, Tan Thanh (Phu Binh), the starting point connects the main road through Xuan Phuong commune, the end point intersects with DT.269B at Km5+450.
3
According to the reporter's records in early January 2025, after more than 1 year of implementation, the project has been basically completed. Workers and machines are urgently implementing some items, speeding up the progress.
Gh
Machinery and vehicles urgently leveled and transported soil to create a flat surface.
Mot so doan tuyen khac sau khi tien hanh san gat, dao dap nen duong, rai da xong se duoc don vi thi cong dang lu nen nen dat truoc khi tham nhua.
Some other sections, after leveling, digging, and spreading rocks, will have the ground compacted by the construction unit before asphalting.
Bbss
At some construction sites, barriers and warning signs are installed to ensure safety for people and vehicles passing through.
6
The entire route has basically been paved.
Hbdns
The collection and drainage project on both sides of the road is gradually being completed.
Gbb
Workers are building and installing an overpass at the project's starting point at the intersection with National Highway 37.
Fv
Mr. Nguyen Van Thang, a worker at the project, said: "We are currently constructing the bridge body and approach road. The road surface of the entire route is now basically finished, and people can travel. The weather is dry in the last months of the year, so construction is easy and convenient."
Gv
Talking to reporters, Mr. Nguyen Dinh Dang - Chairman of Tan Kim Commune People's Committee said that currently the section of the route passing through the commune has been paved with asphalt.
Fgh
"Currently, the project progress has reached about 90%, the more than 4 km road section through Tan Kim commune is basically completed. Some other sections are being urgently implemented, expected to be completed by February 2025. This route put into use will help improve the regional traffic infrastructure, shorten travel time and distance, and promote trade," Mr. Dang added.
NGUYỄN HOÀN
TIN LIÊN QUAN

Breaking rocks to open a hundred billion dong road in Tuyen Quang

|

Tuyen Quang - After 3 years of construction, the more than 4 km long Son Duong town bypass road still cannot be completed due to the hard rocky terrain.

46% tariffs from the US - a boost for Vietnam to elevate the value chain

|

The new tax rate from the US causes Vietnamese goods to face many challenges, but this is also the time to restructure, innovate technology and elevate the value chain.

Hoai Duc District responds to illegal factory construction on agricultural land

|

The People's Committee of Hoai Duc district has just issued Official Letter No. 547 to Lao Dong Newspaper to respond to the case of illegal construction of houses and factories on agricultural land.

A project abandoned for many years in Long Bien has resumed operations

|

Hanoi - The wastewater treatment plant of Viet Hung Urban Area (Viet Hung, Long Bien) has resumed operations after many years of "lying still".

Hung Vuong Cup 2025 has no limit on foreign players, creating great attraction

|

The Hung Vuong Cup 2025 does not limit the number of foreign players on the field, creating many expectations for professional quality. Sports perspective No. 209 commented further on this issue.

Vietnam responds to the US announcement of counterpart tariffs

|

Vietnam regrets that the US announced the decision to apply counterpart tariffs on Vietnam's exports to the US.

Revealing that Vietnamese enterprises are behind the plan to exploit 4.6 tons of gold

|

A company under the Vietnam National Coal and Mineral Industries Group (TKV) aims to exploit more than 4.6 tons of gold in the years 2026 - 2030.

Breaking rocks to open a hundred billion dong road in Tuyen Quang

Việt Bắc |

Tuyen Quang - After 3 years of construction, the more than 4 km long Son Duong town bypass road still cannot be completed due to the hard rocky terrain.

Bạt đồi làm đường trăm tỉ kết nối Lạng Sơn - Thái Nguyên

Nguyễn Hoàn |

Sau 2 năm thi công, cung đường trăm tỉ Tân Tri - Nghinh Tường kết nối các xã khó khăn của tỉnh Lạng Sơn và Thái Nguyên đã hoàn thành, đưa vào sử dụng.

Hình hài tuyến đường trăm tỉ kết nối hồ Nặm Cắt tại Bắc Kạn

Lam Thanh |

Bắc Kạn - Dự án tuyến đường đi hồ Nặm Cắt có tổng mức đầu tư 226 tỉ đồng. Hiện các nhà thầu đang xẻ núi, bạt đồi thi công dự án.