On the construction site of a hundred billion dong road in a mountainous district of Thai Nguyen

NGUYỄN HOÀN |

Thai Nguyen - Right in the first days of 2025, at the construction site of the hundred-billion-dong road connecting National Highway 37 and Provincial Road 269B, contractors are rushing to construct and speed up the progress.

1
The project connecting National Highway 37 and Provincial Road (DT) 269B has a total investment of 222 billion VND, invested by the Thai Nguyen Provincial Traffic Construction Investment Project Management Board, and will be implemented in December 2023.
2
The project is designed according to the standards of a grade III mountain road. The total length of the route is 6.1 km through the communes of Xuan Phuong, Tan Kim, Tan Thanh (Phu Binh), the starting point connects the main road through Xuan Phuong commune, the end point intersects with DT.269B at Km5+450.
3
According to the reporter's records in early January 2025, after more than 1 year of implementation, the project has been basically completed. Workers and machines are urgently implementing some items, speeding up the progress.
Gh
Machinery and vehicles urgently leveled and transported soil to create a flat surface.
Mot so doan tuyen khac sau khi tien hanh san gat, dao dap nen duong, rai da xong se duoc don vi thi cong dang lu nen nen dat truoc khi tham nhua.
Some other sections, after leveling, digging, and spreading rocks, will have the ground compacted by the construction unit before asphalting.
Bbss
At some construction sites, barriers and warning signs are installed to ensure safety for people and vehicles passing through.
6
The entire route has basically been paved.
Hbdns
The collection and drainage project on both sides of the road is gradually being completed.
Gbb
Workers are building and installing an overpass at the project's starting point at the intersection with National Highway 37.
Fv
Mr. Nguyen Van Thang, a worker at the project, said: "We are currently constructing the bridge body and approach road. The road surface of the entire route is now basically finished, and people can travel. The weather is dry in the last months of the year, so construction is easy and convenient."
Gv
Talking to reporters, Mr. Nguyen Dinh Dang - Chairman of Tan Kim Commune People's Committee said that currently the section of the route passing through the commune has been paved with asphalt.
Fgh
"Currently, the project progress has reached about 90%, the more than 4 km road section through Tan Kim commune is basically completed. Some other sections are being urgently implemented, expected to be completed by February 2025. This route put into use will help improve the regional traffic infrastructure, shorten travel time and distance, and promote trade," Mr. Dang added.
NGUYỄN HOÀN
RELATED NEWS

Breaking rocks to open a hundred billion dong road in Tuyen Quang

|

Tuyen Quang - After 3 years of construction, the more than 4 km long Son Duong town bypass road still cannot be completed due to the hard rocky terrain.

U17 Japan wins AFC U17 Championship for the 5th time

|

In the early morning of May 23 (Vietnam time), U17 Japan defeated U17 China with a score of 3-2 in the 2026 AFC U17 Championship final, thereby winning the championship for the 5th time.

10 new roads to be built in Long Bien

|

Hanoi - Phase 2026 - 2030, the city will deploy the construction of 10 roads in Long Bien ward.

Gold price update morning of May 23rd: Gold rings and gold bars fall

|

Gold price update morning of May 23rd: Domestic gold prices decreased by about 400,000 VND/tael. World gold prices last night fluctuated around 4,520 USD/ounce.

Weather today May 23: Weekend, intense heat increases in the North

|

Weather today May 23, Northern region has hot sun, in some places intense hot sun with the highest temperature commonly 35 - 37 degrees C, in some places above 37 degrees C.

Solutions to help children be safe from summer drowning risks

|

In the summer, many parents let their children learn to swim not only to improve their health but also to equip them with drowning prevention skills, helping children know how to protect themselves.

Breaking rocks to open a hundred billion dong road in Tuyen Quang

Việt Bắc |

Tuyen Quang - After 3 years of construction, the more than 4 km long Son Duong town bypass road still cannot be completed due to the hard rocky terrain.

Bạt đồi làm đường trăm tỉ kết nối Lạng Sơn - Thái Nguyên

Nguyễn Hoàn |

Sau 2 năm thi công, cung đường trăm tỉ Tân Tri - Nghinh Tường kết nối các xã khó khăn của tỉnh Lạng Sơn và Thái Nguyên đã hoàn thành, đưa vào sử dụng.

Hình hài tuyến đường trăm tỉ kết nối hồ Nặm Cắt tại Bắc Kạn

Lam Thanh |

Bắc Kạn - Dự án tuyến đường đi hồ Nặm Cắt có tổng mức đầu tư 226 tỉ đồng. Hiện các nhà thầu đang xẻ núi, bạt đồi thi công dự án.