Quang Ngai City leaders talk about Thien But Park project slow to start

VIÊN NGUYỄN |

Quang Ngai - Having difficulty in capital and consuming a lot of time to review the art factors, feng shui ... is one of the reasons why the project is stagnant.

In 2017, Thien But Park Project and Thien Tan Ecological Urban Area were advised and proposed by the Department of Construction, proposed that the People's Committee of Quang Ngai Province approved the feasibility study report and the results of the contractor selection for investment in the form of BT (Construction - Transfer). However, the form of BT was later stopped, resulting in the project not being implemented.

By May 2021, the People's Committee of Quang Ngai province had canceled the investment project under the BT form and switched to implementation with budget capital.

The project is slow to be implemented, causing many consequences, the project implementation planning area is now deserted, shabby, making the urban appearance worse, becoming a "way to get" for drug addicts to inject drugs.

According to Mr. Nguyen Lam - Vice Chairman of Quang Ngai City People's Committee, through assessing the situation of social infrastructure, Quang Ngai City basically guaranteed. However, one of the lack of social infrastructure and not meeting the expectations and aspirations of the people is that urban parks are not large enough to serve the needs of entertainment and entertainment of the people.

With the above situation, over time, the province and city have tried hard and efforts to overcome this problem soon. The city has focused on directing the planning, planning, making Thien But Park Investment Project.

Nui Thien But o TP Quang Ngai hien nhech nhac, hoang tan, vi vay nguoi dan mong moi du an cong vien Thien But som duoc khoi cong. Anh: Vien Nguyen.
Thien But Mountain in Quang Ngai City is currently sloppy and ruin, so people expect Thien But Park project to be started soon. Photo: Vien Nguyen.

According to Mr. Nguyen Lam, Thien But Mountain is located in the heart of Quang Ngai City, one of the 12 landscapes of the province; This place is important in terms of landscape, history and feng shui elements of Quang Ngai City. According to the general planning project and the central subdivision planning, Thien But mountain area is oriented to build a landscape park, combined with the conservation of cultural and historical relics of the city.

With that importance, the planning project is very focused by the provincial People's Committee and the Department of Construction, carefully reviewing the art, technical and feng shui elements so that when completed, the project will be highly effective in aesthetics, meeting the requirements of socio -economic development, while ensuring feasibility when implementing investment projects. This is also the reason for taking a lot of time to complete, choose and approve.

In addition, for many years, resources from the state budget to balance and arrange the project implementation have also faced many difficulties. This is one of the main causes leading to slow implementation.

According to the leader of Quang Ngai City, at present, in order to have a basis for making investment projects, the provincial People's Committee has assigned the City People's Committee to organize the detailed planning scheme of 1/500 scale of Thien But Park. This project was approved by the People's Committee of Quang Ngai Province in Decision No. 845/QD-UBND dated December 31, 2024.

Currently, Thien But Park project has been approved by the City People's Committee in investment policy in Decision No. 704/QD-UBND dated 4.3.2025. The project is assigned to the Management Board of Construction Investment Project and Development of Land Fund as an investor. Currently, the Management Board is in the process of selecting a consulting unit to prepare a feasibility study report, as a basis for the next steps. It is expected that the project will be started construction in 2025. Thien But Park project has a total investment of about VND 800 billion.

VIÊN NGUYỄN
RELATED NEWS

The site of the nearly 1,500 billion VND dam project in Quang Ngai is deserted

|

Quang Ngai - The Tra Khuc River downstream dam project is expected to be completed in 2021, but is still unfinished, the construction site is deserted.

Confused when implementing, many key projects in Quang Ngai are sluggish

|

Many key projects in Quang Ngai province are behind schedule, causing difficulties in disbursing public investment capital, directly affecting the province's economic growth rate in 2025.

People monitor the largest park project in Quang Ngai

|

The Chairman of the People's Committee of Quang Ngai City announces the progress of the Thach Bich green park project every month for people to monitor and supervise.

G-Dragon finalizes concert schedule in Hanoi

|

The information just announced by G-Dragon has made the fan community in Vietnam " restless".

Poland sends 40,000 troops closer to the border, tensions in Eastern Europe rise to alert level

|

Poland has sent 40,000 troops closer to the border as Russia and Belarus conduct a Zapad 2025 drill, pushing tensions in Eastern Europe to an alarming level.

Da Nang plans to have a Secretary of the City Party Committee and five Deputy Secretaries for the 2025-2030 term

|

Da Nang - 75 members are expected to join the Da Nang Party Executive Committee for the 2025-2030 term, of which 73 are re-elected.

Nearly 1,600 students in the mountainous commune of Son La are still isolated due to landslides

|

Son La - More than 10 days have passed, the main road in Tuong Ha commune has not been repaired yet, thousands of students and people are still isolated.

Vietnam youth volleyball training needs a breakthrough

|

The selection and training of Vietnamese youth volleyball athletes faces many difficulties due to objective and subjective reasons.

The site of the nearly 1,500 billion VND dam project in Quang Ngai is deserted

VIÊN NGUYỄN |

Quang Ngai - The Tra Khuc River downstream dam project is expected to be completed in 2021, but is still unfinished, the construction site is deserted.

Confused when implementing, many key projects in Quang Ngai are sluggish

Viên Nguyễn |

Many key projects in Quang Ngai province are behind schedule, causing difficulties in disbursing public investment capital, directly affecting the province's economic growth rate in 2025.

People monitor the largest park project in Quang Ngai

VIÊN NGUYỄN |

The Chairman of the People's Committee of Quang Ngai City announces the progress of the Thach Bich green park project every month for people to monitor and supervise.