Resolutely answer voters when the 10,000 billion VND flood prevention project will be completed

Lê Thanh Phong |

At the meeting on September 27, many voters in Ho Chi Minh City expressed special interest in the progress of the 10,000 billion VND tidal prevention project.

Voter Doan Thi Kim Cuc (Tan Thuan ward) suggested that the authorities need to give a definitive answer about the fate of the project: "I hope the National Assembly will pay attention and clearly affirm whether to do or not to do it. If the 10,000 billion VND project is left unfinished, it would be a waste, while the city's people are still suffering from flooding."

This is a representative of the voice of voters in Ho Chi Minh City.

This question has been asked many times with many concerns, worries and expectations. From 2020 to present, at each meeting, voters have asked when the project will be completed and put into use.

Heavy rain causes flooding, people suffer, affecting their lives, activities, and economic damage. While the 10,000 billion VND flood prevention project is exposed to the sun and rain.

There have been many meetings, many answers, many commitments to remove difficulties and obstacles so that the project can be completed soon, but until now, everything is still the same.

Mr. Nguyen Hoang Anh Dung - Deputy Director of the Ho Chi Minh City Urban Infrastructure Construction Investment Project Management Board - said that the flood prevention project has completed 92% of the construction volume.

The immediate goal is to complete the two large sluices of Ben Nghe and Muong Chuoi, then complete all six sluices to put them into use in 2026.

Not to mention the percentage of completion, people clearly see that the project has not been put into operation yet, and the flooding is still complete.

People do not care about the numbers on paper, but the reality on the ground. In fact, the flood prevention project has been put into operation, a large area of Ho Chi Minh City is no longer flooded.

This meeting, voters once again hope.

The project started in 2016, if it is put into use in 2026 as Mr. Nguyen Hoang Anh Dung said, it will take 10 years.

However, it is not known whether this is a final commitment or not, the managers have promised many times, and voters have been disappointed many times.

Mr. Phan Van Mai - Chairman of the National Assembly's Economic and Financial Committee, former Chairman of the Ho Chi Minh City People's Committee - frankly admitted that he had promised this project "no less than three times" during meetings with voters.

The flood prevention project with the goal of controlling flooding for 570km2 and protecting 6.5 million residents along the Saigon River, which has been "frozen" for several years, is a huge waste. The damage caused by flooding alone cannot be fully calculated.

Respond to voters about when to complete and fulfill the commitment.

Lê Thanh Phong
RELATED NEWS

Voters in Ho Chi Minh City propose answering whether or not to continue the 10,000 billion VND flood prevention project

|

HCMC - The nearly VND10,000 billion flood prevention project will complete the two large culverts of Ben Nghe and Muong Chuoi first, then put all six culverts into operation in 2026.

The 10,000 billion VND flood prevention super project in Ho Chi Minh City has new progress

|

Ho Chi Minh City established a Working Group led by Vice Chairman of the People's Committee Bui Xuan Cuong to remove obstacles and promote a super project to prevent the flood of nearly 10,000 billion VND to the finish line.

The Government issues a resolution to remove obstacles for the 10,000 billion VND flood prevention project in Ho Chi Minh City

|

HCMC - The nearly VND10,000 billion flood prevention project and the Ring Road 2 section with a capital of more than VND2,700 billion have just been resolved by the Government to remove difficulties and obstacles.

International beauties, used cars add sparkling beauty to Da Lat streets

|

Da Lat - Da Lat City of Thousands of Flowers is more sparkling with the participation of nearly 80 international beauties and dozens of ancient cars participating in the parade through the streets.

Electricity says Ecohome Nhon Binh lacks cooperation in power generation

|

Gia Lai - Regarding the prolonged power outage at Ecohome Nhon Binh Social Housing Apartment, the Electricity sector said it has provided full support but the repair process is still very slow.

Thien Khoi FC crowned champion of the 2025 National 7-a-side Football Cup

|

Defeating Dai Tu in a dramatic final match, Thien Khoi FC became the champion of the 2025 Hyundai Thanh Cong Cup National 7-a-side Football Cup (VSC-S5).

Traffic ban on Prenn Pass to Da Lat from tomorrow afternoon, December 8

|

Lam Dong - The ban on traffic on Prenn Pass will take place from 11am to 5pm on December 8 to cut down trees at risk of falling, causing traffic insecurity.

Gia Bac Pass in Lam Dong opens to traffic after 5 days of paralysis due to serious landslides

|

Lam Dong - At 5:00 p.m. this afternoon, Gia Bac Pass officially opened the route, vehicles on National Highway 28 began traveling again after a period of paralysis due to landslides.

Voters in Ho Chi Minh City propose answering whether or not to continue the 10,000 billion VND flood prevention project

MINH QUÂN |

HCMC - The nearly VND10,000 billion flood prevention project will complete the two large culverts of Ben Nghe and Muong Chuoi first, then put all six culverts into operation in 2026.

The 10,000 billion VND flood prevention super project in Ho Chi Minh City has new progress

MINH QUÂN |

Ho Chi Minh City established a Working Group led by Vice Chairman of the People's Committee Bui Xuan Cuong to remove obstacles and promote a super project to prevent the flood of nearly 10,000 billion VND to the finish line.

The Government issues a resolution to remove obstacles for the 10,000 billion VND flood prevention project in Ho Chi Minh City

MINH QUÂN |

HCMC - The nearly VND10,000 billion flood prevention project and the Ring Road 2 section with a capital of more than VND2,700 billion have just been resolved by the Government to remove difficulties and obstacles.