behind schedule
Many tourism projects in Phong Nha "covered in tarpaulins" on golden land
|
Quang Tri - Phong Nha commune has many tourism projects in "golden land" that are slow to implement, abandoned for a long time, causing waste of resources.
Billion-dollar bridge completed but no access road due to site clearance problems
|
Quang Tri - Nhat Le 3 bridge has been basically completed but still has to "wait" when many households have not handed over the site to construct the access road to the bridge.
Hue terminates contract for bidding package worth over 114 billion VND due to slow progress
|
HUE - The contractor of the Vy Da bridge project was terminated after many warnings of slow progress.
Cam Lo - La Son expressway expansion site like a "stir-fried pan", worried about slow progress
|
Quang Tri - Under the scorching heat, workers constructing the Cam Lo - La Son expressway had to work early and at night, but the project is still behind schedule due to many obstacles.
Contractor requests postponement of nearly 200 billion VND project in Hue but is not approved
|
HUE - The contractor for the Culture and Sports Square Project worth nearly 200 billion VND proposed to extend the progress due to difficulties arising, but the investor did not approve.
Investor explains the reason for the 191 billion VND project in Nghe An being behind schedule
|
Nghe An - The investor of a project worth more than 191 billion VND in Vinh Loc ward explains the reasons for slow implementation.
Vintraco project in Nghe An worth more than 190 billion VND is behind schedule
|
Nghe An - The Vintraco project has expired and has not yet been implemented, the locality has reported to the provincial inspection team for consideration.
400 billion VND project in Da Nang disaster area, urgent on paper, messy on the ground
|
Da Nang - As an emergency reconstruction project after natural disasters, but after many years, the nearly 400 billion VND traffic road is still unfinished, causing people to face many difficulties.
Da Nang Chairman sets deadline for completion of bridge access roads
|
Da Nang - Chairman of Da Nang City People's Committee requests units to focus on removing site obstacles to soon complete access roads for bridge projects.
400 billion VND emergency traffic project in Da Nang is slow due to a series of bottlenecks
|
Da Nang - Sluggish construction contractors, loose management, and continuous changes in focal points have caused the nearly 400 billion VND traffic reconstruction project in Da Nang mountainous area to be delayed for a long time.
Stone mine "suspended" for 9 months, Gia Lai warns to replace commune leaders
|
Gia Lai - Although licensed, a quarry is still "suspended" for 9 months due to land lease procedures at the commune level.
Accelerate the construction of the final intersection on the 34 trillion VND expressway
|
Despite the lack of materials, construction units are still making efforts to accelerate the progress of the Tri Binh - Dung Quat intersection, the last intersection on the Da Nang - Quang Ngai expressway.
Gia Lai "bans" slow construction contractors amidst material price fever
|
Gia Lai - In the afternoon of April 3, Member of the Party Central Committee, Chairman of the Provincial People's Committee Pham Anh Tuan met with the Steering Committee for management, administration and price stabilization.
Gia Lai issues "ultimatum" for coastal resort project
|
Gia Lai - If the coastal resort project continues to be delayed and slow to be put into construction, it will be considered for revocation.
Series of large projects in Hue are directed to accelerate
|
HUE - Hue City leaders inspect and request to accelerate the progress of a series of key transportation, industrial, and tourism projects.