HCMC builds an intersection connecting the South with the Ben Luc - Long Thanh Expressway, with a total capital of 591 billion VND
|
HCMC - The Ben Luc - Long Thanh Expressway Intersection with National Highway 50 (Binh Chanh District) has a total capital of VND591 billion, expected to start construction at the end of 2025, and be completed in 2026.
1,500 billion VND project to expand the southern gateway of Ho Chi Minh City after more than 2 years of construction
|
HCMC - The project to expand National Highway 50 through Binh Chanh District has reached 67% of the volume, and there are still some site clearance problems affecting the construction progress.
HCMC is about to build a 4-6 lane elevated road connecting the center and the South
|
HCMC - The Binh Tien Bridge and Road Project is an elevated road 3.66 km long, 4 - 6 lanes wide, connecting Districts 6, 8, Binh Chanh, with a total investment of nearly 6,300 billion VND.
Chairman of Ho Chi Minh City assigns the task of widening the Southern road to 60 m
|
The Chairman of the Ho Chi Minh City People's Committee assigned the task of expanding Nguyen Huu Tho Street (from Nguyen Van Linh Street to Ben Luc - Long Thanh Expressway) to 60 m, accommodating 10 lanes.
The largest intersection in the South of Ho Chi Minh City officially opened
|
HCMC - The Nguyen Van Linh - Nguyen Huu Tho intersection (District 7) has removed all barriers after a year of closure to construct an underpass.
Vital bridge clears traffic congestion in southern HCMC before opening day
|
HCMC - The Phuoc Long bridge project connecting District 7 and Nha Be district, after 4 years of construction, has now completed nearly 100% of the work volume, preparing to open to traffic on December 30.
Parallel road to clear traffic jams at HCMC gateway still congested
|
HCMC - The National Highway 50 expansion project, with a total investment of more than VND1,500 billion, has achieved about 75% of its progress, but is at risk of missing the deadline due to land acquisition issues.
Ho Chi Minh City misses deadline to start construction of 3,700 billion VND bridge connecting District 7, 4 and 1
|
HCMC - The Nguyen Khoi bridge and road project worth over VND3,700 billion, connecting District 7, District 4 and District 1, could not start construction at the end of this year as planned.
Drivers excited to travel through the 830 billion VND underpass in the South of Ho Chi Minh City
|
HCMC - After 2 days of opening the HC2 Nguyen Van Linh tunnel branch (District 7), drivers are excited because traffic is more convenient and traffic congestion is reduced as before.
Ho Chi Minh City opens important underpass in District 7, bans motorbikes
|
HCMC - On the morning of October 4, the Nguyen Van Linh - Nguyen Huu Tho tunnel branch (from District 7 to Binh Chanh) opened to traffic, only allowing cars to pass, banning motorbikes and pedestrians.