Ho Chi Minh City to start a series of projects to rescue traffic jams at gateways
|
Ho Chi Minh City is about to start a series of projects to expand roads, build elevated roads, and build bridges at gateways to reduce congestion and increase regional connectivity.
Dong Nai submits elevated road project along National Highway 51, investing more than 16,400 billion VND
|
Dong Nai - The elevated road project along National Highway 51 from Vung Tau intersection to Vo Nguyen Giap road intersection with Bien Hoa - Vung Tau expressway.
The first elevated road in Ho Chi Minh City continues to postpone the opening date
|
Ho Chi Minh City - The elevated road belonging to the Ring Road 3 project, the eastern section, 14.7km long, 4 lanes, continues to postpone the opening date to June 30, instead of April 30.
The largest boulevard in the South of Ho Chi Minh City is proposed to add a 6-lane elevated road
|
Ho Chi Minh City - Nguyen Van Linh Street - the southern artery of the city is proposed to build an additional 6-lane elevated road, combined with 7 grade-separated intersections.
Ring Road 3 HCMC elevated section asphalt paved seamlessly, racing for traffic opening progress 30. 4
|
Many elevated sections of Ring Road 3 in Ho Chi Minh City have been beautifully asphalted, and contractors are focusing their efforts on completing the final part to meet the traffic opening milestone on April 30th.
Eastern HCMC area is about to reduce traffic jams thanks to the 4-lane elevated road
|
Ho Chi Minh City - The elevated road from Ho Chi Minh City - Long Thanh expressway to Tan Van intersection, 14.7km long, 4 lanes will be opened to traffic on April 30, helping to reduce traffic jams in the East.
The elevated road is nearly 7 km long, 4 lanes connecting the center of Ho Chi Minh City with the South
|
Ho Chi Minh City - Nguyen Huu Tho elevated road from Nguyen Van Linh to Ben Luc - Long Thanh expressway is nearly 7 km long, with a scale of 4 car lanes, helping to reduce traffic jams in the South.
Ho Chi Minh City accelerates the construction of 4-x6 lane elevated road connecting the center with the South
|
Ho Chi Minh City - Binh Tien bridge and road are more than 3 km long, with a scale of 4 - 6 lanes, and are required to submit a feasibility study report for approval in January.
Ho Chi Minh City Ring Road 3 urgently paves asphalt for many sections of overpasses
|
Ho Chi Minh City - At the beginning of 2026, many sections of the main elevated Ring Road 3 in Ho Chi Minh City have begun to be asphalted, marking an important milestone in progress.
Metro and elevated roads relieve congestion at Tan Son Nhat airport
|
Ho Chi Minh City will implement a series of large transportation projects such as metro, elevated roads, and expand key axes to reduce congestion and increase connectivity in the Tan Son Nhat airport area.
Technical traffic opening of nearly 15 km of Ring Road 3 overpass through the eastern urban area of Ho Chi Minh City
|
HCMC - The nearly 15 km long section of the Ho Chi Minh City Ring Road 3 overpass was technically opened to traffic on December 19, after more than two years of construction.
Current status of the two most congested roads in Ho Chi Minh City about to build an elevated road
|
HCMC - Xo Viet Nghe Tinh and Dinh Bo Linh streets at the Northeast gateway of HCMC will be expanded and an elevated road will be built, helping to eliminate constant traffic jams.
HCMC is about to build a series of elevated roads to relieve traffic jams at gateways
|
Ho Chi Minh City will build a series of elevated roads to form rapid traffic axes, with less intersection with the road below, reducing pressure on the road surface.
The shape of the elevated beltway winding through the metropolis in the East of Ho Chi Minh City
|
HCMC - 14.7 km of the Ring Road 3 overpass is being urgently completed, in order to serve the goal of opening the entire technical route on December 19.
The Traffic Department states the reason for the delay in the opening of the first elevated road in Ho Chi Minh City
|
HCMC - The 14.7 km long eastern elevated road section of Ho Chi Minh City Ring Road 3 will only be technically open to traffic on December 19, 2025, instead of officially opening as planned.