Ministries, branches and localities are responsible to the Prime Minister if they miss out, and projects are still pending

PHẠM ĐÔNG |

Ministries, branches and localities must take full responsibility to the Prime Minister if they miss out, and if there are backlogs and difficulties, they cannot be included in the report.

Politburo member, Permanent Deputy Prime Minister Nguyen Hoa Binh - Head of the Steering Committee on resolving difficulties and problems of backlogged projects (Steering Committee 751) has just signed Document No. 117/CV-BCD751 requesting ministries, branches and localities to study, review and propose solutions to remove difficulties and problems of backlogged projects on Database System 751.

The document stated that in recent times, the Government and the Prime Minister have resolutely directed ministries, branches and localities to implement solutions to completely handle long-standing projects, revive and put into operation and operation many large-scale projects, contributing to promoting socio-economic development in localities.

However, there are still many works and projects that have not been promptly resolved by all levels, sectors, agencies and units, causing long backlogs and construction stops, causing waste of state and social resources.

To focus on resolving the issue, the Permanent Deputy Prime Minister requested ministries, agencies under the Government, People's Committees of provinces and centrally run cities to continue reviewing and updating information on projects with difficulties and problems on the Database System of Steering Committee 751 (System 751).

In particular, the Government and the Prime Minister are fully responsible for any omission, projects that are still backlogged, or have difficulties and problems that are not included in the reporting list as required by Steering Committee 751.

At the same time, ministries, branches and localities should carefully study the provisions of current law and specific policies stated in Resolution No. 170/2024/QH15 (abbreviated as NQ170.

On that basis, urgently review and determine all projects with similar legal situations to NQ170, propose competent authorities to allow similar application to resolve according to each specific policy group of NQ170, synthesize and send to the Steering Committee on system 751 for a deadline of August 10, noting:

- Review only projects with difficulties and problems after having inspection, examination and judgment conclusions.

- Refer to project issues to accurately determine the legal situation similar to the case specified in NQ170, clearly stating the proposed provision of applying a special mechanism to resolve each specific project.

- Be fully responsible to the Prime Minister if there are similar difficulties and problems to projects in NQ170 after the above-mentioned deadline.

The Permanent Deputy Prime Minister requested the People's Committees of provinces and cities to establish a Working Group to review and remove difficulties and obstacles for long-standing projects in the locality directly directed by the leaders of the People's Committees of provinces and cities.

Thereby, studying the viewpoints, principles, and legal situations to review and propose the project to apply the mechanism of removing difficulties and obstacles as prescribed in NQ170, Conclusion No. 77-KL/TW of the Politburo.

At the same time, build a timely coordination mechanism with Steering Committee 751 to propose solutions to remove difficulties and obstacles beyond authority; ensure progress, accurate data information, and report the results of the resolution promptly to the Prime Minister and Steering Committee 751.

PHẠM ĐÔNG
RELATED NEWS

Permanent Deputy Prime Minister works with Dong Nai to remove difficulties and obstacles for projects

|

Dong Nai province has nearly 260 projects facing difficulties and obstacles that need to be resolved.

Handling 2,981 backlog projects, not allowing mistakes to overlap, getting one job at a time

|

The Prime Minister emphasized that in handling 2,981 backlog projects, one thing must be done without another and requested the Central Inspection Committee to continue monitoring.

Authority to resolve 1,533 long-standing backlog projects

|

Of the 1,533 projects that are still pending and facing difficulties and obstacles, there are 338 public investment projects, 1,126 non-budget investment projects and 69 PPP projects.

People release buffaloes and crawl to the edge of the Vinh Hao - Phan Thiet expressway

|

Lam Dong - From the locations where the barbed wire fence was cut, people released buffaloes and cows into the corridor next to the Vinh Hao - Phan Thiet expressway.

It's a bit of a bit of a bit of a bit of a bit of a bit.

Vinh Chau purple onions in season, rural workers have more jobs

|

Can Tho - Vinh Chau is not only famous for its purple onion fields but also creates stable livelihoods for thousands of local workers.

US economy accelerates in 2025, opening a brighter growth period in 2026

|

The US economy recorded strong growth in 2025, GDP broke through in the third quarter and consumption maintained its momentum, creating a positive foundation for the outlook for 2026.

How Thanh Nhan deceived the U23 Korean goalkeeper

|

Striker Thanh Nhan took the decisive penalty to bring home a bronze medal for U23 Vietnam at the 2026 AFC U23 Championship.

Border" beauty: I also love myself and instinctively like chairman My Trinh

|

In "Cafe chieu thu 7", actress Huyen Trang (as My Trinh in "Lan ranh") shared about her career and views on happiness.

It's a bit of a bit of a bit of a bit of a bit of a bit.

Permanent Deputy Prime Minister works with Dong Nai to remove difficulties and obstacles for projects

HÀ ANH CHIẾN |

Dong Nai province has nearly 260 projects facing difficulties and obstacles that need to be resolved.

Handling 2,981 backlog projects, not allowing mistakes to overlap, getting one job at a time

PHẠM ĐÔNG |

The Prime Minister emphasized that in handling 2,981 backlog projects, one thing must be done without another and requested the Central Inspection Committee to continue monitoring.

Authority to resolve 1,533 long-standing backlog projects

PHẠM ĐÔNG |

Of the 1,533 projects that are still pending and facing difficulties and obstacles, there are 338 public investment projects, 1,126 non-budget investment projects and 69 PPP projects.