The Ministry of Agriculture and Environment must review responsibilities

PHẠM ĐÔNG |

The Prime Minister assigned the Ministry of Agriculture and Environment to review and handle the responsibility for the slow implementation of the construction of the Long Thanh Airport Plant Quarantine Station.

The Government Office has just issued Document No. 1783/VPCP-CN dated March 6, 2025, conveying the opinion of Prime Minister Pham Minh Chinh on reviewing the responsibility for slow implementation of the project to build the Plant and Animal Quarantine Station, Long Thanh International Airport (Long Thanh Airport).

Regarding the review of responsibilities for the delay in implementing the project to build the Plant and Animal Quarantine Station and Long Thanh Airport Phase 1, the Prime Minister assigned the Ministry of Agriculture and Environment to review and handle responsibilities similar to those implemented by the Ministry of Transport (now the Ministry of Construction) and report in Document No. 25/BGTVT-TCCB dated February 19, 2025.

The Long Thanh airport project includes 4 component projects: Component project 1 (headquarters of state agencies, including: Customs, Border Guard, Local Police, Animal/Property Health Quarantine, Airport Authority); Component project 2 (works serving flight management); Component project 3 (essential works); Component project 4 (land service works).

The Government's electronic information portal said that information at the meeting on the implementation of the Long Thanh International Airport Project held on January 25, 2025 chaired by the Prime Minister, for component project 1, the Ministry of Agriculture and Rural Development (now the Ministry of Agriculture and Environment) has not yet arranged capital and has not completed procedures to approve the investment policy for the headquarters item of the agency for quarantine/ vat chat.

The Prime Minister requested the Ministry of Agriculture and Rural Development (now the Ministry of Agriculture and Environment) and relevant agencies to review, clarify responsibilities and handle officials responsible for the delay in allocating capital for the headquarters of the dynamic quarantine station/ vat at component project 1.

At the same time, the Prime Minister requested the Ministry to be more urgent and stronger in implementing the project of the mobile/ vatal quarantine station headquarters under component project 1 (other agencies have completed).

Previously, in Document No. 1774/VPCP-CN dated March 5, 2025, the Prime Minister also requested the Ministry of Construction to learn from experience in the delay in organizing the implementation of assigned tasks on Component Project 4, Long Thanh Airport Project Phase 1.

PHẠM ĐÔNG
RELATED NEWS

Prime Minister requests Ministry of Construction to learn from experience

|

The Prime Minister requested the Ministry of Construction to learn from experience in performing assigned tasks for component project 4, Long Thanh airport.

The Ministry of Agriculture and Environment has 10 Deputy Ministers and 30 units

|

From March 1, the Ministry of Agriculture and Environment has 10 deputy ministers and 30 units after the arrangement and merger.

Shortening the time to complete the Long Thanh airport passenger terminal

|

The Deputy Prime Minister hopes to shorten the completion time of the package, which is considered the "heart" of Long Thanh airport, to ensure quality and economic efficiency.

Mr. Maduro escorted by the US by helicopter to court

|

On the morning of January 5, Venezuelan President Nicolas Maduro was preparing to enter a hearing in New York, on drug charges.

Electricity consumption deviates from GDP growth: Statistics Department explains the reason

|

GDP in 2025 grew at a high level of 8.02%, but the total commercial electricity output of the entire system only increased by 4.9%, much lower than the previous year.

Suoi Sap is encroached upon, people worry about landslides

|

Son La - People in Long Sap commune are worried about the situation of soil and rock encroachment on the Sap stream, causing the flow to narrow, risk of landslides, and unsafety during the rainy and flood season.

Houses in Hanoi emit many explosions and then catch fire, 3 people injured and killed

|

Hanoi - The 2nd floor of a house in a residential area suddenly caught fire after many loud explosions. Initial determination shows 3 casualties.

Athletes receive increased salaries and nutrition

|

The new Government Decree adjusts the spending level on salary, training wages, nutrition and achievement allowances for coaches and athletes.

Prime Minister requests Ministry of Construction to learn from experience

PHẠM ĐÔNG |

The Prime Minister requested the Ministry of Construction to learn from experience in performing assigned tasks for component project 4, Long Thanh airport.

The Ministry of Agriculture and Environment has 10 Deputy Ministers and 30 units

PHẠM ĐÔNG |

From March 1, the Ministry of Agriculture and Environment has 10 deputy ministers and 30 units after the arrangement and merger.

Shortening the time to complete the Long Thanh airport passenger terminal

PHẠM ĐÔNG |

The Deputy Prime Minister hopes to shorten the completion time of the package, which is considered the "heart" of Long Thanh airport, to ensure quality and economic efficiency.