The Ministry of Agriculture and Environment must review responsibilities

PHẠM ĐÔNG |

The Prime Minister assigned the Ministry of Agriculture and Environment to review and handle the responsibility for the slow implementation of the construction of the Long Thanh Airport Plant Quarantine Station.

The Government Office has just issued Document No. 1783/VPCP-CN dated March 6, 2025, conveying the opinion of Prime Minister Pham Minh Chinh on reviewing the responsibility for slow implementation of the project to build the Plant and Animal Quarantine Station, Long Thanh International Airport (Long Thanh Airport).

Regarding the review of responsibilities for the delay in implementing the project to build the Plant and Animal Quarantine Station and Long Thanh Airport Phase 1, the Prime Minister assigned the Ministry of Agriculture and Environment to review and handle responsibilities similar to those implemented by the Ministry of Transport (now the Ministry of Construction) and report in Document No. 25/BGTVT-TCCB dated February 19, 2025.

The Long Thanh airport project includes 4 component projects: Component project 1 (headquarters of state agencies, including: Customs, Border Guard, Local Police, Animal/Property Health Quarantine, Airport Authority); Component project 2 (works serving flight management); Component project 3 (essential works); Component project 4 (land service works).

The Government's electronic information portal said that information at the meeting on the implementation of the Long Thanh International Airport Project held on January 25, 2025 chaired by the Prime Minister, for component project 1, the Ministry of Agriculture and Rural Development (now the Ministry of Agriculture and Environment) has not yet arranged capital and has not completed procedures to approve the investment policy for the headquarters item of the agency for quarantine/ vat chat.

The Prime Minister requested the Ministry of Agriculture and Rural Development (now the Ministry of Agriculture and Environment) and relevant agencies to review, clarify responsibilities and handle officials responsible for the delay in allocating capital for the headquarters of the dynamic quarantine station/ vat at component project 1.

At the same time, the Prime Minister requested the Ministry to be more urgent and stronger in implementing the project of the mobile/ vatal quarantine station headquarters under component project 1 (other agencies have completed).

Previously, in Document No. 1774/VPCP-CN dated March 5, 2025, the Prime Minister also requested the Ministry of Construction to learn from experience in the delay in organizing the implementation of assigned tasks on Component Project 4, Long Thanh Airport Project Phase 1.

PHẠM ĐÔNG
RELATED NEWS

Prime Minister requests Ministry of Construction to learn from experience

|

The Prime Minister requested the Ministry of Construction to learn from experience in performing assigned tasks for component project 4, Long Thanh airport.

The Ministry of Agriculture and Environment has 10 Deputy Ministers and 30 units

|

From March 1, the Ministry of Agriculture and Environment has 10 deputy ministers and 30 units after the arrangement and merger.

Shortening the time to complete the Long Thanh airport passenger terminal

|

The Deputy Prime Minister hopes to shorten the completion time of the package, which is considered the "heart" of Long Thanh airport, to ensure quality and economic efficiency.

Cars parked rampant on Tang Bat Ho street causing traffic obstruction

|

Hanoi - Traffic police will strengthen patrols and handle the situation of cars stopping and parking in violation of regulations on Tang Bat Ho street.

16th National Assembly deputies candidates meet with voters in Bac Ninh

|

Candidates for National Assembly Deputies of the 16th term meet with voters at constituency No. 3, Bac Ninh province.

Tan Van intersection, the largest on Ring Road 3 in Ho Chi Minh City, is about to open to traffic, reducing congestion in the East

|

Ho Chi Minh City - Tan Van intersection, the largest of the Ho Chi Minh City Ring Road 3 project with a total capital of more than 1,800 billion VND, is being accelerated and is expected to open to traffic on June 30.

Holiday schedule for Hung Kings Commemoration Day 2026 and occasion April 30 - May 1

|

In 2026, the holiday schedule for the Hung Kings Commemoration Day and the occasion April 30 - May 1 for workers has been determined according to the provisions of the Labor Code.

Thanh Hoa Department of Education and Training concludes the case of teachers of To Hien Thanh High School correcting scores

|

Thanh Hoa - The Department of Education and Training (GDĐT) of the province has the results of inspection and verification of the case of amending semester exam scores that occurred at To Hien Thanh High School.

Prime Minister requests Ministry of Construction to learn from experience

PHẠM ĐÔNG |

The Prime Minister requested the Ministry of Construction to learn from experience in performing assigned tasks for component project 4, Long Thanh airport.

The Ministry of Agriculture and Environment has 10 Deputy Ministers and 30 units

PHẠM ĐÔNG |

From March 1, the Ministry of Agriculture and Environment has 10 deputy ministers and 30 units after the arrangement and merger.

Shortening the time to complete the Long Thanh airport passenger terminal

PHẠM ĐÔNG |

The Deputy Prime Minister hopes to shorten the completion time of the package, which is considered the "heart" of Long Thanh airport, to ensure quality and economic efficiency.