The Ministry of Agriculture and Environment must review responsibilities

PHẠM ĐÔNG |

The Prime Minister assigned the Ministry of Agriculture and Environment to review and handle the responsibility for the slow implementation of the construction of the Long Thanh Airport Plant Quarantine Station.

The Government Office has just issued Document No. 1783/VPCP-CN dated March 6, 2025, conveying the opinion of Prime Minister Pham Minh Chinh on reviewing the responsibility for slow implementation of the project to build the Plant and Animal Quarantine Station, Long Thanh International Airport (Long Thanh Airport).

Regarding the review of responsibilities for the delay in implementing the project to build the Plant and Animal Quarantine Station and Long Thanh Airport Phase 1, the Prime Minister assigned the Ministry of Agriculture and Environment to review and handle responsibilities similar to those implemented by the Ministry of Transport (now the Ministry of Construction) and report in Document No. 25/BGTVT-TCCB dated February 19, 2025.

The Long Thanh airport project includes 4 component projects: Component project 1 (headquarters of state agencies, including: Customs, Border Guard, Local Police, Animal/Property Health Quarantine, Airport Authority); Component project 2 (works serving flight management); Component project 3 (essential works); Component project 4 (land service works).

The Government's electronic information portal said that information at the meeting on the implementation of the Long Thanh International Airport Project held on January 25, 2025 chaired by the Prime Minister, for component project 1, the Ministry of Agriculture and Rural Development (now the Ministry of Agriculture and Environment) has not yet arranged capital and has not completed procedures to approve the investment policy for the headquarters item of the agency for quarantine/ vat chat.

The Prime Minister requested the Ministry of Agriculture and Rural Development (now the Ministry of Agriculture and Environment) and relevant agencies to review, clarify responsibilities and handle officials responsible for the delay in allocating capital for the headquarters of the dynamic quarantine station/ vat at component project 1.

At the same time, the Prime Minister requested the Ministry to be more urgent and stronger in implementing the project of the mobile/ vatal quarantine station headquarters under component project 1 (other agencies have completed).

Previously, in Document No. 1774/VPCP-CN dated March 5, 2025, the Prime Minister also requested the Ministry of Construction to learn from experience in the delay in organizing the implementation of assigned tasks on Component Project 4, Long Thanh Airport Project Phase 1.

PHẠM ĐÔNG
RELATED NEWS

Prime Minister requests Ministry of Construction to learn from experience

|

The Prime Minister requested the Ministry of Construction to learn from experience in performing assigned tasks for component project 4, Long Thanh airport.

The Ministry of Agriculture and Environment has 10 Deputy Ministers and 30 units

|

From March 1, the Ministry of Agriculture and Environment has 10 deputy ministers and 30 units after the arrangement and merger.

Shortening the time to complete the Long Thanh airport passenger terminal

|

The Deputy Prime Minister hopes to shorten the completion time of the package, which is considered the "heart" of Long Thanh airport, to ensure quality and economic efficiency.

U17 Vietnam beat U17 Singapore in the U17 Asian qualifiers

|

U17 Vietnam won 6-0 against U17 Singapore in the opening match of the 2026 U17 Asian qualifiers.

National Highways 1A and 29 in Dak Lak have been opened to traffic but essential goods are still locally scarce

|

Dak Lak - National Highways 1A and 29 have been opened to traffic to serve the transportation needs of the people. However, some essential goods are still locally scarce.

High tide continues to rise in Ho Chi Minh City, many people have to stay vigil and prevent water

|

HCMC - On the evening of November 22, the high tide rose, many households had to stay up watching over the planks and sandbags to prevent water from flooding into their homes.

Deputy security team in Gia Lai rushed into the fierce flood, saving people struggling

|

Gia Lai - Deputy Head of the Security and Order Team of Duong Thien village Nguyen Tan Diep promptly rushed out into the flood, saving the lives of people about to drown in the rushing water.

Baby born safely at flood shelter in Nha Trang

|

Khanh Hoa - The medical team of the Provincial General Hospital has just successfully given birth to a pregnant woman at a temporary hotel in Nha Trang ward.

Prime Minister requests Ministry of Construction to learn from experience

PHẠM ĐÔNG |

The Prime Minister requested the Ministry of Construction to learn from experience in performing assigned tasks for component project 4, Long Thanh airport.

The Ministry of Agriculture and Environment has 10 Deputy Ministers and 30 units

PHẠM ĐÔNG |

From March 1, the Ministry of Agriculture and Environment has 10 deputy ministers and 30 units after the arrangement and merger.

Shortening the time to complete the Long Thanh airport passenger terminal

PHẠM ĐÔNG |

The Deputy Prime Minister hopes to shorten the completion time of the package, which is considered the "heart" of Long Thanh airport, to ensure quality and economic efficiency.