Can Tho - Ca Mau Expressway must be inaugurated by December 19 at the latest

NHẬT HỒ |

Ca Mau - Inspecting the Can Tho - Ca Mau expressway, the Prime Minister directed that the entire route must be inaugurated by December 19, 2025 at the latest.

On the afternoon of April 20, at the IC12 intersection in Ho Thi Ky commune and the IC10 intersection in Tan Phu commune, Thoi Binh district, Ca Mau province, Prime Minister Pham Minh Chinh and the working delegation surveyed the progress of the Can Tho - Ca Mau expressway project.

Thu tuong Chinh phu Pham Minh Chinh den cong truong kiem tra tien do cao toc Can Tho - Ca Mau. Anh: Nhat Ho
Prime Minister Pham Minh Chinh visited the construction site to inspect the progress of the Can Tho - Ca Mau expressway. Photo: Nhat Ho

Reporting to the Prime Minister and the delegation, the Ministry of Construction said that up to now, contractors have mobilized 183 constructions, 971 machinery and equipment, 3,000 manpower, organized construction of overtime, construction output reached 66% of the plan (4% slow compared to expected). In particular, the route has completed the load of 74.9km (reaching 89.84%), the bridge part has implemented 95/95 bridges on the main route, meeting the progress.

Regarding disbursement, the accumulated disbursement to date has reached 15,778/22,222 billion VND of allocated capital (reaching 71%.

Also according to the report of the Ministry of Construction, since December 15, 2024, after the Prime Minister's meeting with ministries, branches, localities and instructions to remove difficulties and obstacles, the project's construction progress has had significant changes. Difficulties in materials have been resolved by localities, output has increased, 3.1 million m3 of sand and 0.7 million m3 of stone have been gathered, and the loading work has increased by 50.5km.

Cong trinh cao toc Can Tho - Ca Mau dang thi cong. Anh: Nhat Ho
The Can Tho - Ca Mau expressway project is under construction. Photo: Nhat Ho

Reporting to Prime Minister Pham Minh Chinh, the leader of Ca Mau province said that according to preliminary estimates, to clear the expressway section from Ca Mau city to Dat Mui to connect with Hon Khoai Port cluster in the future, Ca Mau will only try to get about 1,000 billion VND, the remaining about 1,000 billion VND must rely on support from the Central Government.

Directing at the construction site, the Prime Minister proposed to inaugurate it on December 19, 2025. To achieve this, it is necessary to construct more quickly, be more determined, and focus all resources to complete the entire route.

Thu tuong Chinh phu chi dao phai khanh thanh toan tuyen cao toc Can Tho - Ca Mau vao ngay 19.12.2025. Anh: Nhat Ho
The Prime Minister directed the inauguration of the entire Can Tho - Ca Mau expressway on December 19, 2025. Photo: Nhat Ho

The Prime Minister also suggested that when there are highways, the locality should put them into operation most effectively, which is to develop the economy, education, especially tourism. Regarding the expressway from Ca Mau city to Dat Mui, the Prime Minister agreed with Ca Mau's proposal on land clearance funding.

The Can Tho - Ca Mau expressway project has a main route length of 110.85km (through Can Tho city is 0.6km, Hau Giang province is 63.65km, Bac Lieu province is 7.7km, Kien Giang province is 17km, Ca Mau province is 21.9km) and 25.85km connecting route. The project is divided into 2 component projects including the Can Tho - Hau Giang section and the Hau Giang - Ca Mau section invested by the My Thuan Project Management Board, with a scale of 4 lanes, a total investment of VND 27,523 billion. The project started on January 1, 2023, and is scheduled to be completed by the end of 2025.

NHẬT HỒ
TIN LIÊN QUAN

Initial information on the dead rice crop next to the Can Tho - Ca Mau expressway

|

Hau Giang - In the area, there are 49 households affected with a total rice growing area of over 21 hectares, located on both sides of the Can Tho - Ca Mau expressway under construction.

50 days and nights to speed up the construction of the Can Tho - Ca Mau expressway

|

After 2 years of implementing the Can Tho - Ca Mau expressway, the shape of the project has begun to appear clearly.

Can Tho - Ca Mau Expressway seen from above has gradually taken shape

|

Can Tho - Ca Mau Expressway has completed the handover of the entire route, reaching 100%. Construction has reached about 58%.

"Sleepless" days and nights with Can Tho - Ca Mau expressway during Tet

|

Can Tho - In the days leading up to Lunar New Year 2025, engineers and workers are still working tirelessly day and night to construct the Can Tho - Ca Mau expressway.

Construction of Can Tho - Ca Mau Expressway day and night during Tet

|

While the whole country is busy preparing for Tet, engineers and workers are still working hard day and night on the Can Tho - Ca Mau expressway.

Can Tho - Ca Mau Expressway continues to be paved with asphalt concrete

|

Can Tho - On January 2-3, 2025, the Can Tho - Ca Mau expressway continued to be paved with asphalt concrete with a length of 800m.

Can Tho - Ca Mau Expressway marks 2 years since construction began

|

After 2 years of construction, Can Tho - Ca Mau expressway has reached 56% progress and has paved the first meters of asphalt concrete.

Prime Minister sets deadline for completion of Can Tho - Ca Mau expressway

|

Prime Minister Pham Minh Chinh requested the Can Tho - Ca Mau expressway to be completed before December 31, 2025.

Initial information on the dead rice crop next to the Can Tho - Ca Mau expressway

TẠ QUANG - YẾN PHƯƠNG |

Hau Giang - In the area, there are 49 households affected with a total rice growing area of over 21 hectares, located on both sides of the Can Tho - Ca Mau expressway under construction.

50 days and nights to speed up the construction of the Can Tho - Ca Mau expressway

Tạ Quang |

After 2 years of implementing the Can Tho - Ca Mau expressway, the shape of the project has begun to appear clearly.

Can Tho - Ca Mau Expressway seen from above has gradually taken shape

Tạ Quang |

Can Tho - Ca Mau Expressway has completed the handover of the entire route, reaching 100%. Construction has reached about 58%.

"Sleepless" days and nights with Can Tho - Ca Mau expressway during Tet

TẠ QUANG - YẾN PHƯƠNG |

Can Tho - In the days leading up to Lunar New Year 2025, engineers and workers are still working tirelessly day and night to construct the Can Tho - Ca Mau expressway.

Construction of Can Tho - Ca Mau Expressway day and night during Tet

Tạ Quang - Yến Phương |

While the whole country is busy preparing for Tet, engineers and workers are still working hard day and night on the Can Tho - Ca Mau expressway.

Can Tho - Ca Mau Expressway continues to be paved with asphalt concrete

Tạ Quang |

Can Tho - On January 2-3, 2025, the Can Tho - Ca Mau expressway continued to be paved with asphalt concrete with a length of 800m.

Can Tho - Ca Mau Expressway marks 2 years since construction began

Tạ Quang |

After 2 years of construction, Can Tho - Ca Mau expressway has reached 56% progress and has paved the first meters of asphalt concrete.

Prime Minister sets deadline for completion of Can Tho - Ca Mau expressway

PHẠM ĐÔNG |

Prime Minister Pham Minh Chinh requested the Can Tho - Ca Mau expressway to be completed before December 31, 2025.