Proposal to increase more than 86,000 billion VND for the Lao Cai - Hanoi - Hai Phong railway line

Tô Thế |

The Government proposes to adjust and increase more than 86,000 billion VND of investment capital for the Lao Cai - Hanoi - Hai Phong railway line.

Implementing the program of the First Extraordinary Session, on the morning of August 6, under the direction of Member of the Party Central Committee, Vice Chairman of the National Assembly Nguyen Hong Dien, the National Assembly listened to the Submission and Appraisal Report on adjusting the investment policy of the Lao Cai - Hanoi - Hai Phong railway line construction investment project (referred to as the Project - PV).

Authorized by the Prime Minister, Member of the Party Central Committee, Minister of Construction Tran Hong Minh said that the adjustment of the Project to be consistent with the strategy, socio-economic development plan and related planning has been approved by competent authorities.

According to the content of the Submission, based on updating the scope, scale, volume, unit price, exchange rate and policy, the preliminary total investment of the Project is 289,339 billion VND, an increase of 86,108 billion VND compared to the preliminary total investment approved by the National Assembly.

In which, construction and equipment costs increased by 51,210 billion VND; Compensation, support, and resettlement costs increased by 34,849 billion VND; Project management costs, construction investment consulting costs, and other costs increased by about 163 billion VND; contingency costs decreased by 114 billion VND.

sss
Proposal to increase more than 86,000 billion VND to build the Lao Cai - Hanoi - Hai Phong railway. Photo: Media.quochoi.vn

According to Minister Tran Hong Minh, the adjustment of the investment policy of the Project focuses on updating the scope, investment scale, type of pulling power, total investment and economic efficiency indicators to be consistent with the new plan and actual exploitation needs.

The content of the Submission clearly states that the investment scope is adjusted in the direction of adding 8.4km of the Yen Vien - Gia Lam section, and at the same time changing the location of the North passenger hub station from Yen Vien to Gia Lam. The adjustment is to ensure compliance with the Hanoi Capital Master Plan with a 100-year vision and the newly adjusted railway network plan.

Along with that, the project adjusts the name of the Nam Hai Phong - Lach Huyen section from the main line to a branch line to be consistent with the newly adjusted railway network plan and the transport operation organization plan; and at the same time adds 2 branches connecting the existing railway system to the stations of the Lao Cai - Hanoi - Hai Phong railway line.

The project proposes to adjust the scale of the section from Bac Hong station to Nam Hai Phong station from the phased investment plan for single roads to investing in completing double roads.

The updated forecast results show that if investment continues according to the phasing plan, investment preparation procedures must be carried out by 2038, upgrading to a double-track road must be implemented by 2041, and the double-track road must be put into operation by 2045.

According to the drafting agency, the phasing of investment is no longer appropriate because this section of the route is accompanied by a corridor with the expressway to Gia Binh International Airport and the Hanoi - Quang Ninh high-speed railway line that has just been decided on investment policy, making the expansion from single road to double road later technically unfeasible.

In addition, the section from Lac Dao station to Nam Hai Phong station passes through an area with thick weak soil. If invested in a phased manner, phase 2 construction may disrupt the foundation, cause subsidence and affect the operational safety of the first route.

According to calculations, investing in double roads immediately will reduce the demand for use of about 115ha of land, save 12,587 billion VND compared to the phased plan, shorten passenger travel time by about 14 minutes, bring economic benefits of about 50 billion VND per year, and at the same time eliminate risks arising during operation when building the second road.

Regarding the type of traction, the drafting agency proposed branch lines connecting seaports that do not use electric traction but use diesel locomotives that are already in the approved investment policy. It is expected that by 2045, they will switch to using clean energy locomotives.

sss
Delegates listen to the submission and project report. Photo: Media. quochoi. vn

Appraising the adjustment of the investment policy of the Project, the Economic and Financial Committee believes that investing in completing the double-track road right in the 2026 - 2030 period will significantly increase the demand for public investment capital.

At the same time, the thẩm tra agency noted that the preliminary adjusted total investment is very large compared to the policy decided by the National Assembly.

Therefore, the Committee proposed to continue reviewing the basis for determining the total investment; complete the forecast of transport demand, update the efficiency indicators after adjustment and assess the capital recovery capacity and exploitation efficiency to ensure the long-term investment efficiency of the project.

Tô Thế
RELATED NEWS

Plan to arrange cadres and headquarters when establishing Quang Ninh and Bac Ninh cities

|

The project to establish Quang Ninh city and Bac Ninh city is being submitted to the National Assembly for comments.

Land recovery for more than 1,100 households to serve the Lao Cai - Hanoi - Hai Phong railway project

|

Hai Phong - August 1, Kien Minh Commune People's Committee announced the policy of land recovery to implement the Lao Cai - Hanoi - Hai Phong railway line construction investment project.

Accelerate resettlement area for Lao Cai - Hanoi - Hai Phong railway project

|

To ensure the progress of the Lao Cai - Hanoi - Hai Phong railway project, localities are focusing on completing site clearance and building 11 resettlement areas.

Keeping street names in Ho Chi Minh City, a problem of preserving urban culture

|

After the merger, Ho Chi Minh City has 782 streets with duplicate names and numbers. Behind the seemingly repeated names are the history, lifestyle and personal memories of each community. Therefore, reviewing street names is not only a management story but also a problem of preserving urban culture.

Colonel Trinh Khac Cuong becomes Director of Lao Cai Provincial Police

|

Lao Cai - On the morning of August 10, the Provincial Police organized a ceremony to announce and announce the decisions of the Minister of Public Security on personnel work.

Indonesian experts predict Vietnam and Thailand to enter the ASEAN Cup 2026 final

|

Indonesian football expert Faris Ruswandi assesses that Vietnam and Thailand are likely to win tickets to the ASEAN Cup 2026 final.

Commune-level health stations in Gia Lai sharply reduced, many stations lack personnel

|

Gia Lai reduced 238 health stations after arrangement, while the number of people served by each station increased nearly 3 times.

House cracked due to landslide, households in Thanh Hoa cannot handle it due to electric poles

|

Thanh Hoa - Landslides have caused house cracks and peeling tiles for more than a year, but households have not been able to handle it due to electric poles on the hill.

Plan to arrange cadres and headquarters when establishing Quang Ninh and Bac Ninh cities

Tô Thế |

The project to establish Quang Ninh city and Bac Ninh city is being submitted to the National Assembly for comments.

Land recovery for more than 1,100 households to serve the Lao Cai - Hanoi - Hai Phong railway project

Theo Cổng TTĐT TP Hải Phòng |

Hai Phong - August 1, Kien Minh Commune People's Committee announced the policy of land recovery to implement the Lao Cai - Hanoi - Hai Phong railway line construction investment project.

Accelerate resettlement area for Lao Cai - Hanoi - Hai Phong railway project

An Vi |

To ensure the progress of the Lao Cai - Hanoi - Hai Phong railway project, localities are focusing on completing site clearance and building 11 resettlement areas.