Agree to expand the entire North-South expressway in the East under the PPP method

PHẠM ĐÔNG |

The Deputy Prime Minister agreed to the plan to expand the entire North-South expressway in the East; requested that before August 4, the Prime Minister be informed of the expansion plan.

The Government Office has just issued Notice No. 391/TB-VPCP dated July 31, 2025, concluding the conclusion of Deputy Prime Minister Tran Hong Ha at the meeting on research and investment in expanding the sections of the North - South expressway in the East under the public-private partnership (PPP) method.

The notice clearly stated that in Official Dispatch No. 16/CD-TTg dated February 21, 2024, the Prime Minister assigned the Minister of Transport (now the Ministry of Construction) to urgently study investment plans and upgrade invested expressways according to the scale of the phased expressway to reach the full scale, in accordance with design standards.

Deputy Prime Minister Tran Hong Ha chaired two meetings on researching investment in expanding the North-South expressway sections in the East under the public-private partnership method, directing the Ministry of Construction to study optimal and feasible options to avoid waste.

The Deputy Prime Minister acknowledged that the Ministry of Construction, the Ministry of Finance and the Ministry of Justice have implemented the direction of the Government leaders, proposing an investment plan to expand the North-South expressway in the East; the proposed plan of the Ministry of Finance and the Ministry of Construction is basically a consensus (divided into 2 investment projects under the public-private partnership method), but there are still differences in the investment phasing plan.

At the same time, the implementation of legal regulations in cases of PPP-style expansionary investment for public investment projects has different opinions.

The Deputy Prime Minister agreed with the proposal of the Ministry of Construction on the expansion of the entire North-South expressway in the East; in which, the Ministry of Construction worked with investors of 3 component projects that have been implemented under the PPP method to study the expansion investment plan.

For 15 public investment component projects, the Ministry of Construction will preside over and coordinate with relevant agencies to carry out investment preparation work under the PPP method.

The Deputy Prime Minister assigned the Ministry of Construction to prepare a report to the Prime Minister before August 4, 2025 on the expansion investment plan, clarifying the political basis, legal basis, economic basis, practical basis, planning, regulations, and standards; proposing an optimal investment plan, specific mechanisms and policies (if any) to be able to implement as soon as possible.

In case of implementing investment phasing, there needs to be an argument and clarify the reasons. Along with the proposed plan, there needs to be a specific and feasible implementation plan (from the project preparation stage including preparation, appraisal, approval; organization of investor selection; construction, completion progress) to ensure the completion of all investment and expansion in the period of 2026-2030.

PHẠM ĐÔNG
RELATED NEWS

20 inspections by the Prime Minister and Deputy Prime Minister to accelerate the progress of 3,000 km of expressway

|

The Prime Minister requested to continue accelerating, making a breakthrough to strive to have 2,476 km of expressway by August 19 and exceed the target of 3,000 km of expressway by the end of 2025.

Racing against time, resolutely completing the target of 3,000km of highway

|

The Prime Minister emphasized the spirit of racing against time, only discussing work, not retreating, and resolutely completing the goal of having at least 3,000km of expressway by the end of 2025.

Foreign car accessories without sub-labels flood the market

|

Many imported car accessories are being publicly sold on the market even though there are no invoices or documents proving their origin.

Rainstorms cover many areas of Ho Chi Minh City, flooding some roads

|

On the evening of June 11, convective clouds developed strongly, causing widespread thunderstorms in many wards and communes in Ho Chi Minh City.

Finishing the Math exam of the 2026 High School Exam: Many candidates are confident of getting 8-10 points

|

Ho Chi Minh City - At the end of the first day of the 2026 high school exam, many candidates assessed that the Math exam was differentiated, but still confidently achieved high scores, even absolute.

20 inspections by the Prime Minister and Deputy Prime Minister to accelerate the progress of 3,000 km of expressway

PHẠM ĐÔNG |

The Prime Minister requested to continue accelerating, making a breakthrough to strive to have 2,476 km of expressway by August 19 and exceed the target of 3,000 km of expressway by the end of 2025.

Racing against time, resolutely completing the target of 3,000km of highway

PHẠM ĐÔNG |

The Prime Minister emphasized the spirit of racing against time, only discussing work, not retreating, and resolutely completing the goal of having at least 3,000km of expressway by the end of 2025.

Thủ tướng yêu cầu bàn giao mặt bằng cao tốc Bắc - Nam phía Đông trong quý 2

PHẠM ĐÔNG |

Thủ tướng Chính phủ yêu cầu bí thư, chủ tịch UBND các tỉnh tập trung chỉ đạo, hoàn thành bàn giao mặt bằng dự án cao tốc Bắc - Nam phía Đông giai đoạn 2021-2025, 2 dự án đường vành đai và 3 dự án cao tốc trục Đông – Tây trong quý II/2024.