No change in target to complete Long Thanh airport by 2025

HÀ ANH CHIẾN |

Dong Nai - Prime Minister Pham Minh Chinh and the Central working delegation extended New Year greetings, presented gifts and inspected the progress of the Long Thanh airport project.

On the morning of February 1 (the 4th day of the Lunar New Year), after giving the order to start the construction of the Ho Chi Minh City - Thu Dau Mot - Chon Thanh expressway project, Prime Minister Pham Minh Chinh inspected the progress of the Long Thanh airport project (Dong Nai).

Attending the Central delegation were Deputy Prime Minister Tran Hong Ha and leaders of relevant ministries and branches.

At the Long Thanh airport project construction site, Prime Minister Pham Minh Chinh wished a happy new year, gave gifts and lucky money to officers, engineers and workers who were working through the Tet holiday on the aircraft parking and passenger terminal construction sites.

After wishing a Happy New Year to officials, engineers and workers, Prime Minister Pham Minh Chinh and the Central working delegation worked with relevant units and Dong Nai province on the progress of the Long Thanh airport project.

At the meeting, Prime Minister Pham Minh Chinh said that the progress of the Long Thanh airport project has not changed the target of completion by December 31, 2025.

Therefore, the Prime Minister requested investors and contractors to change construction methods, increase machinery, increase working hours, work in 3 shifts, and not set tables back... to ensure progress.

The Prime Minister suggested additional solutions such as mobilizing military, police, youth, trade unions, etc. to participate in the construction.

The Prime Minister requested Dong Nai province to coordinate with ministries and branches to thoroughly resolve problems related to the supply of construction materials and filling materials for the project...

Thu tuong Chinh phu Pham Minh Chinh tham hoi, chuc Tet va dong vien can bo, ky su, cong nhan dang thi cong xuyen Tet tai goi thau san do tau bay. Anh: HAC
Prime Minister Pham Minh Chinh visited, wished a happy new year and encouraged cadres, engineers and workers who were working through the Tet holiday at the aircraft parking contract. Photo: HAC
Thu tuong Chinh phu Pham Minh Chinh mong muon cac can bo, ky su, cong nhan dang thi cong tai san bay Long Thanh quyet tam hoan thanh du an dung tien do. Anh: HAC
Prime Minister Pham Minh Chinh hopes that the officials, engineers and workers currently working at Long Thanh airport will be determined to complete the project on schedule. Photo: HAC
Thu tuong Chinh phu Pham Minh Chinh de nghi tinh Dong Nai phoi hop voi cac bo nganh lien quan thao go vuong mac, cung cap day du kip thoi nguon vat lieu xay dung, vat lieu san lap phuc vu thi cong du an san bay Long Thanh. Anh: HAC
Prime Minister Pham Minh Chinh requested Dong Nai province to coordinate with relevant ministries and branches to remove obstacles and promptly provide adequate construction materials and landfill materials for the construction of Long Thanh airport project. Photo: HAC
Thu tuong Chinh phu Pham Minh Chinh kiem tra khu vuc thi cong noi that ben trong cua nha ga hanh khach san bay Long Thanh thuoc goi thau 5.10, du an thanh phan 3. Anh: HAC
Prime Minister Pham Minh Chinh inspects the interior construction area of ​​the Long Thanh airport passenger terminal under package 5.10, component project 3. Photo: HAC
Thu tuong Chinh phu Pham Minh Chinh chi dao tai goi thau 5.10 nha ga hanh khach san bay Long Thanh. Anh: HAC
Prime Minister Pham Minh Chinh gives instructions at package 5.10 of Long Thanh airport passenger terminal. Photo: HAC
Pho Thu tuong Chinh phu Tran Hong Ha phat bieu tai buoi lam viec tai du an san bay Long Thanh. Anh: HAC
Deputy Prime Minister Tran Hong Ha speaks at a working session at the Long Thanh airport project. Photo: HAC
Thu tuong Chinh phu Pham Minh Chinh yeu cau khong thay doi muc tieu san bay Long Thanh. Anh: HAC
Prime Minister Pham Minh Chinh requested that the target of completing Long Thanh airport not be changed. Photo: HAC

HÀ ANH CHIẾN
TIN LIÊN QUAN

2025 breakthrough to bring Long Thanh airport to the finish line soon

|

Dong Nai - Long Thanh Airport Project Management Board said that 2025 is the year to accelerate and make a breakthrough to bring the project to the earliest progress milestone.

Construction through Tet, racing to meet progress of Long Thanh airport project

|

Dong Nai - Although it is the 2025 Lunar New Year holiday, thousands of officers, engineers and workers at Long Thanh airport are still speeding up construction throughout Tet.

Request 3 "no"s, for Long Thanh airport to be completed on time

|

To achieve the basic goal of completing Long Thanh airport by the end of 2025, the Prime Minister requested "no saying no, no saying difficult, no saying yes but not doing".

Sad news

|

Mr. Thai Huy Viet (born in 1954, residing at 05/10, Ba Trieu Street, Ham Rong Ward, Thanh Hoa City) is the father-in-law of comrade Nguyen Thi Ha - Deputy Director of the Multimedia Communication Center - passed away at 19:20, February 1, 2025 (January 4, At Ty Year 2025); at the age of 72.

Coach Kim Sang-sik says goodbye to 3 assistants

|

Coach Kim Sang-sik parted ways with three Korean assistants after winning the 2024 ASEAN Cup.

Thousands of people jostle for a walk on Hanoi's walking street on Tet holiday

|

Hanoi - On February 1 (the 4th day of Tet), Hoan Kiem Lake walking street was bustling with people, people jostling to go to pagodas and sightseeing on the first day of the year.

Tran Thanh, Thu Trang and the game of hundred billion stars

|

The 2025 Tet film season is a race of names worth hundreds of billions of dong, from actors to directors such as Tran Thanh, Thu Trang, Nguyen Quang Dung.

Quang Ngai fishermen excitedly open the sea at the beginning of the year

|

At the beginning of the year of At Ty 2025, Quang Ngai fishermen eagerly opened the sea at the beginning of the year, showing their determination to protect the sovereignty of the Fatherland's sea and islands, hoping for a bumper fishing season.

2025 breakthrough to bring Long Thanh airport to the finish line soon

HÀ ANH CHIẾN |

Dong Nai - Long Thanh Airport Project Management Board said that 2025 is the year to accelerate and make a breakthrough to bring the project to the earliest progress milestone.

Construction through Tet, racing to meet progress of Long Thanh airport project

HÀ ANH CHIẾN - NHƯ QUỲNH |

Dong Nai - Although it is the 2025 Lunar New Year holiday, thousands of officers, engineers and workers at Long Thanh airport are still speeding up construction throughout Tet.

Request 3 "no"s, for Long Thanh airport to be completed on time

Lê Thanh Phong |

To achieve the basic goal of completing Long Thanh airport by the end of 2025, the Prime Minister requested "no saying no, no saying difficult, no saying yes but not doing".