Violations in land management and project implementation in Phu Yen exposed

Hoài Luân |

Phu Yen - Government Inspectorate discovered many violations in land management, use, project implementation, mineral exploitation... in Phu Yen.

On October 10, the Government Inspectorate announced the conclusion of the inspection of the responsibility of the People's Committee of Phu Yen province in receiving citizens, handling complaints and denunciations, and preventing corruption; and compliance with policies and laws in land management and use, mineral exploitation, and construction investment management.

A series of violations at projects were "named and shamed"

During the period 2016-2020, the Government Inspectorate (GIA) discovered many violations in land management and use; exploitation of soil, stone, sand, gravel and project implementation in Phu Yen.

Accordingly, the Government Inspectorate determined that there are still many problems in the allocation of forestry land such as not handing over on the field, not defining boundaries leading to overlap and disputes...

Du an Khu do thi cao cap Vuon Phuong Hoang thuoc  Khu do thi Nam TP Tuy Hoa. Anh: Hoai Luan
Phoenix Garden high-end urban area project in the South Urban Area of ​​Tuy Hoa City (Phu Yen). Photo: Hoai Luan

There are still errors in the issuance of land use right certificates; the arrangement and handling of public land in the province is still slow, leading to vacancy; the permission to sell some public land according to the resolution of the Provincial People's Council is not in accordance with regulations.

Some projects have been approved by competent authorities for investment policies or have been allocated land or leased land but are slow to be implemented or not implemented, including: Cu Lao Mai Nha high-end resort; Tuy Hoa City coastal international tourist village; Sunrise Phu Yen high-end island resort; New City Vietnam high-end complex tourist area; Phu Yen International General Hospital.

Projects with land prices determined incorrectly include: Dung Tien Auto Showroom, Hotel and Office for Lease Trade Center; Tuy Hoa City International Coastal Tourist Village; Bac Luc Khau New Urban Area (Area A).

TTCP determined that Phu Yen province had approved the investment policy for the Nam Hung Vuong social housing project but it was not included in the approved social housing development program; there was no bidding to select an investor for the Bac Luc Khau new urban area project (Area A)...

Determining land use fees for 6 projects that were not used for the right purposes, causing a loss of more than 21.7 billion VND to the State budget. By December 2022, the units had paid more than 18.6 billion VND, with more than 3.1 billion VND remaining. The outstanding financial obligations as of June 30, 2022 were more than 54.6 billion VND.

Phu Yen province is also slow to implement the Prime Minister's instructions on the following projects: Investment in exploiting the Hon Mo O gold mine in Song Hinh district; Phoenix Garden high-end urban area (Tuy Hoa city) and New City Vietnam high-end tourist complex.

Proposal to review the responsibility of provincial leaders

The Government Inspectorate also discovered many violations in the management of public investment capital in Phu Yen.

According to the Government Inspectorate, regarding the appraisal and approval of investment policies, 18 projects with a total investment of more than VND 3,787 billion have been approved but have not been implemented, stopping at the stage of project investment preparation, causing waste of investment costs. The results of capital plan implementation in the province are still low, reaching only 77.8%.

s
New City Vietnam high-end tourist complex project. Photo: Thi Ca

The inspection, acceptance and payment work was not in accordance with legal regulations, and the economic handling to reduce investment costs for 12 projects and some district-level projects was more than 44 billion VND...

Regarding the above violations, the Government Inspectorate determined that the main responsibility belongs to the Chairman of the Provincial People's Committee, Vice Chairmen of the Phu Yen Provincial People's Committee in charge of the field; directors of departments, branches and investors of projects with violations.

Inspector-General recommended that the Prime Minister direct a review of responsibilities to take disciplinary action against the Chairman and Vice Chairmen of the People's Committee of Phu Yen province in different periods; direct clarification of responsibilities of relevant organizations and individuals for violations.

At the same time, it is recommended that the Chairman of the People's Committee of Phu Yen province organize a review and clarify responsibilities for handling according to authority. Direct the competent authorities to handle the economic issue, with a total amount of more than 261 billion VND...

Hoài Luân
TIN LIÊN QUAN

Hanoi boy writes lettering like printing on a thin seaweed fabric

|

Instead of writing calligraphy on paper and silk, Chau Viet Ut (28 years old, Hanoi) chose to "pince" on fabric. His elaborate work has made the online community admire him.

Hundreds of 4-wheeled electric vehicles at Sam Son beach serve tourists again

|

Thanh Hoa - From July 2, hundreds of 4-wheeled electric vehicles in the Sam Son coastal area will return to serve tourists.

Dak Lak people are excited when a large whale appears in Mui Dien

|

Dak Lak - A large whale appeared in the sea area of Hoa Xuan commune, Dak Lak province.

Look up the fastest 10th grade entrance exam scores in 2025 in Hanoi

|

The Hanoi Department of Education and Training (DET) plans to announce the 10th grade entrance exam scores for the 2025-2026 school year on July 4.

On the first day of operation, Hong Ha ward in Hanoi recorded 100% of people's opinions

|

Hanoi - On the first day of operating the two-level government model, the Hong Ha ward government proactively recorded 100% of the comments.

Thailand has an interim prime minister

|

After the Constitutional Court suspended Thai Prime Minister Paetongtarn Shinawatra from office, Suriya Deputy Prime Minister Jungrungreangkit became acting Prime Minister.

Cán bộ ở Phú Yên bị kẻ xấu ghép ảnh nhạy cảm, dọa tống tiền

Hoài Luân |

Phú Yên - Một cán bộ ở Phú Yên nhận được tin nhắn kèm hình ảnh nhạy cảm mà kẻ xấu cắt ghép, dọa tống tiền.

"Siêu" dự án du lịch vẫn là bãi đất đầy cỏ dại sau gần 14 năm triển khai

Hoài Luân |

Phú Yên - Sau gần 14 năm triển khai, dự án Khu du lịch nghỉ dưỡng cao cấp Cù Lao Mái Nhà với vốn đầu tư hơn 18.000 tỉ đồng vẫn chỉ là bãi đất trống đầy cỏ dại.

Phú Yên: Kiến nghị thu hồi dự án khu đô thị cao cấp nghìn tỉ

Hoài Luân |

Nhiều năm qua, tại khu đất vàng ngay phía Nam chân cầu Hùng Vương thuộc Khu đô thị Nam TP Tuy Hòa, tỉnh Phú Yên, dự án khu đô thị cao cấp mang tên Vườn Phượng Hoàng vẫn nằm trơ. Được cấp chủ trương đầu tư từ năm 2016 nhưng đến nay, nơi này vẫn là một khu đất mọc đầy cỏ dại.