Shortening the time to complete the Long Thanh airport passenger terminal

PHẠM ĐÔNG |

The Deputy Prime Minister hopes to shorten the completion time of the package, which is considered the "heart" of Long Thanh airport, to ensure quality and economic efficiency.

On the morning of February 17, Party Central Committee member and Deputy Prime Minister Tran Hong Ha received Mr. Reha Denemec - Vice President of IC ICTAS Construction Industry and Trade Group, the General Contractor Leading the VETUR Contractor consortium to implement package 5.10 of the Long Thanh International Airport project (Long Thanh airport).

Package 5.10 is the item "Construction and installation of equipment for the Passenger Terminal project" - considered the "heart" of Long Thanh airport.

At the meeting, the Government leaders assessed IC ICTAS as a prestigious group with experience in building many airports in the world.

The Deputy Prime Minister said that the Government and the Prime Minister are very interested, regularly inspect, urge, and have very specific meetings to speed up progress, and soon complete the Long Thanh airport project.

The Deputy Prime Minister hopes that IC ICTAS and the VETUR Contractor Joint Venture will continue to work with equipment suppliers to determine the time, and may shorten the completion time for package 5.10, ensuring the highest quality, technical requirements, and economic efficiency.

"This is not only an affirmation of IC ICTAS' prestige and capacity but will become a symbol of the increasingly extensive cooperation between Vietnam and Türkiye, contributing to promoting investment, economic, trade, tourism, culture cooperation... as well as exchange activities between the people of the two countries," said the Deputy Prime Minister.

Discussing the needs for developing transport infrastructure (high-speed railway, urban railway), energy infrastructure, the Deputy Prime Minister highly appreciated the approach and approach of IC ICTAS in particular and Turkish enterprises in general, when implementing transport infrastructure projects, it is necessary to create synchronous connectivity.

Pho Thu tuong Chinh phu Tran Hong Ha tiep ong Reha Denemec. Anh: VGP
Deputy Prime Minister Tran Hong Ha received Mr. Reha Denemec. Photo: VGP

Regarding the Long Thanh airport project, the Deputy Prime Minister requested ACV, ministries and branches to work with IC ICTAS General contractor to agree in March 2025, on specific solutions and plans, detailing issues that need to be resolved when speeding up the completion of package 5.10, as well as coordinating the progress of other packages and component projects of the project.

The Deputy Prime Minister hopes IC ICTAS will continue to have more projects in Vietnam.

Thanking Deputy Prime Minister Tran Hong Ha for taking more time, Mr. Reha Denemec affirmed that the consortium will make every effort, seek technical solutions, construct... to shorten the completion time of package 5.10.

At the same time, it hopes to realize more infrastructure projects to serve the operation and exploitation of Long Thanh airport, as well as transport infrastructure projects in Vietnam in the future.

PHẠM ĐÔNG
RELATED NEWS

No change in target to complete Long Thanh airport by 2025

|

Dong Nai - Prime Minister Pham Minh Chinh and the Central working delegation extended New Year greetings, presented gifts and inspected the progress of the Long Thanh airport project.

Deputy Prime Minister inspects progress of Long Thanh airport project

|

Dong Nai - On the afternoon of January 9, Deputy Prime Minister Tran Hong Ha and a delegation of the Government and ministries worked and inspected the progress of the Long Thanh airport project.

Submit to the National Assembly to build runway number 3 of Long Thanh airport

|

The immediate construction of runway number 3 at Long Thanh airport will meet the needs of phase 1 exploitation.

Handover of work of the Chairman of the Central Inspection Committee

|

The Central Inspection Committee held a conference to hand over the work of the Chairman of the Central Inspection Committee, on the afternoon of November 7, in Hanoi.

The surface of the Vinh Hao - Phan Thiet expressway is flooded again

|

Lam Dong - Vinh Hao - Phan Thiet Expressway was flooded again in 2 sections due to heavy rain, causing temporary road closures at Ma Lam intersection.

School health workers in Nghe An are tired of waiting to be recruited

|

Nghe An - Many school health workers in the province are waiting for the opportunity to be recruited into the payroll.

The actor who played Sa Tang in Journey to the West passed away

|

Chinese media reported that actor Liu Daoreong - who played Sa Tang in Journey to the West part 2 (in 2000) passed away at the age of 78.

Students, Ho Chi Minh City residents remove shoes, wear pants to wade through water to get home

|

HCMC - High tides caused many roads to be deeply flooded, forcing students and residents to take off their shoes and break their pants to wade through water to get home.

No change in target to complete Long Thanh airport by 2025

HÀ ANH CHIẾN |

Dong Nai - Prime Minister Pham Minh Chinh and the Central working delegation extended New Year greetings, presented gifts and inspected the progress of the Long Thanh airport project.

Deputy Prime Minister inspects progress of Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai - On the afternoon of January 9, Deputy Prime Minister Tran Hong Ha and a delegation of the Government and ministries worked and inspected the progress of the Long Thanh airport project.

Submit to the National Assembly to build runway number 3 of Long Thanh airport

PHẠM ĐÔNG |

The immediate construction of runway number 3 at Long Thanh airport will meet the needs of phase 1 exploitation.