Removing difficulties, speeding up the progress of 2 expressways through Dong Nai

HÀ ANH CHIẾN |

Dong Nai - Deputy Prime Minister Ho Duc Phoc worked on the progress of the Ben Luc - Long Thanh expressway project and the Bien Hoa - Vung Tau expressway.

On March 14, Deputy Prime Minister Ho Duc Phoc worked with Dong Nai province and related localities on the construction progress of the Bien Hoa - Vung Tau, Ben Luc - Long Thanh expressway projects.

According to the report, the construction progress of the Bien Hoa - Vung Tau Expressway Component 3 project (through Ba Ria - Vung Tau province) meets the requirements and will be technically open to traffic before April 30.

Particularly for component projects 1 and 2 passing through Dong Nai province, the construction output is currently low, causing difficulties in site clearance, relocation of technical infrastructure systems and construction materials.

Mr. Duong Minh Dung - Vice Chairman of Dong Nai Provincial People's Committee said that the locality strives to complete the handover of the remaining 300m of the Ben Luc - Long Thanh expressway project to the investor in May 2025.

For the Bien Hoa - Vung Tau expressway project, the locality will basically hand over the site in March 2025.

Regarding the relocation of the technical infrastructure system, component project 1 will be completed in April 2025 and component project 2 will be completed in July 2025.

Dong Nai has coordinated with relevant units and has basically removed difficulties and obstacles in construction materials for project construction.

Mr. Ho Thanh Son - Standing Deputy Secretary of Dong Nai Provincial Party Committee also suggested that for the Bien Hoa - Vung Tau Expressway component 2 project, the investor, Project Management Board 85, speed up the construction progress.

Pho thu tuong Chinh phu Ho Duc Phoc phat bieu tai buoi lam viec tai Dong Nai. Anh: HAC
Deputy Prime Minister Ho Duc Phoc spoke at the meeting. Photo: HAC

Concluding the meeting, Deputy Prime Minister Ho Duc Phoc suggested that Dong Nai province soon complete site clearance and relocate the technical infrastructure system of the two projects of Ben Luc - Long Thanh Expressway and Bien Hoa - Vung Tau Expressway.

At the same time, the Deputy Prime Minister also suggested that Dong Nai should pay attention to building beautiful and modern resettlement areas so that people have a new place to live better than the old place; Closely coordinate with the Ministry of Agriculture and Environment to completely handle difficulties and problems related to construction materials serving projects. For related units, they must coordinate to speed up the construction progress, determined to complete the projects on schedule.

Pho thu tuong Chinh phu Ho Duc Phoc cung doan cong tac kiem tra thuc dia 2 du an cao toc ngay 13.3. Anh: HAC
Deputy Prime Minister Ho Duc Phoc and the working delegation inspected the two expressway projects on March 13. Photo: HAC

Previously, on March 13, Deputy Prime Minister Ho Duc Phoc and the working delegation of Chinh Phu inspected the two projects of Bien Hoa - Vung Tau Expressway and Ben Luc - Long Thanh Expressway.

HÀ ANH CHIẾN
TIN LIÊN QUAN

The highway lacks sand, the bridge has been installed but cannot yet build an approach road

|

To ensure the Chau Doc - Can Tho - Soc Trang (horizontal) expressway project is completed in 2026, the construction unit recommends that the investor promptly resolve the sand source.

Deputy Prime Minister Ho Duc Phoc inspects abandoned project in Nha Trang

|

Khanh Hoa - During his working trip to the locality, Deputy Prime Minister Ho Duc Phoc inspected a series of abandoned golden land projects in Nha Trang.

Establishing a dossier to invest in a 1,000 billion VND arterial road in Dong Nai

|

Dong Nai - Bien Hoa City People's Committee is preparing public investment documents for the Tan Phong - Trang Dai - Tan Hiep inter-ward road project (about 1,000 billion VND).

Coach Kim Sang-sik explains the arrangement of the Vietnam team

|

Coach Kim Sang-sik explained that the use of personnel by the Vietnam team in the match against Cambodia was to prepare for the match against Laos.

Proposal to name Quang Nam City - Da Nang after the reorganization

|

The Standing Committee of the Quang Nam Provincial Party Committee has proposed to name Quang Nam City - Da Nang after the reorganization of the two localities.

Su-30MK2 fighter jets practice acrobatics before the April 30 grandstand

|

Dong Nai - On March 19, a series of Su-30MK2 fighters took off over Bien Hoa, conducting a training course to prepare for the 50th anniversary of the country's reunification.

There will be many Vietnamese enterprises investing in the US

|

Vice Chairman of the National Assembly Vu Hong Thanh hopes that in the coming time, many Vietnamese enterprises will invest in the US.

Continuing to enforce a series of illegal houses on agricultural land

|

After the reflection of Lao Dong Newspaper, on March 19, the People's Committee of Song Phuong Commune, Hoai Duc, Hanoi continued to enforce and dismantle illegal constructions on agricultural land.

The highway lacks sand, the bridge has been installed but cannot yet build an approach road

Tạ Quang |

To ensure the Chau Doc - Can Tho - Soc Trang (horizontal) expressway project is completed in 2026, the construction unit recommends that the investor promptly resolve the sand source.

Deputy Prime Minister Ho Duc Phoc inspects abandoned project in Nha Trang

Hữu Long |

Khanh Hoa - During his working trip to the locality, Deputy Prime Minister Ho Duc Phoc inspected a series of abandoned golden land projects in Nha Trang.

Establishing a dossier to invest in a 1,000 billion VND arterial road in Dong Nai

HÀ ANH CHIẾN |

Dong Nai - Bien Hoa City People's Committee is preparing public investment documents for the Tan Phong - Trang Dai - Tan Hiep inter-ward road project (about 1,000 billion VND).