Deadline for completing the expansion of Ho Chi Minh City - Long Thanh Expressway

PHẠM ĐÔNG |

Deputy Prime Minister Tran Hong Ha requested to strive to inaugurate the Ho Chi Minh City - Long Thanh expressway expansion project on September 2, 2026.

The Government Office has issued Document No. 2143/VPCP-CN conveying the direction of Central Party Committee member, Deputy Prime Minister Tran Hong Ha on the investment plan for the Ho Chi Minh City - Long Thanh Expressway expansion project (project).

Deputy Prime Minister Tran Hong Ha directed the Ministry of Construction to be responsible for the proposed plan, organize the implementation of the project, and strive to inaugurate the project on September 2, 2026.

The Minister of Construction decides to apply contractor selection in special cases according to authority, in accordance with current regulations; responsible for coordinating with relevant ministries, branches and localities to implement according to regulations, not allowing negativity, waste and group interests to occur.

The Ministry of Finance urgently synthesizes the proposal of the Ministry of Transport (now the Ministry of Construction) on the capital source for the Project from the increased central budget revenue in 2024 according to the direction of Politburo member, Permanent Deputy Prime Minister Nguyen Hoa Binh in Notice No. 22/TB-VPCP dated February 26, 2025 of the Government Office.

PHẠM ĐÔNG
RELATED NEWS

deadline for completing the Chau Doc - Can Tho - Soc Trang expressway

|

The Prime Minister requested to restore the delayed progress, completing the Chau Doc - Can Tho - Soc Trang expressway in June 2026.

Progress milestones for the two expressway projects through Lang Son and Cao Bang

|

Before March 31, Lang Son and Cao Bang must clear and hand over clean land to implement the construction of 2 expressway projects in the area.

Ho Chi Minh City - Long Thanh Expressway is about to escape traffic jams

|

Ho Chi Minh City spends nearly VND1,000 billion to expand the Ho Chi Minh City - Long Thanh - Dau Giay expressway from 4 to 8 lanes, with plans to start construction in 2025 and complete in 2026.

The new Minister of Home Affairs will explain the issues in the draft Law on Civil Servants (amended)

|

Minister of Home Affairs Do Thanh Binh will explain and clarify a number of issues raised by National Assembly deputies in the draft Law on Civil Servants (amended).

Pokrovsk is tense, fog creates an advantage for the Russian army's advance

|

The thick fog helps the Russian army advance deeper into the strategic city of Pokrovsk, eastern Ukraine.

functioningless while teaching, a teacher in the highlands has been teaching for 20 years

|

For more than 20 years on the podium, teacher Hoang Thi Thiet (Chieng Xuan Primary and Secondary School) still maintains her passion for the profession, considering sowing in the highlands as a part of her life.

Citizens will have the right to complain about the results of consulting on merging and renaming provinces and communes

|

The Ministry of Home Affairs proposes to regulate the reception and handling of recommendations on the results of collecting public opinions on the establishment, dissolution, merger and renaming of provinces and communes.

Hanoi announces the results of the personnel vote

|

The Hanoi Party Committee Executive Committee elected Mr. Do Anh Tuan and Mr. Tran Dinh Canh to respectively hold the positions of Chairman of the City Party Committee's Inspection Committee and Head of the City Party Committee's Internal Affairs Committee.

deadline for completing the Chau Doc - Can Tho - Soc Trang expressway

PHẠM ĐÔNG |

The Prime Minister requested to restore the delayed progress, completing the Chau Doc - Can Tho - Soc Trang expressway in June 2026.

Progress milestones for the two expressway projects through Lang Son and Cao Bang

PHẠM ĐÔNG |

Before March 31, Lang Son and Cao Bang must clear and hand over clean land to implement the construction of 2 expressway projects in the area.

Ho Chi Minh City - Long Thanh Expressway is about to escape traffic jams

MINH QUÂN |

Ho Chi Minh City spends nearly VND1,000 billion to expand the Ho Chi Minh City - Long Thanh - Dau Giay expressway from 4 to 8 lanes, with plans to start construction in 2025 and complete in 2026.