The Prime Minister set the time to complete the 500 kV circuit 3 line

PHẠM ĐÔNG |

The Prime Minister requested units to complete the 500kV circuit 3 line construction project before September 2, to celebrate the 79th anniversary of National Day.

On the afternoon of August 13, at the Government Headquarters, Prime Minister Pham Minh Chinh chaired a meeting with ministries and branches; online with Nghe An and Ha Tinh provinces on the implementation status of the 500kV circuit 3 transmission line project (from Pho Noi, Hung Yen province to Quang Trach, Quang Binh province).

According to the Government Office, at the meeting, the Prime Minister listened to leaders of ministries, branches, units and the two provinces of Nghe An and Ha Tinh discuss and assess the situation and propose tasks and solutions to soon complete the situation. project as planned.

Concluding the meeting, Prime Minister Pham Minh Chinh emphasized that the 500kV circuit 3 line is a dual circuit line, with important significance, increasing the power supply for the North, serving stable electricity for production and consumption. used by people and businesses.

Recognizing the importance of the project, the Government has directed it drastically and closely, removing all difficulties and mobilizing large resources for the project.

Ministries, branches, localities, units and the entire political system participated fiercely and received support from people and businesses for the project.

The Prime Minister requested the inauguration of the 500 kV circuit 3 line on the occasion of National Day this year. Photo: Nhat Bac
The Prime Minister requested the inauguration of the 500 kV circuit 3 line on the occasion of National Day this year. Photo: Nhat Bac

According to the Prime Minister, the project's workload is huge, constructed in harsh weather conditions, difficult and complex terrain, especially in the North Central localities, which are considered "rain bags". pan of fire", but so far the project has achieved a large amount of work, the remaining amount of work is not much...

However, to complete and put the entire line into operation as planned, it is necessary to continue to concentrate highly.

The Prime Minister requested to review and assign "clear people, clear tasks, clear time, clear responsibilities, clear products"; Organize the construction and carry out the remaining work in the spirit of "overcoming the sun, overcoming the rain, not losing to the wind and storm", organizing "3 shifts, 4 crews, working continuously 24/7"... completed project before September 2, 2024, to celebrate the 79th anniversary of National Day.

The Prime Minister assigns specific tasks to each ministry, branch, locality and unit; At the same time, direct forces to coordinate closely and support each other to successfully complete tasks; Organize a summary and draw lessons learned in directing, leading, operating, and organizing project implementation.

In particular, the Ministry of Industry and Trade regularly inspects and urges project implementation; Organize project acceptance. The Ministry of National Defense mobilizes forces and technical means to support project construction units.

The Ministry of Agriculture and Rural Development and the Ministry of Natural Resources and Environment guide localities to change forest purposes in accordance with the law; Guide and organize inspection of reconstitution, ensuring environmental hygiene where the project passes through.

Localities continue to mobilize human resources to participate in tasks within the project scope; Organizing reconstitution, protecting the environment and traffic; take care of the lives and jobs of the people who have given up their land for the project, ensuring that no one lacks food, clothing, or shelter. People have a new place to live that is better than their old place of residence.

Local police ensure security and order at construction sites and during the project's restoration and operation.

The Ministry of Home Affairs summarizes the results and proposes rewards to units and individuals with outstanding achievements in project implementation at all levels, sectors and localities.

Media agencies increase information and communication about the situation and results of project implementation; just praised the efforts of all subjects participating in the project; recently disseminated lessons learned from the project; Motivate and inspire all levels and sectors in implementing other important programs and projects throughout the country.

PHẠM ĐÔNG
RELATED NEWS

Thi công “3 ca, 4 kíp”, đưa công trình đường dây 500kV mạch 3 về đích

QUANG ĐẠI |

Ngày 23.6, Ủy viên Bộ Chính trị, Thủ tướng Chính phủ Phạm Minh Chính cùng đoàn công tác đã đi kiểm tra, đôn đốc thực hiện dự án đường dây tải điện 500kV mạch 3 Quảng Trạch - Phố Nối, đoạn qua địa bàn tỉnh Nghệ An.

Thủ tướng Chính phủ Phạm Minh Chính kiểm tra dự án đường dây 500kV mạch 3 tại Nghệ An

QUANG ĐẠI - DUY CHƯƠNG |

Sáng 23.6, Thủ tướng Chính phủ Phạm Minh Chính cùng đoàn công tác đã đi kiểm tra, đôn đốc thực hiện dự án đường dây tải điện 500kV mạch 3 Quảng Trạch - Phố Nối, đoạn qua địa bàn tỉnh Nghệ An.

Thủ tướng biểu dương các đơn vị thi công đường dây 500 kV mạch 3

PHẠM ĐÔNG |

Thủ tướng Chính phủ ghi nhận, đánh giá cao và nhiệt liệt biểu dương các cơ quan, doanh nghiệp, người lao động và sự đồng lòng của người dân với tinh thần quyết tâm cao nhất, vượt mọi khó khăn, huy động mọi nguồn lực tập trung thi công công trình đường dây 500 kV mạch 3 từ Quảng Trạch đến Phố Nối.

Trực tiếp bóng đá Argentina 3-0 Bolivia: Alvarez ghi bàn thứ ba

tam nguyên |

Trực tiếp trận Argentina vs Bolivia lúc 07h00 ngày 16.10, tại vòng loại World Cup 2026 khu vực Nam Mỹ.

Ngoài cầu Phong Châu, Phú Thọ còn rất nhiều cây cầu yếu

Bài và Ảnh: Tô Công |

Phú Thọ - Rất nhiều cây cầu nằm trên các tuyến tỉnh lộ đã cũ, yếu nhưng nhiều năm chưa được sửa chữa, hàng ngày vẫn "cõng" vô số loạt xe trọng tải lớn.

Ông Trump nhún nhảy 40 phút trong cuộc vận động tranh cử

Song Minh |

Cựu Tổng thống Donald Trump kết thúc cuộc vận động tranh cử ở Pennsylvania bằng cách nhún nhảy theo nhạc suốt 40 phút.

Vàng phát huy vai trò như một loại tiền tệ toàn cầu

Phương Anh (Theo Kitco) |

Theo Kitco - trước diễn biến căng thẳng địa chính trị, các ngân hàng trung ương có thể sử dụng vàng để thanh toán thương mại quốc tế.

Hezbollah kêu gọi ngừng bắn, nếu không sẽ giáng đòn "đau đớn"

Bùi Đức |

Hezbollah quyết giáng một đòn “đau đớn” lên Israel nếu chiến tranh vẫn tiếp tục ở Lebanon.

Thi công “3 ca, 4 kíp”, đưa công trình đường dây 500kV mạch 3 về đích

QUANG ĐẠI |

Ngày 23.6, Ủy viên Bộ Chính trị, Thủ tướng Chính phủ Phạm Minh Chính cùng đoàn công tác đã đi kiểm tra, đôn đốc thực hiện dự án đường dây tải điện 500kV mạch 3 Quảng Trạch - Phố Nối, đoạn qua địa bàn tỉnh Nghệ An.

Thủ tướng Chính phủ Phạm Minh Chính kiểm tra dự án đường dây 500kV mạch 3 tại Nghệ An

QUANG ĐẠI - DUY CHƯƠNG |

Sáng 23.6, Thủ tướng Chính phủ Phạm Minh Chính cùng đoàn công tác đã đi kiểm tra, đôn đốc thực hiện dự án đường dây tải điện 500kV mạch 3 Quảng Trạch - Phố Nối, đoạn qua địa bàn tỉnh Nghệ An.

Thủ tướng biểu dương các đơn vị thi công đường dây 500 kV mạch 3

PHẠM ĐÔNG |

Thủ tướng Chính phủ ghi nhận, đánh giá cao và nhiệt liệt biểu dương các cơ quan, doanh nghiệp, người lao động và sự đồng lòng của người dân với tinh thần quyết tâm cao nhất, vượt mọi khó khăn, huy động mọi nguồn lực tập trung thi công công trình đường dây 500 kV mạch 3 từ Quảng Trạch đến Phố Nối.