Prime Minister sets deadline for reporting on high-speed railway technology and investment forms

PHẠM ĐÔNG |

Prime Minister Pham Minh Chinh requested to urgently propose technology selection and investment forms for the North-South high-speed railway.

On January 6, at the Government Headquarters, Politburo Member, Prime Minister Pham Minh Chinh - Head of the Steering Committee for key projects and important national projects in the railway sector chaired the 5th meeting of the Steering Committee.

Speaking in conclusion, the Prime Minister requested the Steering Committee, relevant ministries, branches, and localities to proactively deploy tasks, coordinate according to assigned functions, tasks, and powers, and whoever is under their authority must do it.

The Prime Minister requested to urgently report on the project to restructure the Vietnam Railways Corporation and assign this Corporation to build a project to develop the railway industry.

Government leaders also assigned specific tasks to ministries, branches, and localities in implementing specific railway projects.

Accordingly, for the high-speed railway project on the North-South axis, the Ministry of Construction, based on the direction of the Politburo, shall preside over and select the most suitable technology for the project, submit it to the Standing Government for reporting to competent authorities, and complete it before January 15.

The Ministry of Construction appoints consultants to prepare feasibility study reports to ensure capacity according to processes, procedures, regulations and authority. At the same time, chair and coordinate with ministries and research agencies to propose the selection of investment forms (public investment, PPP, business) to report at the upcoming meeting of the Steering Committee.

Localities and Vietnam Electricity Group continue to promote site clearance and relocation of technical infrastructure according to the approved plan and the National Assembly's Resolution allowed at the 10th Session of the 15th National Assembly. Viettel and VNPT groups continue to implement assigned tasks on control systems and technology.

Phien hop Ban Chi dao cac cong trinh trong diem, du an quan trong quoc gia linh vuc duong sat. Anh: VGP
Meeting of the Steering Committee for key projects and important national projects in the railway sector. Photo: VGP

For the Lao Cai - Hanoi - Hai Phong railway line project, regarding the progress of component project 2, the Ministry of Construction directed to complete the Feasibility Study Report and approve the project in June 2026 for early commencement.

The Ministry of Finance is responsible for balancing and ensuring sufficient capital to implement the project, including a loan plan if favorable.

Requesting the early completion of the planning of the Hanoi - Lang Son and Hai Phong - Ha Long - Mong Cai railway lines, the Prime Minister also agreed to assign and welcomed Quang Ninh province to be the investor of the Hai Phong - Ha Long - Mong Cai line according to the provisions of law.

Regarding urban railway projects, the Prime Minister highly appreciated Hanoi and Ho Chi Minh City for proactively deploying routes according to their authority, ensuring connectivity and technology transfer; in which priority is given to the railway line connecting Tan Son Nhat airport and Long Thanh airport; Van Cao - Hoa Lac route (Hanoi).

The Ministry of Construction and the Ministry of Science and Technology research and develop national technical regulations on urban railways. Ministries coordinate to support removing obstacles in site clearance, capital, and procedures.

The Ministry of Construction shall preside over and coordinate with the Ministry of Education and Training, Vietnam Railways Corporation to effectively implement the project on training and developing Vietnamese railway human resources to 2035, with orientations to 2045; have specific roadmaps and plans to promptly train human resources to serve the construction, management, operation and exploitation of railway lines, especially the Lao Cai - Hanoi - Hai Phong railway line.

Ministries, branches, and localities continue to closely coordinate with the Ministry of Construction in all stages; request the State Audit Office to support auditing right from the beginning of projects.

PHẠM ĐÔNG
RELATED NEWS

Prime Minister directs urgent operation of national gold exchange

|

The Prime Minister requested that based on the specific situation, appropriate credit room be issued; urgently put the national gold exchange into operation.

Starting construction of 16 Lao Cai - Hanoi - Hai Phong railway stations in the first quarter of 2026

|

The remaining 16 stations of the Lao Cai - Hanoi - Hai Phong railway line are being surveyed and designed to start construction in the first quarter of 2026.

The Prime Minister requested to choose the investment method for the North-South high-speed railway in January 2026

|

Prime Minister Pham Minh Chinh emphasized that it is necessary to choose the investment method for the North-South high-speed railway project in January 2026.

U23 Vietnam returns home in the arms of fans

|

Hundreds of fans were present at Noi Bai airport to welcome U23 Vietnam home after winning a bronze medal at the 2026 AFC U23 Championship.

Live football U23 Japan vs U23 China in the AFC U23 Championship final

|

Live broadcast of the match between U23 Japan and U23 China in the 2026 AFC U23 Championship final, taking place at 10:00 PM today (January 24).

People release buffaloes and crawl to the edge of the Vinh Hao - Phan Thiet expressway

|

Lam Dong - From the locations where the barbed wire fence was cut, people released buffaloes and cows into the corridor next to the Vinh Hao - Phan Thiet expressway.

It's a bit of a bit of a bit of a bit of a bit of a bit.

Vinh Chau purple onions in season, rural workers have more jobs

|

Can Tho - Vinh Chau is not only famous for its purple onion fields but also creates stable livelihoods for thousands of local workers.

US economy accelerates in 2025, opening a brighter growth period in 2026

|

The US economy recorded strong growth in 2025, GDP broke through in the third quarter and consumption maintained its momentum, creating a positive foundation for the outlook for 2026.

Prime Minister directs urgent operation of national gold exchange

PHẠM ĐÔNG |

The Prime Minister requested that based on the specific situation, appropriate credit room be issued; urgently put the national gold exchange into operation.

Starting construction of 16 Lao Cai - Hanoi - Hai Phong railway stations in the first quarter of 2026

PHẠM ĐÔNG |

The remaining 16 stations of the Lao Cai - Hanoi - Hai Phong railway line are being surveyed and designed to start construction in the first quarter of 2026.

The Prime Minister requested to choose the investment method for the North-South high-speed railway in January 2026

Xuyên Đông |

Prime Minister Pham Minh Chinh emphasized that it is necessary to choose the investment method for the North-South high-speed railway project in January 2026.