VEC sues many partners, demands land for Noi Bai - Lao Cai expressway rest stop

Trọng Lộc |

Vietnam Expressway Corporation (VEC) has sued many investors in rest stops on the Noi Bai - Lao Cai Expressway for breach of contract.

On April 18, Ms. Nguyen Hong Phuong - Chief Justice of Tran Yen District People's Court, Yen Bai Province confirmed the information: the agency is handling the construction contract dispute case between VEC and Phu Thinh Phu Tho Joint Stock Company, the investor of Km117+500 rest stop on Noi Bai - Lao Cai Expressway.

According to Ms. Phuong, due to many unsuccessful efforts to mediate, the People's Court of Tran Yen district plans to bring the case to trial in May 2025.

Meanwhile, responding to Lao Dong Newspaper, VEC representative said that - Phu Thinh Phu Tho Company Limited - Km117+500 rest stop violated the provisions of the signed Contract such as: Construction of the project did not comply with the original design; business cooperation with a third party but has not been approved by VEC; environmental sanitation and traffic safety in the rest stop area have not been guaranteed...

Cac hoat dong tai Tram dung nghi Km117+500 tren cao toc Noi Bai - Lao Cai van dien ra binh thuong. Anh: Van Duc
Activities at the Km117+500 rest stop on the Noi Bai - Lao Cai Expressway are still taking place normally. Photo: Van Duc

It is known that in addition to Phu Thinh Phu Tho Company Limited (Km117+500), VEC also sued 3 other resort investors on the Noi Bai - Lao Cai Expressway, including: Phuoc An Company Limited (Km22+900); Tuan Tu Phu Tho Company Limited (Km57+500) and 27/7 Thanh Xuan Joint Stock Company (Km171+500).

Currently, VEC is requiring 4 investors of rest stops on the Noi Bai - Lao Cai route to terminate their operations to return/ hand over the site. However, the business disputes between the parties are still taking place.

"Before filing the lawsuit, VEC has repeatedly invited investors at rest stops on the Noi Bai - Lao Cai route to negotiate contracts. However, because the parties could not reach an agreement, VEC was forced to use the final legal measure of filing a lawsuit," VEC representative informed.

Previously, Lao Dong Newspaper reported that many rest stops on the Noi Bai - Lao Cai Expressway still maintain the placement of "lift support boxes" in front of the restroom.

There are also staff on duty outside the restroom, if anyone does not put the money in the box, they will be reminded.

Upon receiving the information, the management and operation unit of the rest stop has placed all toll boxes in front of the restroom and requested the staff to immediately stop all activities to collect money from passengers.

Trọng Lộc
TIN LIÊN QUAN

Many repairs, Noi Bai - Lao Cai Expressway is covered with patchwork

|

Despite many repairs, the quality of the Noi Bai - Lao Cai expressway is still considered quite bad and has many patches.

Repairing signs on Noi Bai - Lao Cai Expressway after reflection

|

The signs with incorrect instructions about information on the Noi Bai - Lao Cai Expressway passing through Phu Tho province have been adjusted after being reported by Lao Dong Newspaper.

Expanding and upgrading Noi Bai - Lao Cai Expressway

|

Vietnam Expressway Corporation (VEC) has just completed the signing of a contractor selection to repair the damage to the Noi Bai - Lao Cai Expressway.

Rescuing a 19-year-old girl who panicked because she was trapped in an elevator in Ho Chi Minh City

|

HCMC - A 19-year-old girl panicked because of an elevator stuck in District 1, and was quickly rescued safely by the Fire Prevention and Rescue Police - HCMC Police.

Update on historic flash floods in 2 communes in Bac Kan that killed 4 people

|

Bac Kan - The flash flood at night in Dong Phuc and Yen Duong communes (Ba Be district) killed 4 people and caused damage to many properties.

Buying in the midst of a plummeting gold price, investors suffered heavy losses after a week

|

Gold buyers surfed last week and lost up to 6.5 million VND/tael. The main reason comes from the sharp decline in gold prices and the high difference between buying and selling.

The Fatherland Front actively participates in supervising law enforcement

|

The National Assembly Chairman emphasized the requirement for the Fatherland Front and mass organizations to actively participate in supervising the implementation and dissemination of laws.

Restaurant in Hai Duong causes controversy over collecting additional fees from customers for making chicken

|

Hai Duong - An incident at a restaurant caused a stir in public opinion when customers discovered a bill for an additional 200,000 VND for the "making chicken + hotpot + vegetable" category.

Many repairs, Noi Bai - Lao Cai Expressway is covered with patchwork

Việt Bắc |

Despite many repairs, the quality of the Noi Bai - Lao Cai expressway is still considered quite bad and has many patches.

Repairing signs on Noi Bai - Lao Cai Expressway after reflection

Tô Công |

The signs with incorrect instructions about information on the Noi Bai - Lao Cai Expressway passing through Phu Tho province have been adjusted after being reported by Lao Dong Newspaper.

Expanding and upgrading Noi Bai - Lao Cai Expressway

Bảo Nguyên |

Vietnam Expressway Corporation (VEC) has just completed the signing of a contractor selection to repair the damage to the Noi Bai - Lao Cai Expressway.