Requesting Gia Lai to speed up the construction progress of the 1,325 billion VND road

THANH TUẤN |

Gia Lai - Deputy Prime Minister Bui Thanh Son requested the province to direct the acceleration of the construction progress of the Eastern Economic Corridor.

On March 22, Deputy Prime Minister Bui Thanh Son and the working delegation had a working session with Gia Lai province to inspect the progress of the Eastern Economic Corridor project.

The Eastern Economic Corridor project connecting Dak Doa, Chu Pah, and Pleiku districts has a total length of 15.14km, with a total investment of 1,325 billion VND, expected to be completed in 2025.

Currently, the project has cleared 85% of the site, and the remaining 2.22km has not been handed over. Deputy Prime Minister Bui Thanh Son requested to speed up the site clearance progress before April 2025 and complete the route by the end of this year.

When completed, the project will contribute to promoting Gia Lai's socio-economic development, facilitating people and vehicles.

The Deputy Prime Minister and the working delegation also visited and worked at Vinh Hiep Company Limited, one of the leading coffee exporters in Vietnam today.

In 2024, the company achieved an export turnover of 520 million USD, accounting for nearly 80% of Gia Lai province's coffee export turnover. In just the first 3 months of 2025, the company's export value reached 300 million USD.

The Deputy Prime Minister highly appreciated coffee export activities, encouraged businesses to invest in technology, expand production and enhance their brands.

The Deputy Prime Minister also suggested that local governments support businesses in developing and promoting "three-house" cooperation including businesses, the state and the people.

THANH TUẤN
RELATED NEWS

Exceeding the construction progress of Chau Doc - Can Tho - Soc Trang expressway

|

Soc Trang - There have been 41 bridges under the Chau Doc - Can Tho - Soc Trang expressway component 4 project under construction, many bridges are ahead of schedule and are about to be completed.

Adjusting the plan, reviewing the construction site of the Western Expressway

|

Can Tho - Investors and contractors are adjusting the plan, reviewing the construction teams of Chau Doc - Can Tho - Soc Trang expressway, urgently speeding up the progress.

People regret land while waiting for VSIP project to be constructed

|

Ha Tinh - After nearly 1 year of construction, the VSIP Ha Tinh Project still has many hectares of unpaved and abandoned rice fields, making farmers regret their land.

Hanoi Secretary sets deadline for site clearance for Ring Road 4 project

|

Hanoi - Secretary of the City Party Committee Nguyen Duy Ngoc requested that no later than December 31, 2025, the site must be handed over to the construction unit of the Ring Road 4 project.

Hour 9: Love gambling - Part 1

|

Hour 9 No. 178 - A successful couple but apart, both husband and wife have a "third person". How will they face this marriage tragedy?

Dak Lak bans ships from going out to sea before storm No. 15

|

Dak Lak - Chairman of the People's Committees of coastal communes and wards announced a ban on ships going out to sea and fishing activities at sea, before storm No. 15.

Tomorrow night, storm No. 15 Koto will encounter increased cold air, forecast for upcoming developments

|

Storm No. 15 is still likely to strengthen in the next 24 hours when moving in warm ocean waters.

The new land price list in Hanoi takes effect from January 1, 2026, highest at 702 million VND/m2

|

Hanoi officially applied the new land price list from January 1, 2026, an increase of 2-26% compared to the current land price list.

Exceeding the construction progress of Chau Doc - Can Tho - Soc Trang expressway

PHƯƠNG ANH |

Soc Trang - There have been 41 bridges under the Chau Doc - Can Tho - Soc Trang expressway component 4 project under construction, many bridges are ahead of schedule and are about to be completed.

Adjusting the plan, reviewing the construction site of the Western Expressway

TẠ QUANG - YẾN PHƯƠNG |

Can Tho - Investors and contractors are adjusting the plan, reviewing the construction teams of Chau Doc - Can Tho - Soc Trang expressway, urgently speeding up the progress.

People regret land while waiting for VSIP project to be constructed

TRẦN TUẤN |

Ha Tinh - After nearly 1 year of construction, the VSIP Ha Tinh Project still has many hectares of unpaved and abandoned rice fields, making farmers regret their land.