Requesting Gia Lai to speed up the construction progress of the 1,325 billion VND road

THANH TUẤN |

Gia Lai - Deputy Prime Minister Bui Thanh Son requested the province to direct the acceleration of the construction progress of the Eastern Economic Corridor.

On March 22, Deputy Prime Minister Bui Thanh Son and the working delegation had a working session with Gia Lai province to inspect the progress of the Eastern Economic Corridor project.

The Eastern Economic Corridor project connecting Dak Doa, Chu Pah, and Pleiku districts has a total length of 15.14km, with a total investment of 1,325 billion VND, expected to be completed in 2025.

Currently, the project has cleared 85% of the site, and the remaining 2.22km has not been handed over. Deputy Prime Minister Bui Thanh Son requested to speed up the site clearance progress before April 2025 and complete the route by the end of this year.

When completed, the project will contribute to promoting Gia Lai's socio-economic development, facilitating people and vehicles.

The Deputy Prime Minister and the working delegation also visited and worked at Vinh Hiep Company Limited, one of the leading coffee exporters in Vietnam today.

In 2024, the company achieved an export turnover of 520 million USD, accounting for nearly 80% of Gia Lai province's coffee export turnover. In just the first 3 months of 2025, the company's export value reached 300 million USD.

The Deputy Prime Minister highly appreciated coffee export activities, encouraged businesses to invest in technology, expand production and enhance their brands.

The Deputy Prime Minister also suggested that local governments support businesses in developing and promoting "three-house" cooperation including businesses, the state and the people.

THANH TUẤN
RELATED NEWS

Exceeding the construction progress of Chau Doc - Can Tho - Soc Trang expressway

|

Soc Trang - There have been 41 bridges under the Chau Doc - Can Tho - Soc Trang expressway component 4 project under construction, many bridges are ahead of schedule and are about to be completed.

Adjusting the plan, reviewing the construction site of the Western Expressway

|

Can Tho - Investors and contractors are adjusting the plan, reviewing the construction teams of Chau Doc - Can Tho - Soc Trang expressway, urgently speeding up the progress.

People regret land while waiting for VSIP project to be constructed

|

Ha Tinh - After nearly 1 year of construction, the VSIP Ha Tinh Project still has many hectares of unpaved and abandoned rice fields, making farmers regret their land.

Storm No. 13 gusts to level 12 but is not a typhoon

|

On the evening of November 6, storm No. 13 officially made landfall in the coastal area from Quang Ngai to Dak Lak very strongly, but it did not have to be a typhoon.

Quang Ngai authorities strive to protect people in the midst of storm No. 13

|

Quang Ngai - Storm No. 13 has made landfall in Quang Ngai with strong gusts of wind. Sa Huynh coastal ward has urgently evacuated more than 600 households.

Typhoon makes landfall, 1 person in Dak Lak dies

|

When storm No. 13 (Kalmaegi) made landfall in the eastern area of Dak Lak province with gusts of level 12 13. The locality recorded 1 death due to house collapse.

Khanh Hoa Secretary inspects vulnerable areas when storm No. 13 makes landfall at night

|

Khanh Hoa - On the evening of November 6, Mr. Nghiem Xuan Thanh - Secretary of Khanh Hoa Provincial Party Committee - inspected the response to storm No. 13 (Kalmaegi) in vulnerable areas.

Gia Lai strong gusts of wind level 15, fallen trees, corrugated iron roofs fly everywhere

|

Gia Lai - Recorded at 8:00 p.m. on November 6, many communes and wards in the eastern province had strong thunderstorms, knocking down many trees, corrugated iron roofs, and civil houses.

Exceeding the construction progress of Chau Doc - Can Tho - Soc Trang expressway

PHƯƠNG ANH |

Soc Trang - There have been 41 bridges under the Chau Doc - Can Tho - Soc Trang expressway component 4 project under construction, many bridges are ahead of schedule and are about to be completed.

Adjusting the plan, reviewing the construction site of the Western Expressway

TẠ QUANG - YẾN PHƯƠNG |

Can Tho - Investors and contractors are adjusting the plan, reviewing the construction teams of Chau Doc - Can Tho - Soc Trang expressway, urgently speeding up the progress.

People regret land while waiting for VSIP project to be constructed

TRẦN TUẤN |

Ha Tinh - After nearly 1 year of construction, the VSIP Ha Tinh Project still has many hectares of unpaved and abandoned rice fields, making farmers regret their land.