Requesting Gia Lai to speed up the construction progress of the 1,325 billion VND road

THANH TUẤN |

Gia Lai - Deputy Prime Minister Bui Thanh Son requested the province to direct the acceleration of the construction progress of the Eastern Economic Corridor.

On March 22, Deputy Prime Minister Bui Thanh Son and the working delegation had a working session with Gia Lai province to inspect the progress of the Eastern Economic Corridor project.

The Eastern Economic Corridor project connecting Dak Doa, Chu Pah, and Pleiku districts has a total length of 15.14km, with a total investment of 1,325 billion VND, expected to be completed in 2025.

Currently, the project has cleared 85% of the site, and the remaining 2.22km has not been handed over. Deputy Prime Minister Bui Thanh Son requested to speed up the site clearance progress before April 2025 and complete the route by the end of this year.

When completed, the project will contribute to promoting Gia Lai's socio-economic development, facilitating people and vehicles.

The Deputy Prime Minister and the working delegation also visited and worked at Vinh Hiep Company Limited, one of the leading coffee exporters in Vietnam today.

In 2024, the company achieved an export turnover of 520 million USD, accounting for nearly 80% of Gia Lai province's coffee export turnover. In just the first 3 months of 2025, the company's export value reached 300 million USD.

The Deputy Prime Minister highly appreciated coffee export activities, encouraged businesses to invest in technology, expand production and enhance their brands.

The Deputy Prime Minister also suggested that local governments support businesses in developing and promoting "three-house" cooperation including businesses, the state and the people.

THANH TUẤN
TIN LIÊN QUAN

Exceeding the construction progress of Chau Doc - Can Tho - Soc Trang expressway

|

Soc Trang - There have been 41 bridges under the Chau Doc - Can Tho - Soc Trang expressway component 4 project under construction, many bridges are ahead of schedule and are about to be completed.

Adjusting the plan, reviewing the construction site of the Western Expressway

|

Can Tho - Investors and contractors are adjusting the plan, reviewing the construction teams of Chau Doc - Can Tho - Soc Trang expressway, urgently speeding up the progress.

People regret land while waiting for VSIP project to be constructed

|

Ha Tinh - After nearly 1 year of construction, the VSIP Ha Tinh Project still has many hectares of unpaved and abandoned rice fields, making farmers regret their land.

Mental assessment: It is time to open the process, re-assess when necessary

|

36 officials of the Central Institute of Forensic Psychiatry were arrested for violations in the assessment, revealing a major loophole in the current process.

Hai Phong dried coconut specialties are in high demand like fresh shrimp on hot days

|

Hai Phong - During the peak hot weather, a refreshing specialty that many diners love in the port city is bean sprouts.

Moved when seeing a giant whale in the middle of Vinh Hy Bay for the first time

|

Ninh Thuan - The scene of whale hunting for prey in Vinh Hy sea received great attention from the tourism-loving community.

Taking his child to do high school graduation exam procedures, father in Binh Dinh died, child seriously injured

|

Binh Dinh - Father drove a motorbike carrying his son to the high school graduation exam preparation point when he suddenly crashed into an electric pole, causing him to die on the spot and seriously injuring his son.

Binh Duong officials and civil servants going to work in Ho Chi Minh City will have a car to pick them up and drop them off every day

|

Ho Chi Minh City plans to deploy 12 trips per day to pick up and drop off officials and civil servants from Binh Duong to the City for work.

Exceeding the construction progress of Chau Doc - Can Tho - Soc Trang expressway

PHƯƠNG ANH |

Soc Trang - There have been 41 bridges under the Chau Doc - Can Tho - Soc Trang expressway component 4 project under construction, many bridges are ahead of schedule and are about to be completed.

Adjusting the plan, reviewing the construction site of the Western Expressway

TẠ QUANG - YẾN PHƯƠNG |

Can Tho - Investors and contractors are adjusting the plan, reviewing the construction teams of Chau Doc - Can Tho - Soc Trang expressway, urgently speeding up the progress.

People regret land while waiting for VSIP project to be constructed

TRẦN TUẤN |

Ha Tinh - After nearly 1 year of construction, the VSIP Ha Tinh Project still has many hectares of unpaved and abandoned rice fields, making farmers regret their land.