Requesting Gia Lai to speed up the construction progress of the 1,325 billion VND road

THANH TUẤN |

Gia Lai - Deputy Prime Minister Bui Thanh Son requested the province to direct the acceleration of the construction progress of the Eastern Economic Corridor.

On March 22, Deputy Prime Minister Bui Thanh Son and the working delegation had a working session with Gia Lai province to inspect the progress of the Eastern Economic Corridor project.

The Eastern Economic Corridor project connecting Dak Doa, Chu Pah, and Pleiku districts has a total length of 15.14km, with a total investment of 1,325 billion VND, expected to be completed in 2025.

Currently, the project has cleared 85% of the site, and the remaining 2.22km has not been handed over. Deputy Prime Minister Bui Thanh Son requested to speed up the site clearance progress before April 2025 and complete the route by the end of this year.

When completed, the project will contribute to promoting Gia Lai's socio-economic development, facilitating people and vehicles.

The Deputy Prime Minister and the working delegation also visited and worked at Vinh Hiep Company Limited, one of the leading coffee exporters in Vietnam today.

In 2024, the company achieved an export turnover of 520 million USD, accounting for nearly 80% of Gia Lai province's coffee export turnover. In just the first 3 months of 2025, the company's export value reached 300 million USD.

The Deputy Prime Minister highly appreciated coffee export activities, encouraged businesses to invest in technology, expand production and enhance their brands.

The Deputy Prime Minister also suggested that local governments support businesses in developing and promoting "three-house" cooperation including businesses, the state and the people.

THANH TUẤN
RELATED NEWS

Exceeding the construction progress of Chau Doc - Can Tho - Soc Trang expressway

|

Soc Trang - There have been 41 bridges under the Chau Doc - Can Tho - Soc Trang expressway component 4 project under construction, many bridges are ahead of schedule and are about to be completed.

Adjusting the plan, reviewing the construction site of the Western Expressway

|

Can Tho - Investors and contractors are adjusting the plan, reviewing the construction teams of Chau Doc - Can Tho - Soc Trang expressway, urgently speeding up the progress.

People regret land while waiting for VSIP project to be constructed

|

Ha Tinh - After nearly 1 year of construction, the VSIP Ha Tinh Project still has many hectares of unpaved and abandoned rice fields, making farmers regret their land.

Female teacher suspended for impacting student's face right on the podium

|

Thai Nguyen - Teacher N.T.T.N was suspended for 15 days to verify and clarify the incident related to the video spread on social networks.

Lao Dong Newspaper presents Binh Ngo Tet Newspaper to forces tasked with protecting borders and islands

|

Hà Nội - Chiều 2.2, Báo Lao Động đã trao tặng 13.000 cuốn báo Tết cho các chiến sĩ Bộ đội biên phòng, Quân chủng Hải quân và Cảnh sát biển Việt Nam.

Artist Tan Bo's move in the face of information about borrowing hundreds of millions and not repaying

|

Before the information that musician To Hieu accused Tan Bo of borrowing hundreds of millions and not paying, the male artist sent a denunciation, asking functional agencies to intervene and clarify.

Vietnam deeply concerned about new US taxes related to Cuba

|

Vietnam is concerned about the US announcement of additional tariffs on goods from oil suppliers to Cuba.

Gold prices continue to decline, many stores temporarily stop selling

|

Ngày 2.2, giá vàng trong nước tiếp đà giảm sâu. Lượng khách giao dịch vàng tấp nập nhưng cửa hàng đưa ra thông báo bất ngờ.

Exceeding the construction progress of Chau Doc - Can Tho - Soc Trang expressway

PHƯƠNG ANH |

Soc Trang - There have been 41 bridges under the Chau Doc - Can Tho - Soc Trang expressway component 4 project under construction, many bridges are ahead of schedule and are about to be completed.

Adjusting the plan, reviewing the construction site of the Western Expressway

TẠ QUANG - YẾN PHƯƠNG |

Can Tho - Investors and contractors are adjusting the plan, reviewing the construction teams of Chau Doc - Can Tho - Soc Trang expressway, urgently speeding up the progress.

People regret land while waiting for VSIP project to be constructed

TRẦN TUẤN |

Ha Tinh - After nearly 1 year of construction, the VSIP Ha Tinh Project still has many hectares of unpaved and abandoned rice fields, making farmers regret their land.