17 days of sprinting before Long Thanh airport welcomes the first flight

ANH CHIẾN - ANH TÚ |

Dong Nai - With only 17 days left, the Long Thanh airport project must be basically completed, ensuring standards and conditions for inauguration and welcoming the first flight.

sprinting at the heart of the Long Thanh airport project

According to the schedule, the Long Thanh airport project must be basically completed, ensuring standards and conditions to be inaugurated on December 19, 2025.

Toan canh nha ga hanh khach san bay Long Thanh. Anh: Anh Tu
Panorama of Long Thanh airport passenger terminal. Photo: Anh Tu

On December 2, according to a reporter from Lao Dong Newspaper, in package 5.10 for the construction of the Long Thanh airport passenger terminal, the construction atmosphere was very urgent. This is the most important package of the entire project and is considered the heart of Long Thanh airport.

Thi cong he thong thang tai du an san bay Long Thanh. Anh: Anh Tu
Construction of the staircase system at the Long Thanh airport project. Photo: Anh Tu

Mr. Ngo Thanh Nghia - Commander of the elevator and escalator system construction in package 5.10 - Long Thanh airport passenger terminal said that the construction is being urgently implemented, closely following the plan on December 19, the work of installing mechanics, electricity, balancing, and operation is under construction "3 shifts, 4 teams" to complete and put into operation 108 elevators on all 3 wings of the terminal.

Worker Dang Ngoc Trieu said he has been working at the Long Thanh airport project since March 2025 and he is very proud to be working at the national key project, working with other workers to ensure progress.

Khong khi thi cong khan truong tai san bay Long Thanh. Anh: Anh Tu
Urgent construction atmosphere at Long Thanh airport. Photo: Anh Tu

According to Vietnam Airports Corporation (ACV), the project investor, to serve the construction of 12 packages, contractors are mobilizing nearly 14,000 experts, engineers, workers and more than 3,000 construction equipment, organizing hundreds of construction teams to speed up the progress with the goal of basically completing the project before December 19, 2025. With the high determination of contractors, the main packages of Component Project 3 and Long Thanh Airport Project are closely following the set schedule.

All packages and items must be completed before December 19

With package 4.7, airfield, according to ACV, the items will be completed before December 19, including the entire structure of the passenger terminal airfield; tunnel for ground clearance equipment; drainage system; lighting system for the airport area, taxiway and airfield lighting system.

Mai nha ga hanh khach san bay Long Thanh ruc ro trong nang thang 12 o tinh Dong Nai. Anh: Anh Tu
Long Thanh airport passenger terminal roof. Photo: Anh Tu

Meanwhile, with package 4.8, inland transportation and technical infrastructure, priority tuyenel routes have been basically completed to deploy the installation of equipment for water supply and drainage systems, electricity, ICT... At the same time, the main axis road items connecting passenger terminals, service routes to the exploitation service area of phase 1, station, and power supply will be completed before December 19.

Thi cong he thong ong long tai san bay Long Thanh. Anh: Anh Tu
Construction of the cage pipeline system at Long Thanh airport. Photo: Anh Tu

With package 5.10, construction of the passenger terminal, the most important package of the project, the construction and architecture part will meet the basic target of completion before December 19. Particularly for the construction items of the MEPF system (electricity, water, ventilation, fire prevention and fighting); ICT and TE (IT technology, terminal equipment) are being accelerated.

Ben trong nha ga hanh khach san bay Long Thanh. Anh: Anh Tu
Inside the Long Thanh airport passenger terminal. Photo: Anh Tu

In particular, the contractor consortium will complete the construction of cable pulling and connection to supply equipment for medium-voltage cabinets, low-voltage cabinets, electrical conductors, light cables (SCS system), fire alarm (FAS system), wind pipeline system, water supply, drainage... before December 19.

The installation of pipeline systems, fire pumping systems, and fire fighting systems will also be completed before the project's inauguration.

Regarding the construction of equipment for the passenger terminal, the installation of mechanical equipment for the luggage handling system (BHS); luggage screening systems for checked baggage (HBS), aircraft handling (VDGS), escalators, pedestrian elevators (ES/MW), elevators (EL) ... is expected to be completed in December 2025.

Along with that, 28/64 passenger bridges of Long Thanh airport terminal will be completed before December 19

Dai kiem soat khong luu san bay Long Thanh. Anh: Anh Tu
Long Thanh airport air traffic control tower. Photo: Anh Tu

For Component Project 2 - works serving flight management, Vietnam Air Traffic Management Corporation (VATM), the project investor, launched a 20-day competition to complete the project on schedule, ensuring readiness to serve technical flights and complete items on December 19 in accordance with the Prime Minister's direction.

According to Vietnam Airports Corporation (ACV), on December 19, Long Thanh airport will welcome the first flight from Hanoi to Long Thanh International Airport. The plane will roll into the completed terminal through the cable-stayed pipeline system, completing the inauguration procedures for the first phase of the project. December 19 is also the day to complete all packages and items.

Image of the atmosphere of Long Thanh airport construction on December 2, recorded by a reporter from Lao Dong newspaper:

h1
Three wings of Long Thanh airport
h2
The roof of Long Thanh airport terminal is in the shape of a lotus flower.
h3
Long Thanh airport passenger terminal system.
h4
Close-up of the construction of the airport terminal pipeline.
h5
Construction of traffic connecting to the airport.
h6
Urgent construction atmosphere with the target of December 19.
h7
Modern machinery and equipment are imported to the airport.
h8
signs at the passenger terminal.
h9
Construction of the station roof.
h10
Nearly 14,000 officers, engineers, workers and laborers are working day and night at the Long Thanh airport project.
h12
The construction is taking place urgently, but must ensure labor safety.
h13
Stair system at the passenger terminal.
h14
Sprinting before the inauguration day of Long Thanh airport.
ANH CHIẾN - ANH TÚ
RELATED NEWS

Establishment of Dong Nai Logistics Association to take advantage of Long Thanh airport

|

Dong Nai - Mr. Tran Thanh Hai - Deputy Director of the Immigration Department, Ministry of Industry and Trade - proposed to take advantage of Long Thanh airport to create a logistics ecosystem.

The 39 km long road in Dong Nai connecting Long Thanh airport is about to start construction

|

Dong Nai - The project to upgrade and expand DT 773 route, over 39km long, passes through 8 communes connecting Ho Chi Minh City Ring Road 4 and Long Thanh airport.

Long Thanh airport has a separate transformer station with a capacity of 80MVA, ready to supply power to the super project

|

Dong Nai - Dong Nai Power Company has successfully energized the plant installation of 2 110kV transformer stations at Long Thanh airport, increasing the total capacity to 80MVA.

Forecast of heavy rain in the provinces and cities from tonight, December 2 due to the cold air about to strengthen

|

It is forecasted that from tonight, Hue, Da Nang, and the eastern provinces from Quang Ngai to Dak Lak and Khanh Hoa will have heavy rain due to increased cold air.

The journey of a heart through Vietnam was transplanted to a 9-year-old boy in Ho Chi Minh City

|

HCMC - 3 hospitals activated the process of taking - transporting - transplanting hearts across Vietnam for a 9-year-old boy with end-stage heart failure, opening up new life opportunities for the child.

5 recommendations of the Standing Committee of the Central Committee of the Vietnam Fatherland Front

|

According to the Vietnam Fatherland Front, as of November 18, there have been 527,764 comments on the draft documents submitted to the 14th National Congress of the Party.

Cancer patients are being treated with expensive, very expensive drugs and need to be exempted from hospital fees immediately

|

National Assembly deputies recommended exempting hospital fees for cancer patients and serious illnesses immediately instead of waiting until 2030 as the roadmap.

Storm and flood destroy Gia Lai chrysanthemum village, struggling to save the Tet flower crop

|

Gia Lai - Storm and flood continue to destroy Tet flower gardens, chrysanthemum growers in Kien Long village (Binh An commune) are trying to save each bud, hoping to bring a warm and prosperous Tet season.

Establishment of Dong Nai Logistics Association to take advantage of Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - Mr. Tran Thanh Hai - Deputy Director of the Immigration Department, Ministry of Industry and Trade - proposed to take advantage of Long Thanh airport to create a logistics ecosystem.

The 39 km long road in Dong Nai connecting Long Thanh airport is about to start construction

HÀ ANH CHIẾN |

Dong Nai - The project to upgrade and expand DT 773 route, over 39km long, passes through 8 communes connecting Ho Chi Minh City Ring Road 4 and Long Thanh airport.

Long Thanh airport has a separate transformer station with a capacity of 80MVA, ready to supply power to the super project

NHƯ QUỲNH |

Dong Nai - Dong Nai Power Company has successfully energized the plant installation of 2 110kV transformer stations at Long Thanh airport, increasing the total capacity to 80MVA.