24 hours before site clearance for Ring Road 1

SÓNG HỮU |

Hanoi - Households in Giang Vo ward who deliberately do not hand over the land for the Ring Road 1 project will be forced to reclaim their land tomorrow (December 10).

According to Lao Dong on the afternoon of December 8 and the morning of December 9, most of the households subject to site clearance for the Ring Road 1 construction project, Hoang Cau - Voi Phuc section through Giang Vo ward, have completed the handover of the site to the project.

Some people renting premises for business and trading along the route are urgently moving assets and furniture to return the premises.

Many works within the site clearance area are also being demolished by machinery. The work was urgently deployed.

a
a
Many works are being demolished to serve the construction of the Ring Road 1 project, Hoang Cau - Voi Phuc section, on the afternoon of December 8. Photo: Song Huu

The project to build Ring Road 1, Hoang Cau - Voi Phuc section, is more than 2.2 km long, passing through 3 wards of O Cho Dua, Giang Vo and Lang. The project has a total investment of more than 7,200 billion VND, invested by the Hanoi Civil Works Construction Investment Project Management Board.

The project was approved in December 2017 and was expected to be completed in 2020, but was behind schedule due to land clearance problems.

Recently, under the strong direction of the Hanoi Party Committee and People's Committee, the project's site clearance work has recorded positive changes.

According to the direction of Hanoi Party Secretary Nguyen Duy Ngoc, by December 15 at the latest, the wards must complete site clearance to implement the project.

a
Most households in Giang Vo ward have handed over the land for the project. Photo: Song Huu
a
The work of clearing the scene was urgently deployed. Photo: Song Huu

In Giang Vo ward, the Ring Road 1 project through the area has a total of 795 site clearance plans. On November 21, the People's Committee of Giang Vo Ward completed the approval of 795/795 plans.

As of the afternoon of December 8, there were about 20 households in the ward that had not yet handed over the site, a decrease of nearly 80% compared to the number of households that had not yet handed over the site on December 4.

The ward continues propaganda, mobilization, and urging households to urgently relocate and hand over the site, minimizing the majority of households having to organize compulsory land recovery.

According to the plan, tomorrow morning (December 10), the authorities of Giang Vo ward and the city will simultaneously carry out compulsory land recovery to serve the site clearance of the Ring Road 1 project, Hoang Cau - Voi Phuc section for organizations and individuals using areas that have been decided to be reclaimed.

The authorities will organize the movement of all furniture and assets (if any) of individuals, households and organizations in the enforcement area to reclaim the entire site, including: Area of houses, land and construction works on the land according to the issued land recovery decisions.

After the recovery, the ward will hand over the site to the Hanoi Civil Works Construction Investment Project Management Board for receipt and management in accordance with the provisions of law.

The People's Committee of Giang Vo Ward said that the enforcement of land recovery will be carried out in accordance with the provisions of law; ensuring the safety of people, property, vehicles and forces participating in enforcement to handle violations, preventing unexpected incidents. The enforcement was completely implemented by Giang Vo ward and there was a plan to protect and ensure against re-offensive encroachment.

a
a
On December 10, Giang Vo ward will organize compulsory land recovery for households that deliberately do not hand over the site. Photo: Song Huu

Mr. Co Nhu Dung, Chairman of Giang Vo Ward People's Committee, requested units to grasp the security and order situation, ensure absolute safety, before, during and after enforcement; arrange appropriate forces, mobilize all necessary means to serve the enforcement work.

Mr. Dung also requested the arrangement of 24/24-hour citizen reception; continue to review the relocation progress of households that have signed land handover minutes; review households that deliberately do not hand over land, and include them in the list for enforcement.

SÓNG HỮU
RELATED NEWS

As the deadline approaches, some households have not yet handed over the land for the Ring Road 1 project

|

Hanoi - In O Cho Dua ward, there are 16 plans approved for compensation but people have not yet handed over the site for the Ring Road 1 project.

Site clearance for the Ring Road 1 project recorded many positive signals

|

Hanoi - Many households have agreed to hand over the land for the Ring Road 1 project before the authorities organize compulsory land recovery.

Hanoi cuts off electricity and water completely, prepares to enforce land acquisition for Ring Road 1

|

Hanoi - Giang Vo Ward will cut off electricity and water to households who deliberately do not hand over the land for the Ring Road 1 project on December 5, and will forcibly reclaim the land on December 10.

Strong cash flow into stocks, VN-Index surpasses the 1,900 point mark

|

The return of Vingroup stocks combined with large-cap stocks has helped the stock market indices set new highs.

Secretary of the Ho Chi Minh City Party Committee Tran Luu Quang is introduced to run for National Assembly deputy

|

Ho Chi Minh City - Mr. Tran Luu Quang - Secretary of the Party Central Committee, Secretary of the Ho Chi Minh City Party Committee was introduced as a candidate for the 16th National Assembly.

People's meeting right on the night of the garbage incident filling the streets in Thanh Hoa

|

Thanh Hoa - Regarding the incident of waste congestion and overflowing on the streets, functional agencies organized a people's meeting overnight, and proposed a handling plan.

Traffic Tao Chi Trung reveals the reason for being passionate about Dinh Bac and U23 Vietnam

|

Traffic Tao, Meritorious Artist Chi Trung said that he stayed up to watch the final group stage match between U23 Vietnam and U23 Saudi Arabia on the evening of January 12.

Mr. Trump declares 25% tax on countries doing business with Iran

|

The Trump administration is increasing trade pressure as Iranian tensions escalate along with a large wave of protests.

As the deadline approaches, some households have not yet handed over the land for the Ring Road 1 project

SÓNG HỮU |

Hanoi - In O Cho Dua ward, there are 16 plans approved for compensation but people have not yet handed over the site for the Ring Road 1 project.

Site clearance for the Ring Road 1 project recorded many positive signals

SÓNG HỮU |

Hanoi - Many households have agreed to hand over the land for the Ring Road 1 project before the authorities organize compulsory land recovery.

Hanoi cuts off electricity and water completely, prepares to enforce land acquisition for Ring Road 1

SÓNG HỮU |

Hanoi - Giang Vo Ward will cut off electricity and water to households who deliberately do not hand over the land for the Ring Road 1 project on December 5, and will forcibly reclaim the land on December 10.