VND2,500 billion to build a road connecting Dong Nai with the expressway to Ho Chi Minh City

HÀ ANH CHIẾN |

Dong Nai - The total investment of the Huong Lo 2 extension project, section 2 connecting to the Ho Chi Minh City - Long Thanh - Dau Giay Expressway is expected to be nearly 2,500 billion VND.

On February 19, according to information from the Dong Nai Province Traffic Construction Investment Project Management Board, this unit is taking steps to propose the investment policy for the extended Huong Lo 2 project, section 2, with a total length of about 5.2km.

The total estimated investment capital is nearly VND 2,500 billion, of which the construction cost is more than VND 1,400 billion, the site clearance cost for the completion phase with a width of 60m is nearly 999 billion VND.

Huong Lo 2 has a starting point intersecting with National Highway 51 and an ending point intersecting with the Ho Chi Minh City - Long Thanh - Dau Giay Expressway.

According to the plan, this will be a new traffic axis connecting Bien Hoa City with Ho Chi Minh City, shortening the distance and travel time, while contributing to reducing traffic volume on National Highway 51.

Currently, Huong Lo 2, section 1 from National Highway 51 to the intersection with the existing asphalt road (An Hoa - Long Hung road, Long Hung commune, Bien Hoa city) is under construction investment.

At the same time, Vam Cai Sut bridge on Huong Lo 2 has completed construction. However, with section 2 of Huong Lo 2, connecting from the border of Long Hung commune to the Ho Chi Minh City - Long Thanh - Dau Giay expressway, investment has not yet been implemented.

Section 2 of Huong Lo 2 includes 2 branches connecting from the border of Long Hung commune to the Ho Chi Minh City - Long Thanh - Dau Giay expressway.

HÀ ANH CHIẾN
TIN LIÊN QUAN

Vam Cai Sut Bridge without connecting road is a typical waste

|

Vam Cai Sut Bridge has a total investment of more than 387 billion VND, started construction in October 2020, is about to be completed but is at risk of having to "shelve" waiting for a connecting road.

2 bridge and road projects worth 1,170 billion VND in Dong Nai at risk of waste

|

Dong Nai - Huong Lo 2 extension (section 1) and Vam Cai Sut bridge with a total investment of 1,170 billion VND are at risk of being wasted due to lack of connecting roads.

Research on Vietnamese people playing casino after the pilot period

|

The Deputy Prime Minister requested to study special policies for the development of Phu Quoc Special Zone, allowing Vietnamese people to play casino after the pilot period.

Raising growth forecast for 2025, stocks welcome large cash flow

|

Many securities organizations and companies have increased their forecasts for Vietnam's GDP growth in 2025. The stock market flourished, large-cap stocks led the increase.

Continue to reorganize mass organizations assigned by the Party and the State

|

The Party Committee of the Vietnam Fatherland Front and Central organizations will lead and direct the continued reorganization of mass associations assigned by the Party and State to operate under the Vietnam Fatherland Front, in the direction of reducing the number, streamlining the internal apparatus, and operating practically and effectively.

Buying Vietlott lottery on the day of giving birth, a worker won more than 16 billion VND

|

A man has just received the Vietlott Jackpot 2 lottery draw Power 6/55 QSMT No. 01210 with a value of more than 16 billion VND.

Mr. Thaksin declares belief in the integrity of Paetongtarn's daughter

|

Former Thai Prime Minister Thaksin Shinawatra shared his views on the situation in Thailand and the suspension of his daughter, Ms. Paetongtarn, from the position of Prime Minister.

There have been conclusions about the person who shot down the MH17 passenger plane

|

The Malaysia MH17 plane crash due to shelling in 2014, with 298 passengers on board, has been determined.

Vam Cai Sut Bridge without connecting road is a typical waste

Lê Thanh Phong |

Vam Cai Sut Bridge has a total investment of more than 387 billion VND, started construction in October 2020, is about to be completed but is at risk of having to "shelve" waiting for a connecting road.

2 bridge and road projects worth 1,170 billion VND in Dong Nai at risk of waste

HÀ ANH CHIẾN |

Dong Nai - Huong Lo 2 extension (section 1) and Vam Cai Sut bridge with a total investment of 1,170 billion VND are at risk of being wasted due to lack of connecting roads.

Hiện trạng cầu Vàm Cái Sứt gần 400 tỉ đồng ở Đồng Nai sau 3 năm khởi công

HÀ ANH CHIẾN |

Đồng Nai - Dự án cầu Vàm Cái Sứt có tổng vốn đầu tư hơn 387 tỉ đồng đã khởi công từ tháng 10.2020, đến nay đã gần 3 năm dự án đang bước vào giai đoạn cuối chuẩn bị hợp long và hoàn thành phần cầu chính trong tháng 12.2023.