VND2,500 billion to build a road connecting Dong Nai with the expressway to Ho Chi Minh City

HÀ ANH CHIẾN |

Dong Nai - The total investment of the Huong Lo 2 extension project, section 2 connecting to the Ho Chi Minh City - Long Thanh - Dau Giay Expressway is expected to be nearly 2,500 billion VND.

On February 19, according to information from the Dong Nai Province Traffic Construction Investment Project Management Board, this unit is taking steps to propose the investment policy for the extended Huong Lo 2 project, section 2, with a total length of about 5.2km.

The total estimated investment capital is nearly VND 2,500 billion, of which the construction cost is more than VND 1,400 billion, the site clearance cost for the completion phase with a width of 60m is nearly 999 billion VND.

Huong Lo 2 has a starting point intersecting with National Highway 51 and an ending point intersecting with the Ho Chi Minh City - Long Thanh - Dau Giay Expressway.

According to the plan, this will be a new traffic axis connecting Bien Hoa City with Ho Chi Minh City, shortening the distance and travel time, while contributing to reducing traffic volume on National Highway 51.

Currently, Huong Lo 2, section 1 from National Highway 51 to the intersection with the existing asphalt road (An Hoa - Long Hung road, Long Hung commune, Bien Hoa city) is under construction investment.

At the same time, Vam Cai Sut bridge on Huong Lo 2 has completed construction. However, with section 2 of Huong Lo 2, connecting from the border of Long Hung commune to the Ho Chi Minh City - Long Thanh - Dau Giay expressway, investment has not yet been implemented.

Section 2 of Huong Lo 2 includes 2 branches connecting from the border of Long Hung commune to the Ho Chi Minh City - Long Thanh - Dau Giay expressway.

HÀ ANH CHIẾN
RELATED NEWS

Vam Cai Sut Bridge without connecting road is a typical waste

|

Vam Cai Sut Bridge has a total investment of more than 387 billion VND, started construction in October 2020, is about to be completed but is at risk of having to "shelve" waiting for a connecting road.

2 bridge and road projects worth 1,170 billion VND in Dong Nai at risk of waste

|

Dong Nai - Huong Lo 2 extension (section 1) and Vam Cai Sut bridge with a total investment of 1,170 billion VND are at risk of being wasted due to lack of connecting roads.

La Nina has passed its peak, the world weather is facing new changes

|

After two consecutive weak La Nina winters, meteorologists believe that the global weather pattern may be entering a transitional phase.

Parents still have a heavy burden of tuition fees, studying outside of school

|

Many parents are still having to bear the significant costs arising from their children's education.

Thailand and Cambodia speak out together about the F-16 plane that crashed a civil bridge

|

The Thai Air Force used an F-16 fighter jet to attack a civil bridge believed to be related to Cambodia's arms and military transport activities.

Ukraine points out a single ally capable of ending the conflict

|

The Ukrainian leader affirmed that partners from Europe or China cannot replace the US leadership role at the negotiation table.

Teachers and staff of school contracts hope to receive bonuses according to Decree 73

|

Nghe An - Many teachers and contract staff expressed their desire to be considered for bonus benefits according to Decree 73.

seasonal flu broke out early, influenza A/H3N2 K virus is behind 90% of cases

|

Influenza A/H3N2 K is a influenza virus strain that is behind 90% of cases.

Vam Cai Sut Bridge without connecting road is a typical waste

Lê Thanh Phong |

Vam Cai Sut Bridge has a total investment of more than 387 billion VND, started construction in October 2020, is about to be completed but is at risk of having to "shelve" waiting for a connecting road.

2 bridge and road projects worth 1,170 billion VND in Dong Nai at risk of waste

HÀ ANH CHIẾN |

Dong Nai - Huong Lo 2 extension (section 1) and Vam Cai Sut bridge with a total investment of 1,170 billion VND are at risk of being wasted due to lack of connecting roads.

Hiện trạng cầu Vàm Cái Sứt gần 400 tỉ đồng ở Đồng Nai sau 3 năm khởi công

HÀ ANH CHIẾN |

Đồng Nai - Dự án cầu Vàm Cái Sứt có tổng vốn đầu tư hơn 387 tỉ đồng đã khởi công từ tháng 10.2020, đến nay đã gần 3 năm dự án đang bước vào giai đoạn cuối chuẩn bị hợp long và hoàn thành phần cầu chính trong tháng 12.2023.