4 delayed bridge, road and tunnel projects in Ho Chi Minh City are about to reach the finish line

MINH QUÂN |

HCMC - Nam Ly Bridge, Ong Bon Bridge, Long Phuoc Street, and Nguyen Van Linh - Nguyen Huu Tho underpass branch will be open to traffic at the end of September after many years of delays.

After more than a year of restarting, the Nam Ly Bridge project , with an investment capital of VND732 billion, has completed more than 95% of the volume and is expected to open to traffic at the end of September, instead of mid-month as originally planned. The main reason for the delay is due to prolonged rainy weather, affecting the construction and asphalt paving.

After the opening, the construction unit will close the existing side road to continue carrying out auxiliary works and constructing the residential access road. The entire Nam Ly Bridge project is expected to be completed by the end of this year.

Nam Ly Bridge's opening date has been postponed to the end of September. Photo: Anh Tu
Nam Ly Bridge's opening date has been postponed to the end of September. Photo: Anh Tu

The bridge is nearly 450m long and 20m wide, with two ends connecting to a 30-37m wide approach road. This project replaces the old and narrow Rach Chiec dam bridge, which was a "bottleneck" that hindered traffic on Do Xuan Hop Street.

The Nam Ly Bridge project started in 2016, but due to land acquisition issues, the progress was delayed and only 40% of the volume was completed in 2019. After that, the project was suspended until March 2023, when compensation and site clearance were completed and construction was restarted.

Ong Bong Bridge
Ong Bon Bridge on Bung Ong Thoan Street. Photo: Anh Tu

Ong Bon Bridge , another project in Thu Duc City, will open one branch to traffic at the end of September. After this branch is completed, the existing bridge will be dismantled to construct the remaining branch. This project started in 2018 with a total investment of 30 billion VND.

The opening of Ong Bon Bridge will resolve traffic congestion on Bung Ong Thoan Street, helping to improve traffic and facilitate freight transport activities in the area.

Long Phuoc Street connects to Long Dai Bridge, in front is Vinhome Grand Park residential area. Photo: Minh Quan
Long Phuoc Street connects to Long Dai Bridge, in front is Vinhome Grand Park residential area. Photo: Minh Quan

Long Phuoc Road , an important route connecting to Long Dai Bridge (Thu Duc City), is also expected to open to traffic at the end of September. Long Phuoc Road is nearly 6km long and will be widened to 9-12m.

The Long Phuoc road upgrade project has a total investment of more than 260 billion VND, of which construction and installation costs account for only about 75 billion VND, the rest is mainly for compensation and site clearance.

The project started construction at the end of 2017 but encountered many difficulties in compensation, causing the progress to drag on until near the end of 2022 before restarting.

Nguyen Van Linh - Nguyen Huu Tho underpass. Photo: Anh Tu
Nguyen Van Linh - Nguyen Huu Tho underpass. Photo: Anh Tu

At the southern gateway, the HC2 underpass (from District 7 to Binh Chanh) at the Nguyen Van Linh – Nguyen Huu Tho intersection will be opened to traffic at the end of September. Initially, this tunnel was scheduled to be completed on September 15, but due to prolonged heavy rain, the contractor had to delay the opening to ensure the quality of the project.

When completed, the HC2 tunnel branch will not only reduce traffic pressure but also facilitate the construction of the HC1 branch in the opposite direction, from Binh Chanh to District 7. According to plan, this tunnel branch and related items will also be completed by the end of this year.

The Nguyen Van Linh - Nguyen Huu Tho intersection underpass project started construction in April 2020, with a total investment of VND 830 billion (phase one). The project includes two tunnels in each direction of Nguyen Van Linh Street, each tunnel is 456 m long, with 3 lanes.

MINH QUÂN
RELATED NEWS

TPHCM thông xe đường rộng 40m ở Bình Tân sớm 3 tháng

MINH QUÂN |

TPHCM - Đoạn đường Tên Lửa (quận Bình Tân) rộng 40m, 6 làn xe đã chính thức thông xe, vượt 3 tháng so với kế hoạch.

TPHCM thông cầu 500 tỉ đồng nối huyện Nhà Bè và Bình Chánh

MINH QUÂN |

TPHCM - Ngày 30.8, UBND huyện Nhà Bè đã chính thức thông xe cầu Cây Khô, nối liền hai huyện Nhà Bè và Bình Chánh.

Cầu huyết mạch phía Đông TPHCM chạy nước rút thông xe

MINH QUÂN |

TPHCM - Cầu Nam Lý trên đường Đỗ Xuân Hợp (TP Thủ Đức) đã đạt 93% khối lượng và dự kiến thông xe ngày 15.9 tới.

Trạm bơm tiền tỉ, chưa nghiệm thu đã thanh toán tiền rồi bỏ hoang hơn 4 năm

PHÚC ĐẠT |

Công trình trạm bơm trị giá 1,5 tỉ đồng ở xã Hương Phong (TP Huế) bị bỏ hoang hơn 4 năm nay, điều đáng nói, khi công trình chưa thể hoạt động, chưa nghiệm thu, chủ đầu tư là UBND xã Hương Phong đã đem tiền đi thanh toán cho đơn vị thi công.

Xây dựng Nhà nước pháp quyền xã hội chủ nghĩa là nguyện vọng của nhân dân

VƯƠNG TRẦN thực hiện |

Bài viết “Phát huy tính đảng trong xây dựng Nhà nước pháp quyền xã hội chủ nghĩa Việt Nam” của Tổng Bí thư Tô Lâm đang nhận được nhiều sự quan tâm và đồng tình của dư luận. Lao Động có cuộc trao đổi cùng PGS.TS Vũ Văn Phúc - Phó Chủ tịch Hội đồng Khoa học các cơ quan Đảng Trung ương - về các nội dung liên quan tới bài viết của Tổng Bí thư Tô Lâm.

Người dân sống thấp thỏm sau vụ vỡ đập bùn thải ở Bắc Kạn

Ngọc Minh |

Vụ vỡ đập bùn thải chứa kẽm chì ở huyện Chợ Đồn (Bắc Kạn) để lại hậu quả nặng nề về môi trường, khiến cuộc sống của người dân địa phương bị đảo lộn.

Bản tin công đoàn: Tuổi nghỉ hưu năm 2025 của người lao động

Nhóm PV |

Bản tin công đoàn có những nội dung: Tuổi nghỉ hưu năm 2025 của người lao động; Trên 66.500 lao động nghỉ việc, nhảy việc ở Bình Dương...

NATO phản ứng việc Thổ Nhĩ Kỳ muốn gia nhập BRICS

Song Minh |

Nước thành viên NATO Thổ Nhĩ Kỳ đã chính thức nộp đơn xin gia nhập BRICS.

TPHCM thông xe đường rộng 40m ở Bình Tân sớm 3 tháng

MINH QUÂN |

TPHCM - Đoạn đường Tên Lửa (quận Bình Tân) rộng 40m, 6 làn xe đã chính thức thông xe, vượt 3 tháng so với kế hoạch.

TPHCM thông cầu 500 tỉ đồng nối huyện Nhà Bè và Bình Chánh

MINH QUÂN |

TPHCM - Ngày 30.8, UBND huyện Nhà Bè đã chính thức thông xe cầu Cây Khô, nối liền hai huyện Nhà Bè và Bình Chánh.

Cầu huyết mạch phía Đông TPHCM chạy nước rút thông xe

MINH QUÂN |

TPHCM - Cầu Nam Lý trên đường Đỗ Xuân Hợp (TP Thủ Đức) đã đạt 93% khối lượng và dự kiến thông xe ngày 15.9 tới.