The amount of disbursed capital is quite modest
According to Lao Dong's records, 4 key projects in the Capital are being actively implemented by localities, handing over the premises to construct the entire project. However, the amount of disbursed capital in these projects is still quite modest.
At the Ring Road 4 project - Capital Region, after one year of construction, the shape of this "super project" has become clear. The construction item that has progressed most clearly is the parallel road item (component project 2.1) passing through districts in Hanoi. The construction contractors of component 2.1 project have gathered human resources and vehicles, working without days off on the construction sites, determined to complete the assigned schedule.
As for the Ring Road 4 package, the section passing through Kim Hoa commune (Me Linh district), the construction unit has completed the roadbed soil embankment (K98), compensated for subsidence and spread more than 1km of crushed stone gravel. 1. At the same time, workers also construct bridge piers and install beams.
According to newly released data from the Hanoi Department of Statistics, Ring Road 4 - Capital Region passes through 3 provinces and cities (Hanoi, Hung Yen and Bac Ninh), connecting the Hanoi - Lao Cai expressway and Noi Bai - Ha Long has a length of 112.8km with a total investment of phase 1 of about 85.8 trillion VND. Up to this point, the total investment capital for the project is about 12.6 trillion VND, construction progress has reached 9.9% of the volume.
At the Ring Road 1 project, section Hoang Cau - Voi Phuc (phase 1), with a length of 2.3km, cross section of 50m and component of 2 overpasses at Lang Ha - Nguyen Chi Thanh intersection. The starting point of the route intersects with Cat Linh - La Thanh - Yen Lang road at Hoang Cau (Dong Da district), the ending point is at Voi Phuc intersection (Ba Dinh district). The investment in phase 1 of the project is more than 7.2 trillion VND from the city budget, of which construction costs are 627 billion VND and site clearance costs are 5.8 trillion VND. To date, the project has disbursed 34.1% of the capital plan.
At the project to renovate and upgrade National Highway 6 section from Ba La intersection (Ha Dong) to Xuan Mai town (Chuong My district), construction will start in 2022 and is expected to be completed in 2027, with a total cost of over 8,100 VND. billion. Of which, site clearance costs are more than 5,000 billion VND; Construction and equipment costs are more than 2,900 billion VND.
According to reporters, the project has been under construction for 2 years but progress has been sluggish. Along the route, only the section passing through Phu Nghia commune, Chuong My district has been paved and paved with stones on the roadbed surface. Currently, there are 7 road bridges and 1 newly built box culvert on the route. Among them, Tan Truong bridge (Xuan Mai town, Chuong My district) is under construction, with both sides of the bridge abutments completed.
This section will be upgraded to 4-6 lanes, design speed 80km/h, roadbed width opened 50-60m, contributing to completing the radial road connecting National Highway 21A, Ho Chi Minh Road and Ho Chi Minh City. Ring Road 4 - Capital Region. To date, the project has disbursed 7.7% of the capital plan.
The project is at risk of delay due to land problems
As for the Thang Long Highway, the section connecting National Highway 21 to the Hanoi - Hoa Binh Expressway, after nearly 9 months of construction, the project is only in the construction phase of the first items. The reason for the delay is lack of space.
Mr. Do Viet Hung - Deputy Director of the Project Management Board of Hanoi City Civil Construction Investment Project - said that the route was implemented with a total area of land acquisition and clearance of about 105.8 hectares, a total cost of Invest 5,249 billion VND. However, by April 2024, the unit had only received about 7/105 hectares, accounting for less than 7% of the construction area.
According to the Hanoi Department of Statistics, the project has a length of 6.7km, the first point connects Thang Long Highway with National Highway 21, Thach Hoa commune, Thach That district, the last point connects to Hoa Lac - Peace; Cross section from 120m - 180m. To date, the project has disbursed 7.7% of the capital plan.