5 completed expressways connecting Ho Chi Minh City - Nha Trang

Hữu Long |

There are 4 expressways in operation from Ho Chi Minh City to Nha Trang. There is one project ahead of schedule, the Van Phong - Nha Trang expressway, bringing the total number of completed routes to 5.

The Ministry of Transport and Project Management Board 7 - the investor of the Van Phong - Nha Trang expressway project have received documents from contractors including Son Hai Group Co., Ltd., Vietnam Construction and Import-Export Joint Stock Corporation - Vinaconex, and LIZEN Joint Stock Company.

The content of the above document proposes to put into operation 68.35km, connecting from Nha Trang - Cam Lam expressway to Van Gia intersection, belonging to Van Phong - Nha Trang project before January 10, 2025.

According to the initial schedule, the project will be completed and put into operation by the end of 2025.

Cao toc Van Phong - Nha Trang hien da vuot tien do so voi du kien. Anh: Huu Long
The Van Phong - Nha Trang Expressway is currently ahead of schedule. Photo: Huu Long

However, the contractor consortium is currently working ahead of schedule. The contractor consortium affirmed that it will complete the entire project (including the service road, branch road...) of the 68.35km long route, from Van Gia intersection connecting to Nha Trang - Cam Lam expressway before January 10, 2025.

To put the project into operation soon, promote investment efficiency and especially serve people's travel needs during the Lunar New Year, the contractor consortium has requested the Ministry of Transport and Project Management Board 7 to have a plan and direct relevant units to complete the necessary procedures.

Currently, there are 4 expressways operating from Ho Chi Minh City to Nha Trang City. They are Ho Chi Minh City - Long Thanh - Dau Giay, Dau Giay - Phan Thiet, Phan Thiet - Vinh Hao, Cam Lam - Nha Trang.

If approved by the Ministry of Transport, the Van Phong - Nha Trang Expressway will be the fifth component expressway to come into operation. The connection of these five expressways will contribute to promoting socio-economic development in the South Central provinces and Ho Chi Minh City, shortening travel time and reducing traffic pressure on National Highway 1A.

Hữu Long
RELATED NEWS

Van Phong - Nha Trang Expressway completed 8 months ahead of schedule

|

The Van Phong - Nha Trang expressway project will start construction in early 2023 with Project Management Board 7 as the investor, with a total capital of nearly 12,000 billion VND, striving to finish 8 months ahead of schedule.

Investing 230 billion VND to build a rest stop on Van Phong - Nha Trang highway

|

Khanh Hoa - The investor is bidding to find an investor to implement the rest stop project on the Van Phong - Nha Trang highway with a total investment of more than 230 billion VND.

Subsidies for non-specialized commune-level officials who quit their jobs at the end of their activities

|

The Legal Advice Program will analyze the regulations on regimes for non-specialized commune-level officials before the end of the campaign.

Appointment of Chief Justices and Chief Justices in Ho Chi Minh City, Da Nang, and Ca Mau

|

During the week, the court sector recorded the appointment of Chief Justices of regional courts, Chief Justices, Chief Courtiers of appellate courts at the People's Courts of Ho Chi Minh City, Da Nang, and Ca Mau.

Male student in Ninh Binh ganged up on: Family requests 90 million VND in compensation

|

Ninh Binh - Regarding the case of a 9th grade male student being ganged up on, the victim's family requested 90 million VND in compensation.

Alcohol concentration violations account for a high proportion during the April 30 - May 1 holiday

|

During the April 30 - May 1 holiday, alcohol concentration violations continued to account for a high proportion of the total number of traffic order and safety violations nationwide.

Van Phong - Nha Trang Expressway completed 8 months ahead of schedule

Hữu Long |

The Van Phong - Nha Trang expressway project will start construction in early 2023 with Project Management Board 7 as the investor, with a total capital of nearly 12,000 billion VND, striving to finish 8 months ahead of schedule.

Investing 230 billion VND to build a rest stop on Van Phong - Nha Trang highway

Hữu Long |

Khanh Hoa - The investor is bidding to find an investor to implement the rest stop project on the Van Phong - Nha Trang highway with a total investment of more than 230 billion VND.

Cao tốc Vân Phong - Nha Trang vượt tiến độ, băng băng về đích

Hữu Long |

Khánh Hòa - Dự án cao tốc Vân Phong - Nha Trang vượt tiến độ so với kế hoạch, dự kiến về đích trước 6 tháng.