5 completed expressways connecting Ho Chi Minh City - Nha Trang

Hữu Long |

There are 4 expressways in operation from Ho Chi Minh City to Nha Trang. There is one project ahead of schedule, the Van Phong - Nha Trang expressway, bringing the total number of completed routes to 5.

The Ministry of Transport and Project Management Board 7 - the investor of the Van Phong - Nha Trang expressway project have received documents from contractors including Son Hai Group Co., Ltd., Vietnam Construction and Import-Export Joint Stock Corporation - Vinaconex, and LIZEN Joint Stock Company.

The content of the above document proposes to put into operation 68.35km, connecting from Nha Trang - Cam Lam expressway to Van Gia intersection, belonging to Van Phong - Nha Trang project before January 10, 2025.

According to the initial schedule, the project will be completed and put into operation by the end of 2025.

Cao toc Van Phong - Nha Trang hien da vuot tien do so voi du kien. Anh: Huu Long
The Van Phong - Nha Trang Expressway is currently ahead of schedule. Photo: Huu Long

However, the contractor consortium is currently working ahead of schedule. The contractor consortium affirmed that it will complete the entire project (including the service road, branch road...) of the 68.35km long route, from Van Gia intersection connecting to Nha Trang - Cam Lam expressway before January 10, 2025.

To put the project into operation soon, promote investment efficiency and especially serve people's travel needs during the Lunar New Year, the contractor consortium has requested the Ministry of Transport and Project Management Board 7 to have a plan and direct relevant units to complete the necessary procedures.

Currently, there are 4 expressways operating from Ho Chi Minh City to Nha Trang City. They are Ho Chi Minh City - Long Thanh - Dau Giay, Dau Giay - Phan Thiet, Phan Thiet - Vinh Hao, Cam Lam - Nha Trang.

If approved by the Ministry of Transport, the Van Phong - Nha Trang Expressway will be the fifth component expressway to come into operation. The connection of these five expressways will contribute to promoting socio-economic development in the South Central provinces and Ho Chi Minh City, shortening travel time and reducing traffic pressure on National Highway 1A.

Hữu Long
TIN LIÊN QUAN

Van Phong - Nha Trang Expressway completed 8 months ahead of schedule

|

The Van Phong - Nha Trang expressway project will start construction in early 2023 with Project Management Board 7 as the investor, with a total capital of nearly 12,000 billion VND, striving to finish 8 months ahead of schedule.

Investing 230 billion VND to build a rest stop on Van Phong - Nha Trang highway

|

Khanh Hoa - The investor is bidding to find an investor to implement the rest stop project on the Van Phong - Nha Trang highway with a total investment of more than 230 billion VND.

Gloomy scene, empty space on a big love street in Ho Chi Minh City

|

It is currently the peak wedding season, but Ho Van Hue Street - a street specializing in wedding services in Ho Chi Minh City - is deserted, with many premises left empty.

Gold price today 12/21: Widening gap, risk of loss

|

Gold price today 12/21: All increased. The difference between buying and selling plain gold rings is widening, causing buyers to face a higher risk of loss.

The decision of a state official to quit his job at the age of 42

|

After nearly 15 years as a civil servant, Ms. Ngo Thi Thuy Ha decided to quit her job and apply to work at a private enterprise when she was 42 years old.

Defense Exhibition has nearly 100,000 registrations to visit

|

Vietnam International Defense Exhibition 2024 welcomes people and visitors from 9:00 a.m. this morning, December 21, to 3:00 p.m. on December 22.

The large amount of money that Bich Tuyen and her husband supported Dam Vinh Hung

|

It is known that in addition to the money to support Dam Vinh Hung's hospitalization, singer Bich Tuyen and her husband also sponsored the male singer's shows.

Ministry of Home Affairs receives and processes more than 500 complaints in 2024

|

As of November 15, 2024, the Ministry of Home Affairs has received and processed 1,516 petitions, including 502 denunciations, 238 complaints, and 776 petitions.

Van Phong - Nha Trang Expressway completed 8 months ahead of schedule

Hữu Long |

The Van Phong - Nha Trang expressway project will start construction in early 2023 with Project Management Board 7 as the investor, with a total capital of nearly 12,000 billion VND, striving to finish 8 months ahead of schedule.

Investing 230 billion VND to build a rest stop on Van Phong - Nha Trang highway

Hữu Long |

Khanh Hoa - The investor is bidding to find an investor to implement the rest stop project on the Van Phong - Nha Trang highway with a total investment of more than 230 billion VND.

Cao tốc Vân Phong - Nha Trang vượt tiến độ, băng băng về đích

Hữu Long |

Khánh Hòa - Dự án cao tốc Vân Phong - Nha Trang vượt tiến độ so với kế hoạch, dự kiến về đích trước 6 tháng.