876m of road in Quang Ngai has been built for 9 years and still not finished

VIÊN NGUYỄN |

The Chu Van An road project in Quang Ngai city - the section from Hai Ba Trung to Ngo Si Lien is 876m long, but after 9 years of construction, it is still unfinished.

Investor lacks expertise

The project started in 2012, when the People's Committee of Quang Ngai province decided to invest in the Chu Van An road project (connecting Hai Ba Trung - Hung Vuong road) and Nam Hai Ba Trung residential area with a total investment of about 320 billion VND.

The project was initially assigned to the People's Committee of Quang Ngai City as the investor. In 2015, the People's Committee of Quang Ngai Province transferred both the road and the residential area to Quang Ngai Investment, Construction and Service Trading Company Limited (QISC) as the investor. After officially starting in 2016, the 876m road began construction, but in 2020, the People's Committee of Quang Ngai Province transferred the project to Quang Ngai City as the investor.

According to the conclusion of the Quang Ngai Provincial Inspectorate in 2023, the reason for the delay in the project is that there is no regulation allowing QISC Company to be assigned to manage and use State budget capital to invest in and construct works and residential areas that the company will later manage and exploit. Therefore, the transfer from the Provincial People's Committee Chairman of Quang Ngai City to QISC Company as the investor of the Hai Ba Trung Southern Residential Area project and the Chu Van An Road project (from Hung Vuong to Hai Ba Trung) has no legal basis and is not in accordance with the functions and tasks of the company. The fact that QISC Company organized the work of preparing the compensation plan itself but lacked experience and expertise led to delays in compensation work, so the project progress was not implemented on schedule and the project progress had to be adjusted.

Many violations

Also according to the conclusion of the Quang Ngai Provincial Inspectorate in 2023, QISC Company, the investor from 2015 to 2020, did not have the capacity to manage and implement the project; did not have expertise in preparing compensation and resettlement plans to implement the project, leading to many violations. QISC Company, the Provincial Land Fund Development Center, and the Quang Ngai City Land Fund Development and Investment Management Board lacked coordination and were not resolute in implementing the project, leading to the project not being completed.

Du an duong Chu Van An o TP Quang Ngai - doan tu duong Hai Ba Trung - Ngo Si Lien hien dang trong tinh trang nang bui mua bun khien nguoi dan ngan ngam. Anh: Vien Nguyen
The Chu Van An road project in Quang Ngai City - the section from Hai Ba Trung to Ngo Si Lien streets is currently in a state of dusty sun and muddy rain. Photo: Vien Nguyen

Speaking to Lao Dong Newspaper reporters, a representative of the Quang Ngai City Land Fund Development and Investment Project Management Board said that the above project has only had an inspection conclusion for the site clearance compensation and construction part of QISC Company. As for the planning work, the Provincial Inspectorate has not yet concluded because the Provincial Inspectorate is inspecting Quang Ngai City on all detailed planning projects 1/500, including the above project. Therefore, we have to wait for the Provincial Inspectorate to conclude on the planning, then the Department of Construction will consider the content of the request to adjust the project implementation time, so for now, the implementation of the above project must be stopped.

VIÊN NGUYỄN
RELATED NEWS

Trillions of Dong in projects in Quang Ngai waiting for disbursement

|

The implementation of many large projects in Quang Ngai is facing difficulties due to land acquisition problems, leading to stagnant progress, with more than a thousand billion VND waiting for disbursement.

Authorities wade through deep mud and landslides to reach isolated people in Da Nang

|

Da Nang - Hung Son Commune People's Committee said Ch'Noc village is completely isolated. The authorities wade through deep mud, crossing the isolated terrain to reach the people.

Judicial records information on VNeID is as valuable as a criminal record

|

The Minister of Public Security said that he will revise the draft in the direction that citizens' criminal records information is updated and displayed on VNeID.

The Minister of Public Security clarifies the proposal to install cameras in the passenger compartment of cars

|

The Minister of Public Security emphasized that the regulation on installing cameras in passenger cabin only applies to commercial vehicles for transportation, not to private vehicles.

The driver was swept away while driving a tractor-trailer overflooding with floodwater and has not been found

|

Quang Tri - The driver of a tractor-trailer residing in Ba Don ward carrying coal from the border gate to the inland border crossed a fence to cross a flooded bridge and was swept away.

Billionaire Pham Nhat Vuong's assets increased sharply, exceeding 20 billion USD

|

The net assets of billionaire Pham Nhat Vuong, Chairman of Vingroup Corporation, increased sharply, up to 20.1 billion USD, ranking 121st on the ranking of the richest people on the planet.

Proposal to regulate the sale of national reserve goods for national defense and security

|

National reserve goods for national defense and security are only sold for the national defense and security sector, including direct enterprises.

Floodwaters rise, many households in Khanh Hoa climb to the roofs to pray for help

|

Khanh Hoa - Prolonged heavy rain caused many areas in the whole province to be submerged in floodwater. Many households were isolated and had to climb to the roofs to pray for help.

64 trụ điện ở Quảng Ngãi xây dựng trái phép 7 năm... chưa dỡ

Viên Nguyễn |

Công ty Cổ phần Thủy điện Đạt Phương Sơn Trà đã xây dựng 64 trụ điện 110kV trái phép. Sau 7 năm hoạt động, các trụ điện này vẫn chưa được cơ quan chức năng chuyển mục đích sử dụng, giao và cho thuê đất.

Trillions of Dong in projects in Quang Ngai waiting for disbursement

VIÊN NGUYỄN |

The implementation of many large projects in Quang Ngai is facing difficulties due to land acquisition problems, leading to stagnant progress, with more than a thousand billion VND waiting for disbursement.

Đập dâng 1.500 tỉ đồng ở Quảng Ngãi thiếu mặt bằng thi công

VIÊN NGUYỄN |

Dự án đập dâng hạ lưu sông Trà Khúc ở Quảng Ngãi, có tổng vốn đầu tư 1.500 tỉ đồng hiện không có mặt bằng để thi công.