The secret for mountainous districts to disburse nearly 80% of public investment capital

Đặng Tình |

Hoa Binh - Construction projects in Kim Boi district are being accelerated to ensure the disbursement plan for public investment capital.

On October 10, the Kim Boi District Construction Project Management Board announced that the unit was assigned to manage and implement 100 projects with a total investment of VND 1,187 billion (including projects in previous years). The capital allocated in 2024 is more than VND 203 billion, of which VND 157 billion has been disbursed, reaching over 77% of the plan.

Accordingly, there are 13 new projects starting construction in 2024 using district budget capital, with a total investment of 101 billion VND. The projects have signed contracts and handed over the site for construction contractors.

Transitional projects, including 75 projects with district budget capital, with a total investment of 763 billion VND, the total capital granted in 2024 is 131 billion VND, disbursed 119.5 billion VND, reaching 90.7%; 11 projects with additional targeted provincial budget capital and 1 project with central budget capital, with a total investment of 322 billion VND, the total capital granted in 2024 is 31 billion VND, disbursed 17 billion VND, reaching 53.7%.

In October, in Nam Thuong commune (striving to reach the advanced new rural area (NTM) target), according to the reporter's records, many traffic routes have been completed, clean and beautiful. The remaining sections are being urgently implemented by the construction unit.

a
Spacious roads in Kim Boi district. Photo: Dang Tinh

At Dong Bac Kindergarten - a project put into use in the 2024 - 2025 school year, Ms. Bui Thi Hong - Principal of the school said: "From an old, degraded school, students now study in a new, spacious school. We don't know what to say other than thank the Party and the State."

According to Ms. Hong, the school and parents are all very excited to receive such investment, helping students and teachers feel secure in studying and teaching.

Mr. Bach Cong Du - Director of the Kim Boi District Construction Project Management Board said that in order to support the commune in achieving its goals, the unit is making efforts to implement solutions and urge contractors to focus on speeding up the construction progress of works serving the NTM criteria such as: traffic roads in Boi Ca, Nam Thuong, Binh Tan, Nam Bai hamlets; traffic roads in Boi Ca, Nam Thuong, Binh Tan, Nuoc Ruong hamlets; repairing and upgrading roads in Boi Ca, Nam Thuong, Nam Ba hamlets.

In addition, Kim Boi district focuses resources so that Xuan Thuy and Kim Lap communes have enough conditions to meet the NTM criteria.

Huyen Kim Boi dang tap trung cho nhieu xa co du cac tieu chu NMT. Anh: Dang Tinh
Kim Boi district focuses on accelerating disbursement of public investment capital. Photo: Dang Tinh

According to Mr. Du, the unit regularly inspects, urges, and removes difficulties and obstacles for construction units. The entire political system is actively involved in propagating and mobilizing households whose land is affected to promptly hand over the site to the construction unit.

Up to this point, many projects have completed their documents and are awaiting final settlement. The remaining projects currently under construction are ensuring progress and quality compared to the requirements set by the district.

Đặng Tình
RELATED NEWS

Live football U23 Vietnam vs U23 UAE in the U23 Asian Cup quarter-finals

|

Live broadcast of the match between U23 Vietnam and U23 UAE in the quarter-finals of the 2026 AFC U23 Championship, taking place at 10:30 PM today (January 16).

Prosecuting the accident on the highway that killed 4 people in Thanh Hoa

|

Thanh Hoa - The Police Agency has initiated a criminal case related to a particularly serious traffic accident on the highway that killed 4 people.

Live football U23 Japan vs U23 Jordan in the quarter-finals of the 2026 AFC U23 Championship

|

Live football match between U23 Japan vs U23 Jordan in the quarter-finals of the 2026 AFC U23 Championship at 6:30 PM tonight (January 16).

Ms. Lam Thi Phuong Thanh is introduced to run for National Assembly Deputy of the 16th term

|

Voters at the Ministry of Culture, Sports and Tourism voted to agree to introduce Ms. Lam Thi Phuong Thanh, Standing Deputy Minister, to run for National Assembly Deputy of the 16th term.

Thu Thiem - Long Thanh railway line 42km long connects Long Thanh airport

|

Dong Nai - The Thu Thiem - Long Thanh railway project has a total estimated investment of about 84,753 billion VND, completed in 2031.

More provinces and cities announce the 3rd exam subject for 10th grade in 2026

|

Up to now, many provinces and cities have announced the 3rd exam subject in the 10th grade entrance exam for the 2026 - 2027 school year.

After Metro Line 2, Ho Chi Minh City is about to start construction of 5 more metro lines in 2026

|

Ho Chi Minh City - After starting Metro Line 2 (Ben Thanh - Tham Luong), Ho Chi Minh City plans to start construction of 5 more metro lines in 2026, completed in 2030.

Can Tho will replace weak officials in public investment management

Phong Linh |

Can Tho - In the solution to promote disbursement of public investment capital in the last months of the year, Can Tho will strengthen discipline and replace officials with weak capacity.

Ho Chi Minh City faces major challenges in public investment disbursement

MINH QUÂN |

In the last months of the year, Ho Chi Minh City faced a major challenge in disbursing public investment when many key projects were behind schedule, causing the disbursement rate to only reach 20%.

Phân bổ, sử dụng vốn đầu tư công hiệu quả, đúng mục tiêu

Trí Minh |

Xây dựng nguyên tắc, tiêu chí và định mức phân bổ vốn đầu tư công nguồn ngân sách nhà nước giai đoạn 2026 - 2030 là cần thiết.