The secret for mountainous districts to disburse nearly 80% of public investment capital

Đặng Tình |

Hoa Binh - Construction projects in Kim Boi district are being accelerated to ensure the disbursement plan for public investment capital.

On October 10, the Kim Boi District Construction Project Management Board announced that the unit was assigned to manage and implement 100 projects with a total investment of VND 1,187 billion (including projects in previous years). The capital allocated in 2024 is more than VND 203 billion, of which VND 157 billion has been disbursed, reaching over 77% of the plan.

Accordingly, there are 13 new projects starting construction in 2024 using district budget capital, with a total investment of 101 billion VND. The projects have signed contracts and handed over the site for construction contractors.

Transitional projects, including 75 projects with district budget capital, with a total investment of 763 billion VND, the total capital granted in 2024 is 131 billion VND, disbursed 119.5 billion VND, reaching 90.7%; 11 projects with additional targeted provincial budget capital and 1 project with central budget capital, with a total investment of 322 billion VND, the total capital granted in 2024 is 31 billion VND, disbursed 17 billion VND, reaching 53.7%.

In October, in Nam Thuong commune (striving to reach the advanced new rural area (NTM) target), according to the reporter's records, many traffic routes have been completed, clean and beautiful. The remaining sections are being urgently implemented by the construction unit.

a
Spacious roads in Kim Boi district. Photo: Dang Tinh

At Dong Bac Kindergarten - a project put into use in the 2024 - 2025 school year, Ms. Bui Thi Hong - Principal of the school said: "From an old, degraded school, students now study in a new, spacious school. We don't know what to say other than thank the Party and the State."

According to Ms. Hong, the school and parents are all very excited to receive such investment, helping students and teachers feel secure in studying and teaching.

Mr. Bach Cong Du - Director of the Kim Boi District Construction Project Management Board said that in order to support the commune in achieving its goals, the unit is making efforts to implement solutions and urge contractors to focus on speeding up the construction progress of works serving the NTM criteria such as: traffic roads in Boi Ca, Nam Thuong, Binh Tan, Nam Bai hamlets; traffic roads in Boi Ca, Nam Thuong, Binh Tan, Nuoc Ruong hamlets; repairing and upgrading roads in Boi Ca, Nam Thuong, Nam Ba hamlets.

In addition, Kim Boi district focuses resources so that Xuan Thuy and Kim Lap communes have enough conditions to meet the NTM criteria.

Huyen Kim Boi dang tap trung cho nhieu xa co du cac tieu chu NMT. Anh: Dang Tinh
Kim Boi district focuses on accelerating disbursement of public investment capital. Photo: Dang Tinh

According to Mr. Du, the unit regularly inspects, urges, and removes difficulties and obstacles for construction units. The entire political system is actively involved in propagating and mobilizing households whose land is affected to promptly hand over the site to the construction unit.

Up to this point, many projects have completed their documents and are awaiting final settlement. The remaining projects currently under construction are ensuring progress and quality compared to the requirements set by the district.

Đặng Tình
RELATED NEWS

Hanoi continues to sink into pollution, many points are at very unhealthy levels

|

Hanoi - Despite improvements due to wind, Hanoi still has many air pollution points at the danger level.

Phu Tho requires officials not to wear cow's pants, short dresses, or unneck shirts when going to work

|

Phu Tho - Cadres, civil servants, public employees and workers must dress neatly and politely when performing their duties, not wear short dresses, not wear cow's pants...

After the flood, many cracked houses are waiting to collapse on the banks of the Da Nhim river in Lam Dong

|

Lam Dong - The historic flood has passed, but people in D'ran commune are still panicking about the situation of many cracked houses at risk of collapsing into the river.

Suspending a "blood transplant" tubal treatment facility after a report from Lao Dong Newspaper

|

Hue - The interdisciplinary inspection team has temporarily suspended the operation of the Mb Center sewer treatment facility on To Huu Street after discovering many serious violations.

Thailand - Cambodia border tensions escalate every hour

|

Thailand - Cambodia tensions have continuously escalated since the clash broke out at the border between the two countries on December 7, forcing many households to evacuate.

Inside the project worth over VND7,200 billion being implemented in Can Tho

|

Can Tho - At the project to Upgrade and Expand National Highway 91 (Km0 - Km7), construction teams along the route are operating urgently, with machinery and equipment operating continuously.

Can Tho will replace weak officials in public investment management

Phong Linh |

Can Tho - In the solution to promote disbursement of public investment capital in the last months of the year, Can Tho will strengthen discipline and replace officials with weak capacity.

Ho Chi Minh City faces major challenges in public investment disbursement

MINH QUÂN |

In the last months of the year, Ho Chi Minh City faced a major challenge in disbursing public investment when many key projects were behind schedule, causing the disbursement rate to only reach 20%.

Phân bổ, sử dụng vốn đầu tư công hiệu quả, đúng mục tiêu

Trí Minh |

Xây dựng nguyên tắc, tiêu chí và định mức phân bổ vốn đầu tư công nguồn ngân sách nhà nước giai đoạn 2026 - 2030 là cần thiết.