Binh Dinh urges the progress of a series of key transport projects

Hoài Luân |

Along with ensuring progress, the leaders of Binh Dinh province requested the Provincial Traffic Project Management Board to immediately rectify shortcomings in project management and construction quality.

In 2024, the Binh Dinh Provincial Traffic Project Management Board (PMB) implemented many important transport projects, basically ensuring good management of progress and quality of the project.

The Provincial Traffic Project Management Board has coordinated with departments, branches and localities to promptly resolve problems, especially compensation and site clearance (GPMB).

Resolutely cut the construction volume of contractors behind schedule, to transfer to capable contractors to ensure project progress.

However, the Provincial Traffic Project Management Board is slow to propose a handling plan for IDV Investment and Trading Services Joint Stock Company due to the slow construction progress, affecting the overall progress of the project.

With the achieved results, Vice Chairman of Binh Dinh Provincial People's Committee Nguyen Tu Cong Hoang praised the working spirit of the Provincial Traffic Project Management Board. At the same time, he requested this unit to review and overcome limitations, and direct the drastic management of construction quality management in 2025.

Lanh dao tinh Binh Dinh kiem tra hien truong du an Nang cap, mo rong Cang hang khong Phu Cat. Anh: Thanh Thanh
Binh Dinh Provincial leaders inspect the site of the Phu Cat Airport Upgrade and Expansion Project. Photo: Thanh Thanh

"Seriously learn from experience, immediately correct shortcomings in project management and construction quality, absolutely do not let the project damage after being put into use. The Director of the Provincial Traffic Project Management Board must be responsible to the Provincial Chairman for the quality and progress of the project, Mr. Hoang emphasized.

Regarding the progress of the Binh Dinh Province Coastal Road project, Cat Tien - Diem Van section, Vice Chairman of the Binh Dinh Provincial People's Committee assigned the Provincial Traffic Project Management Board to preside over and coordinate with Tuy Phuoc district and related units to urgently relocate households affected by the project, focusing on construction to open the entire route before September 2025.

Coordinate with relevant parties to urgently complete documents and procedures for implementing the construction of the adjusted and supplemented volume and construction of level crossings for the An Nhon Town Center-Center Road project to the coastal road west of Thi Nai lagoon.

"By March 20 at the latest, the project to build a southern bypass of Phu Phong town and build a road connecting National Highway 19 to Becamex Binh Dinh Industrial Park and Urban Area connecting to Quy Nhon Port must be completed.

Develop a detailed schedule for compensation and site clearance for the Phu Cat Airport Expansion Project, including investment in the construction of resettlement areas and burial areas to serve the project. Coordinate with the agencies of the Ministry and the Central branches, promptly report and propose to the Provincial People's Committee to implement the Quy Nhon - Pleiku Expressway project," Mr. Hoang requested.

The Vice Chairman of Binh Dinh People's Committee directed the Provincial Traffic Project Management Board to speed up site clearance and construction of the Dien Bien Phu Road project extended to Diem Van Urban Area; Coastal Road (DT639), section from National Highway 1D to the new National Highway 19; N5 and D5 routes connecting to the boundary of the land of the Trade Union Institution Construction Project; Ring Road of the Software Center and Science Park of Quy Hoa Science and Education Urban Area.

Hoài Luân
RELATED NEWS

District is stuck in recovering more than 5 billion VND for incorrect spending

|

Binh Dinh - 7 years have passed, Phu My district has not been able to recover more than 5.3 billion VND that was spent incorrectly when compensating for the National Highway 1 expansion project, because the people have spent all their money.

Chairman of Binh Dinh requests to work on weekends to speed up the project

|

On February 15, Chairman of Binh Dinh Province Pham Anh Tuan inspected the site and worked with Phu Cat District People's Committee on the progress of implementing a number of key projects.

City Chairman, Department Director in Binh Dinh asks to leave the chair

|

To reorganize the apparatus, Director of the Department of Tourism of Binh Dinh province, Tran Van Thanh, voluntarily applied for early retirement, giving young people the opportunity to contribute.

Warning of heavy rain in 4 provinces, dangerous weather risk in the next 6 hours

|

The meteorological agency warns that Lao Cai, Tuyen Quang, Quang Ninh and Nghe An have experienced heavy rain, with very heavy rain in some places; there is a risk of flash floods and landslides in some communes and wards.

PNJ lost more than VND 2,260 billion in capitalization, what is noteworthy about the financial picture?

|

PNJ shares fell to the floor, causing the enterprise's capitalization to lose more than 2,260 billion VND. Regarding the business situation, PNJ recorded a picture with many bright spots.

Bad news

|

Mr. Nguyen Dinh Hoe, born in 1935 (father of comrade Nguyen Dinh Chuc - Former Deputy Editor-in-Chief of Lao Dong Newspaper) passed away at 22:52 on July 3, 2026 (ie May 19, Binh Ngo year), at the age of 92.

District is stuck in recovering more than 5 billion VND for incorrect spending

Hoài Phương |

Binh Dinh - 7 years have passed, Phu My district has not been able to recover more than 5.3 billion VND that was spent incorrectly when compensating for the National Highway 1 expansion project, because the people have spent all their money.

Chairman of Binh Dinh requests to work on weekends to speed up the project

Thảo Phương |

On February 15, Chairman of Binh Dinh Province Pham Anh Tuan inspected the site and worked with Phu Cat District People's Committee on the progress of implementing a number of key projects.

City Chairman, Department Director in Binh Dinh asks to leave the chair

Hoài Luân |

To reorganize the apparatus, Director of the Department of Tourism of Binh Dinh province, Tran Van Thanh, voluntarily applied for early retirement, giving young people the opportunity to contribute.