Binh Dinh speeds up trillion-dollar project to welcome the big day

Hoài Luân |

The project of the road connecting National Highway 19 - Becamex Vsip Industrial Park - Quy Nhon Port is accelerating, expected to be completed before March 31, to celebrate the 50th anniversary of Binh Dinh's liberation.

On February 4, Secretary of Binh Dinh Provincial Party Committee Ho Quoc Dung inspected the progress of the project to build a road connecting National Highway 19 to Becamex Vsip Binh Dinh Industrial Park connecting to Quy Nhon port.

The project has a total investment of more than 1,160 billion VND, with a route length of more than 19km, a roadbed width of 12m, and construction of 7 bridges on the route. The project passes through Van Canh, Tay Son districts and An Nhon town. The project implementation period is from 2022 to 2025.

May moc, nhan luc hoi ha thi cong de som dua du an ve dich. Anh: Thanh Thanh
Machines and human resources are working hard to bring the project to the finish line soon. Photo: Thanh Thanh

On the main route (from Km0 - Km12+945), the contractor has completed the roadbed, completed 5/5 bridges, 27/27 large box culverts and 43/43 circular culverts. Currently, the contractor is constructing the crushed stone layer and continuing to pour crushed stone and complete the remaining stages of the project.

Mr. Luu Nhat Phong - Director of Binh Dinh Province Traffic Project Management Board said that the project is being constructed on schedule. In order to bring the project to the finish line soon, in the coming time, the investor and contractor will increase machinery and equipment to speed up the construction progress.

Ong Ho Quoc Dung tang qua, li xi dau nam moi cho cong nhan. Anh: Thanh Thanh
Mr. Ho Quoc Dung gives gifts and lucky money to workers at the beginning of the new year. Photo: Thanh Thanh

In the immediate future, the investor and contractor will focus on completing the project of building a road connecting National Highway 19 to Becamex Vsip Binh Dinh Industrial Park connecting to Quy Nhon Port before March 31 to celebrate the 50th anniversary of Binh Dinh Province Liberation Day (March 31, 1975 - March 31, 2025).

At the inspection, Mr. Ho Quoc Dung - Secretary of Binh Dinh Provincial Party Committee highly appreciated the coordination and handling of difficulties during the project implementation process between the investor, contractor and local authorities, contributing to speeding up the project progress.

"The project to build a road connecting National Highway 19 to Becamex Vsip Binh Dinh Industrial Park connecting to Quy Nhon Port is now no longer a problem. By the 50th anniversary of the liberation of Binh Dinh province, the project must be completed and inaugurated before March 31 to celebrate the liberation of Binh Dinh homeland. The contractor must speed up, work even when it is sunny," Mr. Ho Quoc Dung suggested.

Hoài Luân
RELATED NEWS

Binh Dinh proposes to hand over 109 hectares of national defense land to build an airport

|

Binh Dinh province has proposed the Ministry of National Defense hand over 109 hectares of defense land to build runway No. 2 at Phu Cat Airport.

Two young men in Binh Dinh drowned while swimming in the sea on Tet holiday

|

Binh Dinh - While going swimming together on Tet holiday, 2 out of 11 young people were unfortunately swept away by the waves, leading to drowning and death.

Binh Dinh invests nearly 230 billion VND in two infrastructure projects

|

According to the plan, by 2027, Binh Dinh will complete the Vinh Loi resettlement project and the An Lao bridge project, with a total investment of nearly 230 billion VND.

Workshop on unblocking green credit capital flows for businesses

|

Green credit is considered an important capital channel, supporting businesses to transition to green, access capital and promote more sustainable green growth.

To manage and develop education, it is necessary to give substantive power to principals

|

According to Dr. Hoang Ngoc Vinh, to switch to education development management, principals need to be given more power and be responsible for real results.

Lao Dong Newspaper wins 2 awards at the 2026 National Press Festival

|

Hai Phong - Closing after 3 days of operation, the 2026 National Press Festival left many imprints on creativity, digital transformation and social responsibility of the press.

Workers enthusiastically participate in the Health Exchange - Legal Consulting program

|

Ho Chi Minh City - Thousands of workers excitedly participate in "Giving health - Legal advice - For a healthy Vietnam", with many meaningful and practical activities.

Binh Dinh proposes to hand over 109 hectares of national defense land to build an airport

Hoài Phương |

Binh Dinh province has proposed the Ministry of National Defense hand over 109 hectares of defense land to build runway No. 2 at Phu Cat Airport.

Two young men in Binh Dinh drowned while swimming in the sea on Tet holiday

Hoài Phương |

Binh Dinh - While going swimming together on Tet holiday, 2 out of 11 young people were unfortunately swept away by the waves, leading to drowning and death.

Binh Dinh invests nearly 230 billion VND in two infrastructure projects

Hoài Phương |

According to the plan, by 2027, Binh Dinh will complete the Vinh Loi resettlement project and the An Lao bridge project, with a total investment of nearly 230 billion VND.