The Ministry of Construction responds to the Hanoi People's Committee on the content related to the Ring Road 4 project

Xuyên Đông |

The Ministry of Construction has just issued an official dispatch responding to Hanoi on the content related to the Ring Road 4 project in the Hanoi Capital Region.

The Ministry of Construction has just issued Official Letter No. 12611/BXD-CDBVN to the Hanoi People's Committee regarding the settlement of recommendations related to the investment project to build Ring Road 4 in the Hanoi Capital Region.

Accordingly, the Ministry of Construction received a petition from the Hanoi People's Committee with the following content:

"Regarding the source of materials for the construction of Component Project 3 of the Ring Road 4 - Hanoi Capital Region Project: Propose to the National Assembly Standing Committee to allow the contractor to construct Component Project 3 to continue not to have to carry out procedures for granting a Mineral Exploitation License for common construction materials in the Construction Materials Survey Document for the Project as prescribed in Resolution No. 56/2022/QH15 dated June 16, 2022 of the National Assembly, the time allowed to apply is until the completion of the project's construction".

Regarding this issue, the Ministry of Construction responded as follows:

The investment project to build Ring Road 4 - Hanoi Capital Region (abbreviated as the Project) was approved by the 15th National Assembly in Resolution No. 56/2022/QH15 dated June 16, 2022 on investment policy; The Government issued Resolution No. 106/NQ-CP dated August 18, 2022 to implement Resolution No. 56/2022/QH15 dated June 16, 2022 on investment policy (Hanoi People's Committee and People's Committees of Hung Yen and Bac Ninh provinces are the investment managers).

Accordingly, the project is organized and implemented according to 07 component projects, including: 03 compensation, support and resettlement projects; 03 investment projects to build parallel roads (urban roads) under the form of public investment and 01 project to invest in the construction of highways under the public-private partnership method (this is Component Project 3 mentioned above by the Hanoi People's Committee).

Regarding the content of materials for construction for Component Project 3 as proposed by the Hanoi People's Committee, the Government has promptly handled and resolved it when issuing Resolution 66.4/NQ-CP dated September 21, 2025 on specific policies and mechanisms to remove difficulties in implementing the 2024 Law on Geology and Minerals. Up to now, the Investors, Project Enterprises and contractors currently implementing there are no more problems.

Xuyên Đông
RELATED NEWS

Ho Chi Minh City Ring Road 4 project affects 49 cases of using agricultural and forestry land in the battlefield area D

|

HCMC - Localities are urgently clearing land to implement the previous HCMC Ring Road 4 project through Binh Duong area.

Hanoi's Ring Road 4 parallel road lacks completion plan in 2025

|

The slow handover of the site makes it impossible for the Ring Road 4 parallel road project to be completed in 2025 as targeted by Hanoi.

New direction of the Chairman of Hanoi on the Ring Road 4 project

|

The Chairman of Hanoi directed departments, branches and localities to focus on removing obstacles to site clearance and speeding up the construction progress of the Ring Road 4 project.

91-year-old woman in Hanoi receives support after Lao Dong Newspaper article

|

After the article by Lao Dong Newspaper, a 91-year-old woman in Hanoi has received a new allowance for January, February and March, with a level of 650,000 VND per month.

AI cameras support Hanoi traffic police to maintain traffic flow on the days leading up to Tet

|

Hanoi - AI camera data in real time helps traffic police forces flexibly operate traffic lights, remote traffic diversion...

Opposition party raises doubts in Thai election

|

Leaders of the Thai People's Party admitted defeat according to preliminary results, but called for an investigation into unusual signs to ensure the transparency of the election.

Truck bursts into flames on Vinh Hao - Phan Thiet expressway

|

Lam Dong - A truck traveling on the Vinh Hao - Phan Thiet expressway suddenly caught fire fiercely.

Large fire at a charity house in Bac Ninh

|

Bac Ninh - On the morning of February 10, a fire broke out at the Huong La charity house (Luong Tai commune), burning down about 80m2.

Ho Chi Minh City Ring Road 4 project affects 49 cases of using agricultural and forestry land in the battlefield area D

ĐÌNH TRỌNG |

HCMC - Localities are urgently clearing land to implement the previous HCMC Ring Road 4 project through Binh Duong area.

Hanoi's Ring Road 4 parallel road lacks completion plan in 2025

SÓNG HỮU |

The slow handover of the site makes it impossible for the Ring Road 4 parallel road project to be completed in 2025 as targeted by Hanoi.

New direction of the Chairman of Hanoi on the Ring Road 4 project

SÓNG HỮU |

The Chairman of Hanoi directed departments, branches and localities to focus on removing obstacles to site clearance and speeding up the construction progress of the Ring Road 4 project.