Close-up of the construction of the second runway at the Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai - Vietnam Airports Corporation (ACV) has started construction of the second runway of the Long Thanh airport project and is implementing construction items.

On July 20, according to information from Vietnam Airports Corporation (ACV), to meet the progress requirements of the Prime Minister, ACV has urgently deployed and completed the selection of contractors in special cases for packages during the construction phase to deploy the second runway and held a groundbreaking ceremony on May 30, 2025.

Up to now, the contractor consortium has mobilized machinery, equipment, personnel, gathered materials, and laboratories to serve the construction and deploy items such as runway foundation, taxiways and drainage systems.

It is expected that this package will be completed synchronously with the passenger terminal project and put into operation in June 2026 according to the required schedule.

Previously, package 4.6, construction of the first runway, taxiway, and aircraft parking lot (constructed by the ACC - Truong Son - Vinaconex - Vinadic - Cienco4 - ACJC647 consortium), was completed and technically exploited the runway before April 30, 2025 (3 months ahead of the contract).

Some images recorded by Lao Dong Newspaper reporters at the construction site of the second runway at Long Thanh airport:

h1
The second runway is parallel to the first runway.
h2
Currently, the service road has been constructed to serve the implementation of the second runway items.
h3
The contractor has mobilized many machines, equipment and human resources for construction.
h4
Workers at the construction site.
h5
Contractors constructing items of runway foundation, taxiway, and drainage system
h6
It is expected that this package will be completed in sync with the passenger terminal project and put into operation in June 2026.
h7
Panorama of Long Thanh airport and 2 runways.

At the entire Long Thanh airport project site, units are still maintaining the construction progress with hundreds of deployment teams, mobilizing nearly 13,000 experts, engineers, workers, laborers and nearly 3,000 construction equipment to speed up the progress of the packages with the goal of basically completing the project by the end of 2025, putting it into operation and commercial exploitation in the first half of 2026 in accordance with the Prime Minister's request.

HÀ ANH CHIẾN
TIN LIÊN QUAN

Many new adjustments on routes to Tan Son Nhat airport's T3 terminal

|

HCMC - The route to Tan Son Nhat airport's T3 terminal has just been adjusted, the traffic situation in the area in front of terminal T3 has changed more positively.

Overview of more than 5,000 personnel and machinery for the heart-shaped construction of the Long Thanh airport project

|

Dong Nai - The Long Thanh airport component project 3 has 14 packages, of which package 5.10 for the construction of the passenger terminal is considered the heart of the project.

Mobilizing nearly 13,000 personnel to urgently construct Long Thanh airport

|

Despite unfavorable weather and a shortage of human resources, nearly 13,000 experts, engineers and workers are being urgently mobilized to complete the Long Thanh airport project on schedule by the end of 2025.

The ship capsize in Ha Long Bay cannot leave the responsibility of related units unanswered

|

The ship capsize in Ha Long Bay caused dozens of casualties, shocked public opinion, and raised many questions about the responsibility of the parties involved.

The kiss of Phuong My Chi and the hundred-billion-dong beauty caused a stir

|

Phuong My Chi participated in the competition for the competition in Em xinh say hi. She had a surprising kiss with her co-star.

Ninh Binh Department of Tourism leaders talk about the ferry problem in Tam Coc

|

Ninh Binh - The leader of the provincial Department of Tourism informed about the boat problem in Tam Coc Tourist Area on the afternoon of July 19.

Strongly spreading the patriotic emulation movement of the working class

|

During the resistance war against the US (1954 - 1975), the Vietnam General Confederation of Labor gathered, united, and promoted the pioneering role of the working class in overcoming countless difficulties, hardships, and sacrifices, contributing to the army and people of the whole country in the victory on April 30, 1975 .

HCMC reclaims 110 hectares of land, clears 61 households to build the North-South high-speed railway

|

Ho Chi Minh City will reclaim more than 110 hectares of land, clear 61 households with compensation and site clearance costs of more than VND 2,100 billion to build the North-South high-speed railway section.

Many new adjustments on routes to Tan Son Nhat airport's T3 terminal

NHƯ QUỲNH - NGỌC ÁNH |

HCMC - The route to Tan Son Nhat airport's T3 terminal has just been adjusted, the traffic situation in the area in front of terminal T3 has changed more positively.

Overview of more than 5,000 personnel and machinery for the heart-shaped construction of the Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai - The Long Thanh airport component project 3 has 14 packages, of which package 5.10 for the construction of the passenger terminal is considered the heart of the project.

Mobilizing nearly 13,000 personnel to urgently construct Long Thanh airport

HÀ ANH CHIẾN |

Despite unfavorable weather and a shortage of human resources, nearly 13,000 experts, engineers and workers are being urgently mobilized to complete the Long Thanh airport project on schedule by the end of 2025.