Bridge worth over 100 billion VND accelerates amidst hot weather in Lao Cai border region

Đinh Đại |

Lao Cai - Workers and machinery are still busy at the Ngoi Phat bridge construction site to speed up the progress of the project worth more than 100 billion VND before the rainy and flood season.

In the last days of May, the construction atmosphere at the Ngoi Phat bridge construction site became more urgent than ever.

In the hot summer sun in the Lao Cai border area, groups of workers are still diligently working, taking advantage of each favorable hour to complete important items of the project.

Ngoi Phat bridge belongs to the project to build a road running along the Red River connecting Ban Vuoc border gate to Y Ty, the section from Km4+300 to Km7+500, the connecting branch line and the bridge across the Ngoi Phat stream.

Cầu Ngòi Phát đã xong các trụ cầu. Ảnh: Đinh Đại
Ngoi Phat Bridge has completed the bridge piers. Photo: Dinh Dai

The project was approved by Lao Cai Provincial People's Committee according to Decision No. 2805 dated November 1, 2024, belonging to group B with a total investment of 380 billion VND. The investor is the Lao Cai Provincial Traffic Construction Investment Project Management Board.

In which, Package No. 14 of Ngoi Phat bridge construction is worth more than 114.6 billion VND, constructed by the Ngoi Phat Bridge Joint Venture including Lao Cai Bridge Construction Joint Stock Company and Lao Cai Construction and Inspection Joint Stock Company.

According to records at the scene, the underlying structure of the project, including the abutment and bridge piers on the basic bored pile foundation system, has been basically completed. This is considered the most difficult item because it is heavily affected by geology and construction conditions along the stream.

Các phiến dầm đã đúc xong, chờ thực hiện phần việc lao lắp. Ảnh: Đinh Đại
The components have been cast, waiting for the installation work to be carried out. Photo: Dinh Dai

Currently, units are focusing on installing girders, constructing bridge deck slabs and completing the approach road system at both ends of the bridge.

The Ngoi Phat bridge project is built with reinforced concrete and prestressed reinforced concrete at Km4+534.05. The bridge is 198.2m long, 22.5m wide; of which the vehicle part is 20m wide.

The upper part structure includes 5 spans of I-shaped cross-section beams made of prestressed reinforced concrete, each beam 33m long. The horizontal cross-section arranges 10 beam slabs, the distance between beams is 2.25m.

Công nhân cùng máy móc vận chuyển vận liệu phục vụ cho việc thi công. Ảnh: Đinh Đại
Workers and machinery transporting materials for construction. Photo: Dinh Dai

The approach roads at both ends of the bridge are designed according to grade III delta road standards with a design speed of 80km/h, a roadbed width of 22.5m and a road surface width of 20m.

The project started in August 2025, the construction time according to the contract is 540 days.

Talking to reporters, Mr. Hoang The Hoi - Project Director - said that construction in erratic mountain weather conditions, especially when the rainy season is approaching, makes the pressure of progress increasing.

According to Mr. Hoi, so far the contractor has completed the entire drilled pile item, completed the construction of 2 abutments and 4 bridge piers, and completed the casting of 50 girder slabs. The actual value of the package currently reaches over 75%.

The investor requests the supervision unit to regularly be present at the construction site to coordinate and organize construction in accordance with weather conditions, ensuring labor safety and project quality.

Up to now, the underlying structure is basically completed, the main remaining volume is for girder installation and bridge deck construction," Mr. Hoi said.

Công trình giúp kết nối giao thông, thúc đẩy giao thương khi hoàn thành. Ảnh: Đinh Đại
The project helps connect traffic and promote trade when completed. Photo: Dinh Dai

To ensure progress, the contractor has divided into many construction teams, increased manpower, machinery and closely followed the site. Items are implemented according to the design documents, strictly controlling techniques in each stage.

When completed, Ngoi Phat bridge and the road along the Red River are expected to contribute to strengthening traffic connections in the border area, creating favorable conditions for trade and promoting socio-economic development in the locality.

Đinh Đại
RELATED NEWS

Worry about pollution from the large-scale ash and slag storage yard on the Cau River

|

Thai Nguyen - Large-scale ash and slag storage yard lacks covering and shielding plans, causing people to constantly worry about environmental pollution.

Deadline for resolving benefits for thousands of non-specialized commune-level personnel

|

Localities will complete the settlement of regimes for non-specialized people at the commune level before the deadline, some localities have additional support policies.

Traffic lights at many Hanoi intersections will only flash yellow in the coming days

|

Hanoi - From the night of May 23, many streets were barricaded to serve the construction of flood prevention projects, traffic police adjusted traffic lights to flash yellow at some intersections.

Time when gunshots rang near the White House

|

2 people were injured after a shooting near the White House on the evening of May 23, local time.

Me So bridge accelerates construction, completing key items

|

Hanoi - The Me So bridge project is being accelerated by contractors to ensure the goal of completing the items before the 2026 rainy and storm season.

Announcing decisions on personnel work in Hanoi, Da Nang, and Khanh Hoa

|

Hanoi City, Da Nang City, Khanh Hoa province, Dong Thap, Lai Chau... have implemented and announced decisions on personnel work.

Worry about pollution from the large-scale ash and slag storage yard on the Cau River

Việt Bắc |

Thai Nguyen - Large-scale ash and slag storage yard lacks covering and shielding plans, causing people to constantly worry about environmental pollution.

Chủ tịch tỉnh yêu cầu dừng, nhà máy ở Phú Thọ vẫn xả khói nghi ngút

Tô Công |

Phú Thọ - Nhà máy viên nén gỗ tại xã Bình Phú xả khói nghi ngút dù Chủ tịch UBND tỉnh đã yêu cầu dừng hoạt động cho đến khi có giấy phép môi trường.

Cầu trăm tỉ giúp xóa cảnh chờ đò vượt sông Gâm tại Tuyên Quang

Lam Thanh |

Tuyên Quang - Cầu trăm tỉ vượt sông Gâm sau khi hoàn thành sẽ giúp người dân xóa cảnh chờ đò hàng chục năm nay, hiện các hạng mục cuối cùng đang gấp rút được hoàn thiện.