Directive of the Secretary of the Hanoi Party Committee on the Ring Road 2.5 project

SÓNG HỮU |

The Secretary of the Hanoi Party Committee requested the entire political system to participate in the propaganda and mobilization so that people can share, support, and bring the Ring Road 2.5 project to the finish line on schedule.

On December 9, Politburo member and Secretary of the Hanoi Party Committee Nguyen Duy Ngoc chaired a meeting with relevant agencies and units to remove difficulties and obstacles in implementing the Ring Road 2.5 project.

The Ring Road 2.5 route has a total length of 19.41km, a cross-section of 40-50m, the starting point intersects with the Thanh Tri bridge approach road, the end point ends in Phu Thuong ward. The project was started many years ago but has not been completed yet.

The entire Ring Road 2.5 in the city is divided into 13 sections. The project has been invested in 7.6km according to the plan, 9.36km is being invested, and 2.45km has not been studied for investment.

Currently, one of the biggest difficulties is site clearance related to 5 sections that are under implementation and 3 sections that have not been implemented.

The Ring Road 2.5 plays a vital role in the Hanoi capital's transportation system, contributing to connecting inner-city districts from Phu Thuong to Linh Nam, creating a closed circle to reduce traffic pressure on major roads such as Ring Road 2 and Ring Road 3.

In the context of Hanoi's rapid urbanization, Ring Road 2.5 is a key factor to achieve the goal of infrastructure breakthroughs and reducing traffic congestion - one of the 5 bottlenecks that the city focuses on directing to overcome.

At the conference, Secretary of the Hanoi Party Committee Nguyen Duy Ngoc chaired exchanges between relevant agencies, units and localities, clarifying each difficulty and problem that is affecting the situation and progress of project implementation, especially related to site clearance and investment preparation for new sections...

Speaking at the conclusion of the directive, Secretary of the City Party Committee Nguyen Duy Ngoc requested that agencies, units and localities must be very careful in each work, especially in site clearance; focus on basic investigation, grasp the situation, and mobilize people right now.

In addition, the city's agencies and units have made the most of mechanisms and policies to remove obstacles, ensure the legitimate rights of the people; determined to speed up the project's progress to achieve the set goals.

Secretary of the Hanoi Party Committee Nguyen Duy Ngoc emphasized that this is a key and key project of the city, which is significant not only for the development future of Hanoi, but also meets the requirements of the people's practical life.

He requested that the entire political system must be mobilized to participate, increase propaganda and mobilization so that people can share, support and accompany the city to bring the project to the finish line on schedule.

The Ring Road 2.5 project, Dam Hong - National Highway 1A section, is about to be completed

In the sections under implementation, the Dam Hong - National Highway 1A section is being accelerated.

The route is about 1.6km long, with a total investment of more than 1,300 billion VND. The project started in 2014, expected to be completed after 3 years but was delayed due to site clearance problems and waiting for the extension of the BT contract appendix.

By May 2025, the project will be restarted, expected to be completed in the first quarter of 2026, expected to open up new development space for the southern area of the capital.

SÓNG HỮU
RELATED NEWS

Power and water cuts to clear a series of works encroaching on the Ring Road 2.5 tunnel and road project

|

Hanoi - The authorities will cut off electricity and water, then clear the encroached works to construct the underpass and Ring Road 2.5 project.

Some households deliberately encroach, do not hand over land for the construction of the 2.5 belt road in Hanoi

|

Hanoi - Some households deliberately re-encroach on the site and refuse to hand over the site to the contractor for the Ring Road 2.5 project.

Hanoi Ring Road 2.5 enters the final stage, contractors mobilize maximum human resources for construction

|

Hanoi - The contractor has completed the C15 asphalt paving item at the beginning of the route of the Ring Road 2.5 project, Dam Hong - National Highway 1A section, with a total capital of more than 1,300 billion VND.

Directive of the Secretary of the Hanoi Party Committee on the Ring Road 2.5 project

|

The Secretary of the Hanoi Party Committee requested the entire political system to participate in the propaganda and mobilization so that people can share, support, and bring the Ring Road 2.5 project to the finish line on schedule.

High-rise house fire in Indonesia, at least 22 people killed

|

A major fire broke out at a 7-storey building in the capital Jakarta, Indonesia, causing heavy damage to both people and facilities.

Experts propose Hanoi opens more lanes dedicated to buses

|

Hanoi - Traffic expert Phan Le Binh proposed opening more lanes dedicated to buses in the context of the city implementing a low emission zone.

Russian military transport plane crashed, 7 people in the cabin's fate unknown

|

On December 9, Russian media reported that a Russian heavy military transport aircraft An-22 Antei crashed in furmanovsky district, Ivanovo province.

A series of unlicensed cosmetic facilities advertise stem cell services

|

Although not licensed by the Ministry of Health, many beauty establishments are still massively advertising stem cell services, exaggerating their uses and posing a potential health risk to customers.

Power and water cuts to clear a series of works encroaching on the Ring Road 2.5 tunnel and road project

SÓNG HỮU |

Hanoi - The authorities will cut off electricity and water, then clear the encroached works to construct the underpass and Ring Road 2.5 project.

Some households deliberately encroach, do not hand over land for the construction of the 2.5 belt road in Hanoi

HỮU CHÁNH |

Hanoi - Some households deliberately re-encroach on the site and refuse to hand over the site to the contractor for the Ring Road 2.5 project.

Hanoi Ring Road 2.5 enters the final stage, contractors mobilize maximum human resources for construction

SÓNG HỮU |

Hanoi - The contractor has completed the C15 asphalt paving item at the beginning of the route of the Ring Road 2.5 project, Dam Hong - National Highway 1A section, with a total capital of more than 1,300 billion VND.