President Bac Ninh urged the project progress of nearly VND 86,000 billion through the area

Vân Trường |

Bac Ninh - Chairman of the Provincial People's Committee checked the situation of site clearance of Belt 4 project - the capital area through the province.

On April 13, Mr. Vuong Quoc Tuan, Chairman of Bac Ninh People's Committee checked the situation of site clearance (land clearance) of residential land, dismantling houses, properties and works on land under the investment project on construction of Ring Road 4 - Hanoi Capital Region, section through Bac Ninh province.

According to the report of the Transport and Agricultural Project Management Board (investor), the Ring Road 4 Project, the section through the territory of the province has approved the compensation plan, land clearance reaches 98,945%; The remaining 3,945 hectares, accounting for 1.055% of the residential land and the improperly assigned authority has not been completed.

Electric, water and irrigation infrastructure items strive to relocate in September. The localities are urgently completing the resettlement areas to soon hand over land to people with land with land withdrawn and stabilize their lives.

Up to now, the total construction value of the whole project has reached 31% of the volume value.

Directly check the site clearance of the area of ​​residential land and land allocated in the jurisdiction in Khac Niem ward, Hap Linh (Bac Ninh city), Chi Lang commune (Que Vo town), Mao Dien commune (Thuan Thanh town), Chairman of Bac Ninh People's Committee, Tuan Vuong, Tuan, highly appreciated the spirit of urgency, drastic and liability in the advocacy and dialogue of the Party Committee, the local authorities have the high -level project, the local authorities have the project of the local authorities people class.

Chairman of the Provincial People's Committee requested Bac Ninh City, Que Vo Town, Thuan Thanh Town to hand over seamless ground to the investor before April 22.

At the same time, asking Que Vo town to be more determined; Develop detailed plans, clear completion progress, frank dialogue with the people in compensation and support of the recovered land; Develop construction protection plans and accelerate the construction of resettlement areas, ensuring people's security.

Chairman of Bac Ninh People's Committee also requested the Management Board of Transport and Agricultural Project immediately after receiving the ground, determined to go to the destination of the Ring Road 4 project as planned, ensuring technical and fine arts.

The Prime Minister requested to complete the project in 2025

The project of building Ring Road 4 - Hanoi Capital region belongs to an important national project group, with a total length of 112.8 km (including 58.2km through Hanoi territory, the rest is 9.7km of route connecting Hanoi - Ha Long and the part to go through Hung Yen and Bac Ninh provinces).

Preliminary total project investment is 85,813 billion dong.

The 4rd Capital Ring Project has 35.3km passing through Bac Ninh, including 4 districts and towns: Bac Ninh City, Thuan Thanh and Que Vo town, Gia Binh district.

Earlier, on September 22, in the working program in Bac Ninh, Prime Minister Pham Minh Chinh checked the progress of the implementation of the investment project to build Ring Road 4 - Hanoi Capital region through Bac Ninh.

Vân Trường
TIN LIÊN QUAN

Bac Ninh and Bac Giang economies before the merger

|

Bac Ninh and Bac Giang are the provinces of industrial parks and production points of many large corporations in the world.

Natural conditions, population of Bac Ninh, Bac Giang before merger

|

After nearly 30 years of re-establishment, Bac Ninh and Bac Giang are taking steps to merge the two provinces.

The 358 billion VND bridge connecting Bac Ninh - Bac Giang is about to open to traffic

|

Bac Ninh - The People's Committee of Bac Ninh province has just issued an official dispatch on coordinating the organization of the opening ceremony of Ha Bac 2 bridge and access road.

Starting construction of a bridge worth nearly 500 billion VND to solve traffic congestion in the South of Ho Chi Minh City

|

HCMC - This morning (September 10), the new Rach Tom bridge with an investment capital of nearly 500 billion VND has officially started construction, hoping to solve traffic congestion in the South of HCMC.

The crisis of Lang Ha Thuc summer camp from the way MC Minh Trang apologizes

|

In recent days, Hanh Hung Village, a famous summer camp model, has faced an unprecedented media crisis after negative feedback from parents.

Mr. Trump sends more letters to many countries, promotes tariff agreements

|

President Trump continues to put trade pressure on many countries with letters announcing new tax rates expected to be applied.

Metro No. 2 construction site is bustling after 100% of the site is clean

|

HCMC - Metro Line 2 project has completed site clearance and is urgently constructing the relocation of technical infrastructure, aiming to start construction in December 2025.

Difficulty in clearing the channel to 2 fishing ports that are silted up, boats stranded

|

Ha Tinh - The channel to Thach Kim Fishing Port and Cua Nhuong Fishing Port is silted up, causing ships and boats to strand when the tide goes down.

Bac Ninh and Bac Giang economies before the merger

Trần Tuấn |

Bac Ninh and Bac Giang are the provinces of industrial parks and production points of many large corporations in the world.

Natural conditions, population of Bac Ninh, Bac Giang before merger

Trần Tuấn |

After nearly 30 years of re-establishment, Bac Ninh and Bac Giang are taking steps to merge the two provinces.

The 358 billion VND bridge connecting Bac Ninh - Bac Giang is about to open to traffic

Vân Trường |

Bac Ninh - The People's Committee of Bac Ninh province has just issued an official dispatch on coordinating the organization of the opening ceremony of Ha Bac 2 bridge and access road.