With 30m of site yet to be handed over, the drainage project worth over VND56 billion is slow to complete

HƯNG THƠ |

Quang Tri - The drainage project for residential areas that are often flooded has not yet been able to function due to the site clearance of a household.

In a high place, for many years now, people in lot 113 Le Loi street (Nam Dong Ha ward, Quang Tri province) have lived in a state of flooding every time there is heavy rain.

Ms. Le Thi Tu (81 years old) said she is used to the scene of water flooding into her house, causing damage. Every time it rains heavily, the couple has to climb up the floating hall to avoid the water, and the furniture in the house has been damaged many times. Not only Ms. Tu, households in the 131 block and near the drainage area of Phan Dinh Phung Secondary School also often suffer from flooding.

To handle this situation, in June 2022, the People's Committee of Dong Ha city (old) approved the drainage system project in Phan Dinh Phung Secondary School and Quarter 2, with a total investment of 56.2 billion VND. The project includes a sewer line about 1 km long, with an implementation period of 2022-2024, then the progress was adjusted to the end of 2025.

Mr. Thai Vinh Hai - Director of the Dong Ha Ward Investment and Construction Project Management Board said that the Le Loi Bridge construction package has been completed and put into use since August 1, 2025. For the drainage package, the contractor has constructed 902 m, 21 intake holes and 7 entrance gates, reaching 93% of the contract value. However, the project is "stuck" because the last section of the 30-meter long route from Le Loi Bridge to the railway bridge has not been cleared.

Doan cong thoat nuoc thi cong dang do vi chua hoan thanh giai phong mat bang. Anh: Hung Tho
The drainage section is under construction because the project site clearance has not been completed. Photo: Hung Tho

According to the Land Fund Development Center of Dong Ha Ward, the project affected 41 cases, only one household had not agreed to the compensation plan, Mr. L.D.M, residing in Nam Dong Ha Ward. Mr. M said that the area of 123 m2 is located in 144 m2 of residential land that has been granted a land use right certificate, so when it is recovered, compensation must be paid.

However, the Center affirmed that this area is river and stream land managed by the ward. The overlap occurred from the process of transferring land for many generations, causing Mr. M to incorrectly determine the location of the land plot. According to regulations, Mr. M is only supported with assets on the land, without compensation for land.

Mr. Pham Van An - Deputy Director of the Dong Ha Ward Land Fund Development Center, said that the compensation plan has been made public. Mr. An emphasized that the project is of special importance in collecting, regulating the flow, and reducing flooding for hundreds of households. If this household continues to disagree, the unit will implement the steps according to regulations.

HƯNG THƠ
RELATED NEWS

Plugged with prolonged site clearance, coastal road project in Quang Tri is under construction

|

Quang Tri - The coastal road project is facing difficulties due to many sections of land clearance problems, interrupted construction, which may affect progress.

The Ministry of Construction responds to regulations on building resettlement projects

|

The Ministry of Construction has just responded to the Quang Tri Department of Justice on the proposal to regulate the construction of a resettlement project.

Revealing the trick of "securing a goodwill space" for social housing projects in Quang Tri

|

Many people in Quang Tri have paid 10 million VND to "reserve a charity spot" in a social housing project that has not yet started construction. After the reflection of Lao Dong Newspaper, the investor began to refund the money and the authorities began to check.

Hon Vong Phu faces debate, functional sectors get involved

|

Thanh Hoa - After public opinion paid attention to reinforcing the Hon Vong Phu relic, functional agencies intervened to inspect and clarify information.

Failing in the semi-finals, the father of the U23 Vietnam captain sends his belief in the journey ahead

|

After the defeat in the semi-finals, people in the hometown of the U23 Vietnam captain have faith in the future journey of the team.

Trung Kien admits U23 China played differently in the semi-final

|

Goalkeeper Trung Kien admitted that U23 China played tightly and sharply and said that U23 Vietnam will make efforts to recover for the third-place match.

Old Tet atmosphere recreated in the Old Quarter of Hanoi

|

Hanoi - "Vietnamese Spring Tet Market - Tet Pho 2026" recreates the old Northern Tet space, attracting tourists and young people to find traditional Tet values.

Hieu Minh at risk of ligament injury

|

In the 2026 AFC U23 Championship semi-final match between U23 Vietnam and U23 China on the evening of January 20, central defender Hieu Minh suffered an injury and was forced to leave the field early.

Plugged with prolonged site clearance, coastal road project in Quang Tri is under construction

CÔNG SÁNG |

Quang Tri - The coastal road project is facing difficulties due to many sections of land clearance problems, interrupted construction, which may affect progress.

The Ministry of Construction responds to regulations on building resettlement projects

Xuyên Đông |

The Ministry of Construction has just responded to the Quang Tri Department of Justice on the proposal to regulate the construction of a resettlement project.

Revealing the trick of "securing a goodwill space" for social housing projects in Quang Tri

Công Sáng |

Many people in Quang Tri have paid 10 million VND to "reserve a charity spot" in a social housing project that has not yet started construction. After the reflection of Lao Dong Newspaper, the investor began to refund the money and the authorities began to check.