Roads in Quang Ngai invested more than 34 billion VND but no one went

VIÊN NGUYỄN |

The road is expected to become a boost for urban development in Binh Son district, Quang Ngai province, causing overwhelming disappointment when completed without anyone going.

On October 30, 2019, Mr. Do Thiet Khiem - former Chairman of Binh Son District People's Committee - signed a decision approving the investment project to build a road connecting National Highway 1 (District Team section) to Hoc Cam. The project is invested by the Binh Son District Construction Investment Project Management Board. The entire investment capital is from the district budget.

The project aims to concretize the planning for the expansion of Chau Town - 0, modernize the urban transport infrastructure system, exploit land funds on both sides of the route, promote socio-economic development, improve people's lives... The total initial investment was expected to be 45 billion VND, then adjusted down to 34.4 billion VND. The implementation period lasts from 2019 to 2023.

Diem cuoi cua duong dan den ruong lua. Anh: Vien Nguyen.
The end of the road leads to the rice field. Photo: Vien Nguyen

The route is 507m long, designed at a speed of 50km/h, with a two-lane road surface, spacious with full sidewalks, median strips, trees, lighting systems, drainage... It was thought that this would be a project that would create a boost for urban development in the area, but the reality was completely opposite. After completion in the second quarter of 2023, this modern route is... unused.

The reason is that the road is "amputated" in the middle of the rice field. The first point connected to Highway 1, but pulled straight to the west, the sudden ending between the rice field was being cultivated by the people. There is no next connection, no residential area - the route becomes a soulless asphalt in the middle of the field without buttocks.

What makes people even more upset is that while the district still has countless other urgent projects that need to be repaired and upgraded - such as schools, medical stations, and residential roads - the district has chosen to pour tens of billions of VND into a road that no one is using.

Via he cua tuyen duong nay tro thanh noi phoi phan bo cua nguoi dan. Anh: Vien Nguyen.
The sidewalk of this road has become a place for people to dry cow dung. Photo: Vien Nguyen

Talking to the reporter, the representative of the investor said that the province has approved the land use plan, now has also approved the 1/500 planning in the area of ​​Doi Cam - Hoc Cam street project. The district will call on investors to build residential areas in the project area. When the residential project is invested, Doi Cam - Hoc Cam district roads play the role of the main route to the residential area to promote efficiency.

VIÊN NGUYỄN
RELATED NEWS

Quang Ngai City leaders talk about Thien But Park project slow to start

|

Quang Ngai - Having difficulty in capital and consuming a lot of time to review the art factors, feng shui ... is one of the reasons why the project is stagnant.

The site of the nearly 1,500 billion VND dam project in Quang Ngai is deserted

|

Quang Ngai - The Tra Khuc River downstream dam project is expected to be completed in 2021, but is still unfinished, the construction site is deserted.

Confused when implementing, many key projects in Quang Ngai are sluggish

|

Many key projects in Quang Ngai province are behind schedule, causing difficulties in disbursing public investment capital, directly affecting the province's economic growth rate in 2025.

The Department of Sports and Physical Training has not reported the absence of the Chairman of the Vietnam Boxing Federation

|

The Department of Physical Education and Sports said it has not yet received an official report on the absence of President of the Vietnam Boxing Federation Luu Tu Bao.

Traffic Police Department recommends traffic diversion in Hanoi

|

On the afternoon of September 4, the Traffic Police Department (Ministry of Public Security) said it had just sent a document requesting the Hanoi Department of Construction on traffic diversion in the capital.

Teacher salaries expected to increase, the highest is up to 7 million VND/month excluding allowances

|

The basic salary of all teachers is expected to increase, increasing by at least about 2 million VND, the maximum can be up to 5 - 7 million VND/person/month.

The government dialogues with relatives of the martyrs' grave being bombed in Phu Tho

|

Phu Tho - Thanh Ba commune authorities had a dialogue with relatives of martyrs' graves in Dong Xuan martyrs cemetery, Thanh Ba commune.

People report that the 2-month electricity bill is identical, without any wrong numbers

|

During the August electricity bill period, many people complained about the sudden increase in electricity bills compared to normal.

Quang Ngai City leaders talk about Thien But Park project slow to start

VIÊN NGUYỄN |

Quang Ngai - Having difficulty in capital and consuming a lot of time to review the art factors, feng shui ... is one of the reasons why the project is stagnant.

The site of the nearly 1,500 billion VND dam project in Quang Ngai is deserted

VIÊN NGUYỄN |

Quang Ngai - The Tra Khuc River downstream dam project is expected to be completed in 2021, but is still unfinished, the construction site is deserted.

Confused when implementing, many key projects in Quang Ngai are sluggish

Viên Nguyễn |

Many key projects in Quang Ngai province are behind schedule, causing difficulties in disbursing public investment capital, directly affecting the province's economic growth rate in 2025.