Workers race to catch up with Long Thanh airport's trial operation in September

HÀ ANH CHIẾN |

Dong Nai - Long Thanh Airport is undergoing trial operation from September 2026, in which the passenger terminal package is being raced for progress by thousands of workers.

According to the plan, from September 2026, Long Thanh airport will begin trial operation and will be put into commercial operation by the end of 2026.

To achieve this goal, the investor and contractors are focusing resources on completing the passenger terminal, an item considered the "heart" of the project; in which priority is given to completing the construction and installation of terminal equipment.

Hàng nghìn cán bộ, kỹ sư, công nhân được huy động để thi công gói thầu được ví như trái tim của dự án sân bay Long Thành. Ảnh: HAC
Thousands of officials, engineers, and workers are mobilized to construct the package that is likened to the heart of the Long Thanh airport project. Photo: HAC

Package 5. 10 construction of Long Thanh airport passenger terminal is constructed by Vietur consortium, started in July 2023, with a contract value of more than 35,000 billion VND.

Up to now, the contractor consortium has mobilized thousands of personnel, machinery and equipment to deploy construction, basically completing the reinforced concrete structure, steel roof structure, and glass wall elevation.

According to Vietnam Airports Corporation (ACV), on the entire component project 3 construction site, Long Thanh airport maintains an average of 7,170 direct construction workers. However, there is still a shortage of about 1,500 to 2,000 workers (concentrated in packages 5, 10; 4, 8; 7, 8 and 11, 5).

ACV said it needs about 9,000 direct workers and an indirect team to accelerate internal work and complete dossiers.

Images of officials, engineers, and workers constructing the passenger terminal of Long Thanh airport:

Gói thầu 5.10 nhà ga hành khách là đường gantt tiến độ của toàn bộ dự án sân bay Long Thành giai đoạn 1. Ảnh: HAC
Package 5. 10 passenger terminals are the roadmap of the entire Long Thanh airport project phase 1. Photo: HAC
Do đó, việc thi công được diễn ra khẩn trương, gấp rút. Ảnh: HAC
Therefore, construction is taking place urgently and rushedly. Photo: HAC
Người lao động đang hoàn thiện các kết cấu để tiến hành lắp đặt tại nhà ga hành khách. Ảnh: HAC
Workers are completing structures to proceed with installation at the passenger terminal. Photo: HAC
Lắp đặt hệ thống thông gió tại nhà ga hành khách sân bay Long Thành. Ảnh: HAC
Installing ventilation system at Long Thanh airport passenger terminal. Photo: HAC
Công nhân thi công miệt mài hoàn thiện phần mái nhà ga. Ảnh: HAC
Workers diligently complete the roof of the station. Photo: HAC
Vận hành thử hệ thống xử lý hành lý tại nhà ga hành khách sân bay Long Thành. Ảnh: HAC
Trial operation of the luggage processing system at Long Thanh airport passenger terminal. Photo: HAC
Kiểm tra hệ thống điện tại nhà ga hành khách sân bay Long Thành. Ảnh: HAC
Checking the electrical system at Long Thanh airport passenger terminal. Photo: HAC

Long Thanh airport project reaches level 4F according to the classification of the International Civil Aviation Organization (ICAO), with an investment scale of 100 million passengers/year and 5 million tons of cargo/year. In which, phase 1 builds 2 runways, 1 passenger terminal and synchronous auxiliary items, with a capacity of 25 million passengers/year and 1.2 million tons of cargo/year; completion and commissioning time at the end of 2026

HÀ ANH CHIẾN
RELATED NEWS

Dong Nai is about to hand over enough land for the 1,493 billion VND road connecting Long Thanh airport

|

Dong Nai - The 25B Road Upgrade Project, the section from Nhon Trach center to National Highway 51 passing through 2 wards, is about to complete site handover.

Fastest route from the center of Ho Chi Minh City to Long Thanh airport

|

Ho Chi Minh City - When Long Thanh airport comes into operation, Ho Chi Minh City residents will mainly connect through the Ho Chi Minh City - Long Thanh expressway, Ring Road 3 and Ben Luc - Long Thanh expressway.

Dong Nai recovers more than 1.5ha of land for metro extension project from Ho Chi Minh City to Long Thanh airport

|

Dong Nai - Bien Hoa Ward People's Committee announces the recovery of more than 1.5ha of land to implement the metro project from Ho Chi Minh City to the City Administrative Center and Long Thanh airport.

Focus all resources on putting Long Thanh airport into operation in December 2026

|

Minister of Construction Tran Hong Minh requested to focus all resources to put Long Thanh International Airport into operation according to the plan.

VinSpace signs contract with SpaceX to launch satellite in 2027

|

VinSpace has just signed an important contract with SpaceX to launch a Vietnamese satellite into orbit in 2027.

At least 132 people died in earthquake in Colombia

|

The strongest earthquake in a decade has left hundreds of casualties in Colombia, a red alert was issued.

2026 benchmark scores of all universities nationwide

|

From this afternoon, August 9th, after the virtual filtering process is completed, universities across the country will announce the benchmark scores for 2026.

Dong Nai is about to hand over enough land for the 1,493 billion VND road connecting Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The 25B Road Upgrade Project, the section from Nhon Trach center to National Highway 51 passing through 2 wards, is about to complete site handover.

Fastest route from the center of Ho Chi Minh City to Long Thanh airport

MINH QUÂN |

Ho Chi Minh City - When Long Thanh airport comes into operation, Ho Chi Minh City residents will mainly connect through the Ho Chi Minh City - Long Thanh expressway, Ring Road 3 and Ben Luc - Long Thanh expressway.

Dong Nai recovers more than 1.5ha of land for metro extension project from Ho Chi Minh City to Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - Bien Hoa Ward People's Committee announces the recovery of more than 1.5ha of land to implement the metro project from Ho Chi Minh City to the City Administrative Center and Long Thanh airport.

Focus all resources on putting Long Thanh airport into operation in December 2026

Theo Cổng thông tin Bộ xây dựng |

Minister of Construction Tran Hong Minh requested to focus all resources to put Long Thanh International Airport into operation according to the plan.