Da Nang extends riverbank erosion control project until 2025

Nguyễn Linh |

Due to slow progress in site clearance, the investor of the Yen River embankment project in Da Nang City has requested an extension of the construction period.

The People's Committee of Da Nang City has just approved an investment project to build an emergency anti-erosion embankment at a key location on the rivers of Hoa Vang district with a total investment of 250 billion VND in early September.

The project will be implemented in 2022 - 2025 to build a number of embankment sections at vulnerable locations with high risk of landslides on Yen River, Tuy Loan River and Vinh Dien River to prevent riverbank landslides, protect land, assets, and infrastructure systems of the State and people.

However, according to the Management Board of Investment Projects for Construction of Agricultural Works and Rural Development in Da Nang, the compensation plan of the People's Committee of Da Nang City for the emergency embankment project to prevent landslides on the Yen River bank (section from the downstream of An Trach Dam - Yen River Bridge - Cam Le River junction) was completed in the second quarter of 2024, but has not been completed yet.

One of the reasons is that the large number of compensation records, the project stretches across 3 communes of Hoa Vang district, affecting the work of compensation implementation, receiving people to mobilize land handover of the Council for Land Clearance, support and resettlement.

The work of separating and merging land plots during the clearance process resulted in an increase in the number of compensation records compared to the original plan, so the site clearance work could not be completed as planned.

Up to now, the handed-over site is not continuous and due to the special nature of the embankment construction, the construction must ensure the designed length to lock the embankment head to prevent erosion of the embankment line after the construction is completed, so the actual construction volume is less than the actual handed-over site ratio.

Therefore, the construction package of the emergency anti-erosion embankment on Yen river bank (section from downstream of An Trach dam - Yen river bridge - Cam Le river junction) cannot be completed within the expected completion time of 540 days according to the contract.

In addition, the time of completion of site clearance is also the time when the annual flood season is about to begin, so construction must be temporarily suspended during this time.

The Project Management Board has requested the Department of Planning and Investment of Da Nang City to consider reporting to the People's Committee of Da Nang City to agree in principle to allow an extension of the completion time of the Construction Package of the Emergency Anti-Landslide Embankment on the Yen River Bank (section from the downstream of An Trach Dam - Yen River Bridge - Cam Le River junction) to August 3, 2025.

Nguyễn Linh
RELATED NEWS

Man City takes the top spot in Arsenal's Premier League table

|

On the night of December 27 (Vietnam time), Man City defeated Nottingham Forest 2-1, thereby temporarily taking the top spot in Arsenal's Premier League table.

ASEAN observer group in handling Cambodia-Thailand disagreements

|

Vietnam is ready to work with ASEAN to resolve Thailand-Cambodia disagreements, including strengthening the effectiveness of the ASEAN observer group.

U19 Vietnam futsal team loses Southeast Asian semi-final match

|

On the afternoon of December 27, in Thailand, U19 Vietnam futsal suffered a 3-7 defeat to U19 Indonesia futsal in the semi-finals of the 2025 Southeast Asian U19 Futsal Championship.

Identities of 18 casualties in the overturned truck carrying a charity delegation in Lao Cai

|

Lao Cai - Functional agencies have identified the identities and health status of the victims in the overturned truck carrying the charity delegation.

Female workers contribute to beautifying Da Lat to attend the Patriotic Emulation Congress

|

Lam Dong - Ms. Trinh Thi Phung - Da Lat Urban Services Joint Stock Company was honored to represent more than 92,000 workers at the National Patriotic Emulation Congress.

Estimated number of Ukrainian soldiers leaving the army in 2025

|

The number of Ukrainian soldiers defecting in 2025 is said to account for 1/4 of the country's total army.

Ba Ngan bridge opens to motorbikes, reconnecting the bridge to live on for Da Nang workers

|

Da Nang - Ba Ngan bridge (Duy Phuoc bridge) has officially allowed motorbike traffic after a period of lightning-fast construction of an emergency steel girder span.

Land acquisition issues, river embankment to prevent landslides in Da Nang slow progress

Nguyễn Linh |

Due to site clearance problems, some emergency riverbank anti-erosion projects in Da Nang cannot be implemented on schedule.

Many IT projects in Da Nang are stalled due to legal issues

Mai Hương |

Da Nang Concentrated Information Technology Park and Software Park No. 2 are projects with investment capital of up to thousands of billions of VND but have not yet come into operation due to many difficulties.

Da Nang cannot close all residential roads across the railway yet

Nguyễn Linh |

Da Nang - There are currently 10 residential crossings across the railway that cannot be closed because they are serving traffic while waiting for investment in the construction of a service road.