Da Nang extends riverbank erosion control project until 2025

Nguyễn Linh |

Due to slow progress in site clearance, the investor of the Yen River embankment project in Da Nang City has requested an extension of the construction period.

The People's Committee of Da Nang City has just approved an investment project to build an emergency anti-erosion embankment at a key location on the rivers of Hoa Vang district with a total investment of 250 billion VND in early September.

The project will be implemented in 2022 - 2025 to build a number of embankment sections at vulnerable locations with high risk of landslides on Yen River, Tuy Loan River and Vinh Dien River to prevent riverbank landslides, protect land, assets, and infrastructure systems of the State and people.

However, according to the Management Board of Investment Projects for Construction of Agricultural Works and Rural Development in Da Nang, the compensation plan of the People's Committee of Da Nang City for the emergency embankment project to prevent landslides on the Yen River bank (section from the downstream of An Trach Dam - Yen River Bridge - Cam Le River junction) was completed in the second quarter of 2024, but has not been completed yet.

One of the reasons is that the large number of compensation records, the project stretches across 3 communes of Hoa Vang district, affecting the work of compensation implementation, receiving people to mobilize land handover of the Council for Land Clearance, support and resettlement.

The work of separating and merging land plots during the clearance process resulted in an increase in the number of compensation records compared to the original plan, so the site clearance work could not be completed as planned.

Up to now, the handed-over site is not continuous and due to the special nature of the embankment construction, the construction must ensure the designed length to lock the embankment head to prevent erosion of the embankment line after the construction is completed, so the actual construction volume is less than the actual handed-over site ratio.

Therefore, the construction package of the emergency anti-erosion embankment on Yen river bank (section from downstream of An Trach dam - Yen river bridge - Cam Le river junction) cannot be completed within the expected completion time of 540 days according to the contract.

In addition, the time of completion of site clearance is also the time when the annual flood season is about to begin, so construction must be temporarily suspended during this time.

The Project Management Board has requested the Department of Planning and Investment of Da Nang City to consider reporting to the People's Committee of Da Nang City to agree in principle to allow an extension of the completion time of the Construction Package of the Emergency Anti-Landslide Embankment on the Yen River Bank (section from the downstream of An Trach Dam - Yen River Bridge - Cam Le River junction) to August 3, 2025.

Nguyễn Linh
RELATED NEWS

Many roads in Tuyen Quang are still littered with landslides after floods

|

Tuyen Quang - Severe landslides after floods, but up to now, many roads are still littered with rocks and soil, posing a potential risk to traffic safety.

Another subject buying social housing in Hanoi does not need to draw lots

|

Land users who are recovered to implement urban renovation and embellishment projects in Hanoi are allowed to buy social housing without drawing lots.

Concerns of the once-famous poet - "My mother curses the thief"

|

Dien Bien - Mr. Tong Van Han was the author of the poem that caused controversy and was very famous at one time "My Mother Cursed the Thief".

Plan to arrange surplus principals after implementing school mergers

|

Surplus principals when implementing the policy of merging schools can consider applying the regime and policies according to the provisions of Decree No. 154/2025.

Before Christmas, Hanoi streets are bustling with festive colors

|

Hanoi - In mid-December, the Christmas atmosphere has filled Hanoi Cathedral or Hang Ma Street, attracting a large number of people and tourists to check-in.

SEA Games 33 Medal Schedule on December 14

|

Updated total medal table of the 33rd SEA Games on December 14.

HCMC is about to build a series of elevated roads to relieve traffic jams at gateways

|

Ho Chi Minh City will build a series of elevated roads to form rapid traffic axes, with less intersection with the road below, reducing pressure on the road surface.

Seeing Kim Chung's CT3 social housing application being returned due to lack of salary table photos for the whole company

|

Hanoi - Many people who came to submit applications to buy social housing (NOXH) at the CT3 Kim Chung project were suddenly returned because there was no photocopy of the salary table of the entire company.

Land acquisition issues, river embankment to prevent landslides in Da Nang slow progress

Nguyễn Linh |

Due to site clearance problems, some emergency riverbank anti-erosion projects in Da Nang cannot be implemented on schedule.

Many IT projects in Da Nang are stalled due to legal issues

Mai Hương |

Da Nang Concentrated Information Technology Park and Software Park No. 2 are projects with investment capital of up to thousands of billions of VND but have not yet come into operation due to many difficulties.

Da Nang cannot close all residential roads across the railway yet

Nguyễn Linh |

Da Nang - There are currently 10 residential crossings across the railway that cannot be closed because they are serving traffic while waiting for investment in the construction of a service road.