Da Nang extends riverbank erosion control project until 2025

Nguyễn Linh |

Due to slow progress in site clearance, the investor of the Yen River embankment project in Da Nang City has requested an extension of the construction period.

The People's Committee of Da Nang City has just approved an investment project to build an emergency anti-erosion embankment at a key location on the rivers of Hoa Vang district with a total investment of 250 billion VND in early September.

The project will be implemented in 2022 - 2025 to build a number of embankment sections at vulnerable locations with high risk of landslides on Yen River, Tuy Loan River and Vinh Dien River to prevent riverbank landslides, protect land, assets, and infrastructure systems of the State and people.

However, according to the Management Board of Investment Projects for Construction of Agricultural Works and Rural Development in Da Nang, the compensation plan of the People's Committee of Da Nang City for the emergency embankment project to prevent landslides on the Yen River bank (section from the downstream of An Trach Dam - Yen River Bridge - Cam Le River junction) was completed in the second quarter of 2024, but has not been completed yet.

One of the reasons is that the large number of compensation records, the project stretches across 3 communes of Hoa Vang district, affecting the work of compensation implementation, receiving people to mobilize land handover of the Council for Land Clearance, support and resettlement.

The work of separating and merging land plots during the clearance process resulted in an increase in the number of compensation records compared to the original plan, so the site clearance work could not be completed as planned.

Up to now, the handed-over site is not continuous and due to the special nature of the embankment construction, the construction must ensure the designed length to lock the embankment head to prevent erosion of the embankment line after the construction is completed, so the actual construction volume is less than the actual handed-over site ratio.

Therefore, the construction package of the emergency anti-erosion embankment on Yen river bank (section from downstream of An Trach dam - Yen river bridge - Cam Le river junction) cannot be completed within the expected completion time of 540 days according to the contract.

In addition, the time of completion of site clearance is also the time when the annual flood season is about to begin, so construction must be temporarily suspended during this time.

The Project Management Board has requested the Department of Planning and Investment of Da Nang City to consider reporting to the People's Committee of Da Nang City to agree in principle to allow an extension of the completion time of the Construction Package of the Emergency Anti-Landslide Embankment on the Yen River Bank (section from the downstream of An Trach Dam - Yen River Bridge - Cam Le River junction) to August 3, 2025.

Nguyễn Linh
RELATED NEWS

Khanh Hoa supports 300,000 VND for each student in flooded areas to buy uniforms

|

Khanh Hoa - The Standing Committee of the Provincial Party Committee agreed on the policy of supporting 300,000 VND/student affected by floods to buy uniforms.

Assessing the worst scenario of storm No. 15 Koto, forecasting affected provinces

|

The most likely scenario at present is that storm No. 15 will change direction to the north when it reaches the northwest sea of Truong Sa province, weakening into a low pressure area.

Fire-red field kitchen cars in the flooded area, cooking more than 1,500 meals to support people

|

Dak Lak - The self-propelled kitchen truck of Brigade 655 caught fire in the wind and rain, cooking more than 1,500 meals for people in the flooded areas.

"Say a lifetime for you" and the most listened songs in 2025

|

In addition to the series of songs by Hoa Minzy, Phuong My Chi... that were listened to a lot in 2025, the AI-song version of "Say a lifetime for you" also created a "fever" this year.

People denounce a series of passenger cars entering the emergency lane of Ring Road 3, traffic police take action

|

Hanoi - People reported many passenger cars entering the emergency lane on Ring Road 3, traffic police stepped in to verify and handle it promptly.

Phu Quoc residents roast salt and pepper, fish warehouses wrapped to send to people affected by natural disasters

|

An Giang - Thousands of boxes of salt and pepper and braised fish are carefully packaged, wrapped with the love of the people of Phu Quoc pearl island to send to people affected by natural disasters.

Merging a series of schools, temporarily suspending the recruitment of civil servants in the unit under arrangement

|

According to Lao Dong, as of November 26, many localities across the country have plans to arrange and merge schools.

Land acquisition issues, river embankment to prevent landslides in Da Nang slow progress

Nguyễn Linh |

Due to site clearance problems, some emergency riverbank anti-erosion projects in Da Nang cannot be implemented on schedule.

Many IT projects in Da Nang are stalled due to legal issues

Mai Hương |

Da Nang Concentrated Information Technology Park and Software Park No. 2 are projects with investment capital of up to thousands of billions of VND but have not yet come into operation due to many difficulties.

Da Nang cannot close all residential roads across the railway yet

Nguyễn Linh |

Da Nang - There are currently 10 residential crossings across the railway that cannot be closed because they are serving traffic while waiting for investment in the construction of a service road.