Nguyễn Linh |

Due to slow progress in site clearance, the investor of the Yen River embankment project in Da Nang City has requested an extension of the construction period.

The People's Committee of Da Nang City has just approved an investment project to build an emergency anti-erosion embankment at a key location on the rivers of Hoa Vang district with a total investment of 250 billion VND in early September.

The project will be implemented in 2022 - 2025 to build a number of embankment sections at vulnerable locations with high risk of landslides on Yen River, Tuy Loan River and Vinh Dien River to prevent riverbank landslides, protect land, assets, and infrastructure systems of the State and people.

However, according to the Management Board of Investment Projects for Construction of Agricultural Works and Rural Development in Da Nang, the compensation plan of the People's Committee of Da Nang City for the emergency embankment project to prevent landslides on the Yen River bank (section from the downstream of An Trach Dam - Yen River Bridge - Cam Le River junction) was completed in the second quarter of 2024, but has not been completed yet.

One of the reasons is that the large number of compensation records, the project stretches across 3 communes of Hoa Vang district, affecting the work of compensation implementation, receiving people to mobilize land handover of the Council for Land Clearance, support and resettlement.

The work of separating and merging land plots during the clearance process resulted in an increase in the number of compensation records compared to the original plan, so the site clearance work could not be completed as planned.

Up to now, the handed-over site is not continuous and due to the special nature of the embankment construction, the construction must ensure the designed length to lock the embankment head to prevent erosion of the embankment line after the construction is completed, so the actual construction volume is less than the actual handed-over site ratio.

Therefore, the construction package of the emergency anti-erosion embankment on Yen river bank (section from downstream of An Trach dam - Yen river bridge - Cam Le river junction) cannot be completed within the expected completion time of 540 days according to the contract.

In addition, the time of completion of site clearance is also the time when the annual flood season is about to begin, so construction must be temporarily suspended during this time.

The Project Management Board has requested the Department of Planning and Investment of Da Nang City to consider reporting to the People's Committee of Da Nang City to agree in principle to allow an extension of the completion time of the Construction Package of the Emergency Anti-Landslide Embankment on the Yen River Bank (section from the downstream of An Trach Dam - Yen River Bridge - Cam Le River junction) to August 3, 2025.

Nguyễn Linh
RELATED NEWS

Overcoming dangerous mountain passes, bringing votes to voters in isolated areas in Gia Lai

|

Gia Lai - To get the ballots to voters in O2 village (Vinh Son commune), the election team had to cross forests and dangerous passes to complete all stages before voting.

Cuba and the US government are in dialogue

|

Cuban President Miguel Díaz-Canel confirmed that dialogues with the US in an effort to resolve disagreements and seek cooperation are underway.

Cars congested at the Phan Thiet - Dau Giay expressway exit due to technical errors at the toll station

|

Lam Dong - Technical incident at the Phan Thiet intersection toll station on the Phan Thiet - Dau Giay expressway caused prolonged traffic jams.

Solutions for Vietnamese women's football

|

To talk about solutions for Vietnamese women's football, many people can list them, but starting to implement them will see many difficulties.

Ha Dong Ward accelerates site clearance for Yen Nghia Pumping Station project

|

Hanoi - After nearly a decade of obstacles, the Yen Nghia Pumping Station project through Ha Dong ward is entering the final stage of site clearance.

Ensuring energy to promote double-digit growth in Ho Chi Minh City

|

Ho Chi Minh City with the goal of double-digit growth is facing the requirement to ensure stable energy supply to maintain development momentum.

Live football Da Nang vs Hoang Anh Gia Lai in round 16 of V.League

|

Live football match Da Nang vs Hoang Anh Gia Lai in round 16 of V.League 2025-2026 at 6:00 PM today (March 13).

Voters in Hanoi island commune scan QR codes to find out candidates

|

Hanoi - Voters in Minh Chau island commune scan QR codes to find out the list of candidates that has been digitized. The atmosphere of elections is bustling on the island commune in the middle of the Red River.

Land acquisition issues, river embankment to prevent landslides in Da Nang slow progress

Nguyễn Linh |

Due to site clearance problems, some emergency riverbank anti-erosion projects in Da Nang cannot be implemented on schedule.

Many IT projects in Da Nang are stalled due to legal issues

Mai Hương |

Da Nang Concentrated Information Technology Park and Software Park No. 2 are projects with investment capital of up to thousands of billions of VND but have not yet come into operation due to many difficulties.

Da Nang cannot close all residential roads across the railway yet

Nguyễn Linh |

Da Nang - There are currently 10 residential crossings across the railway that cannot be closed because they are serving traffic while waiting for investment in the construction of a service road.