Da Nang extends riverbank erosion control project until 2025

Nguyễn Linh |

Due to slow progress in site clearance, the investor of the Yen River embankment project in Da Nang City has requested an extension of the construction period.

The People's Committee of Da Nang City has just approved an investment project to build an emergency anti-erosion embankment at a key location on the rivers of Hoa Vang district with a total investment of 250 billion VND in early September.

The project will be implemented in 2022 - 2025 to build a number of embankment sections at vulnerable locations with high risk of landslides on Yen River, Tuy Loan River and Vinh Dien River to prevent riverbank landslides, protect land, assets, and infrastructure systems of the State and people.

However, according to the Management Board of Investment Projects for Construction of Agricultural Works and Rural Development in Da Nang, the compensation plan of the People's Committee of Da Nang City for the emergency embankment project to prevent landslides on the Yen River bank (section from the downstream of An Trach Dam - Yen River Bridge - Cam Le River junction) was completed in the second quarter of 2024, but has not been completed yet.

One of the reasons is that the large number of compensation records, the project stretches across 3 communes of Hoa Vang district, affecting the work of compensation implementation, receiving people to mobilize land handover of the Council for Land Clearance, support and resettlement.

The work of separating and merging land plots during the clearance process resulted in an increase in the number of compensation records compared to the original plan, so the site clearance work could not be completed as planned.

Up to now, the handed-over site is not continuous and due to the special nature of the embankment construction, the construction must ensure the designed length to lock the embankment head to prevent erosion of the embankment line after the construction is completed, so the actual construction volume is less than the actual handed-over site ratio.

Therefore, the construction package of the emergency anti-erosion embankment on Yen river bank (section from downstream of An Trach dam - Yen river bridge - Cam Le river junction) cannot be completed within the expected completion time of 540 days according to the contract.

In addition, the time of completion of site clearance is also the time when the annual flood season is about to begin, so construction must be temporarily suspended during this time.

The Project Management Board has requested the Department of Planning and Investment of Da Nang City to consider reporting to the People's Committee of Da Nang City to agree in principle to allow an extension of the completion time of the Construction Package of the Emergency Anti-Landslide Embankment on the Yen River Bank (section from the downstream of An Trach Dam - Yen River Bridge - Cam Le River junction) to August 3, 2025.

Nguyễn Linh
RELATED NEWS

Thailand apologizes for the incident of not playing the national anthem in the match between U22 Vietnam and U22 Laos

|

A rare incident occurred in the opening match of the 33rd SEA Games men's football event between U22 Vietnam and U22 Laos when players of both teams had to "sing" the National Anthem.

Hanoi Police warn of the "diplomatic" scam of social housing spreading online

|

Hanoi - At the Social Housing Dialogue Conference, representatives of Hanoi City Police warned about the "diplomatic" trick of buying social housing

Truck overturned on Cu Hin Pass, causing prolonged traffic congestion

|

Khanh Hoa - The truck overturned accident at Cu Hin Pass caused a long traffic jam from Nha Trang to Cam Ranh airport.

Forecast of bad weather areas in the next 2 days due to tropical depression and cold air

|

The meteorological agency warns that the Dak Lak - Khanh Hoa sea area is affected by the tropical depression.

Establishment of Da Nang Free Trade Zone with seaports, airports and economic zones

|

The Government proposes a series of specific mechanisms and policies for the development of Da Nang, including the establishment of a Free Trade Zone with seaports, airports and economic zones.

Live football U22 Vietnam vs U22 Laos at SEA Games 33

|

Live match between U22 Vietnam and U22 Laos at SEA Games 33, taking place at 4:00 p.m. today (December 3).

La Vong Group's BT project unexpectedly reduces capital by nearly 245 billion VND

|

The BT project of a unit under La Vong Group has been invested in for more than 10 years but is still unfinished, people live in pollution, while the project has unexpectedly decreased by nearly 245 billion VND.

Land acquisition issues, river embankment to prevent landslides in Da Nang slow progress

Nguyễn Linh |

Due to site clearance problems, some emergency riverbank anti-erosion projects in Da Nang cannot be implemented on schedule.

Many IT projects in Da Nang are stalled due to legal issues

Mai Hương |

Da Nang Concentrated Information Technology Park and Software Park No. 2 are projects with investment capital of up to thousands of billions of VND but have not yet come into operation due to many difficulties.

Da Nang cannot close all residential roads across the railway yet

Nguyễn Linh |

Da Nang - There are currently 10 residential crossings across the railway that cannot be closed because they are serving traffic while waiting for investment in the construction of a service road.