The Ho Chi Minh Road project, the section avoiding the East of Buon Ma Thuot, is over 39km long, with a total capital of over VND1,800 billion from the central budget.
The project is invested by the Provincial Management Board of Investment Projects for Construction of Traffic Works and Rural Development.
This is one of two key traffic projects registered by Dak Lak province to be completed in 2025 to practically celebrate the 14th National Party Congress.
On October 27, information from the Investor said that the intersection at the beginning of the route with National Highway 14 is 113m long (through the old Cuor Dang commune) and was once stuck in the handover of land due to affecting 64 households, causing the project to be behind schedule.
With the drastic participation of the political system, on October 9, the household finally handed over the site. Thereby, creating a turning point to help investors and contractors focus on accelerating construction and disbursing public investment capital.
According to the Dak Lak Provincial Department of Finance, to date, the province's public investment capital plan for 2025 is more than 13,092 billion VND. By the end of October 15, the whole province had disbursed more than VND 5,583 billion, equal to 42.64% of the plan.
In order to ensure the progress of public investment disbursement, the Provincial People's Committee regularly organizes thematic meetings on basic construction and working groups to inspect each project, especially key projects, to promptly grasp and remove difficulties.
Vice Chairman of the Provincial People's Committee Truong Cong Thai requested departments, branches and units to focus on guiding and supervising after investment; reviewing administrative procedures; assigning staff and flexibly handling problems, especially in site clearance and capital transfer.
At the same time, it is necessary to develop a plan to inspect key projects and people's lives and strengthen coordination and unity between levels and sectors in the disbursement process.
Dak Lak will establish working groups to direct the acceleration of public investment disbursement
On October 24, the Standing Committee of the Dak Lak Provincial Party Committee held the 1st Executive Committee Conference with many important contents.
Speaking at the conference, Mr. Luong Nguyen Minh Triet - Alternate Member of the Party Central Committee, Secretary of the Provincial Party Committee requested the Standing Committee of the Provincial People's Committee to resolutely direct solutions to promote economic development, striving to achieve the highest growth rate of 8%.
In particular, urgently establish working groups to direct the acceleration of disbursement, associated with specific responsibilities in each project, each locality, each individual.
"It is necessary to focus on removing bottlenecks in site clearance, construction materials, overlapping planning, and labor. Transfer capital, consider the responsibility of the construction contractor.
At the same time, it will strengthen the application of information technology in tax collection management, striving to collect the budget in 2025 to reach the plan of VND 15,000 billion" - Mr. Triet noted.