Accelerate repairing damaged garbage bridges requiring timber boarding

TRẦN TUẤN |

Ha Tinh - The construction unit is focusing on speeding up the repair progress of the damaged Garbage Bridge and the bridge abutment must use a wooden plank under the abutment to reduce vibration.

On May 23, according to a reporter from Lao Dong Newspaper, Investment and Construction Consulting Joint Stock Company 126 is repairing the old Garbage Bridge (the unit located on the right side of National Highway 1 in the South - North direction) in Cam Trung Commune, Cam Xuyen District.

During the construction process, the contractor completely divided the old Trash Bridge, and at the same time placed a soft median strip to divide the new Trash Bridge (located on the left side in the South - North direction) into 2 lanes for vehicles to pass.

Trong qua trinh sua chua, don nguyen cau Rac moi phia ben trai duoc chia doi lam 2 lan xe de cac phuong tien luu thong qua lai. Anh: Tran Tuan.
During the repair process, the new Garbage bridge unit on the left side was divided into 2 lanes for vehicles to pass. Photo: Tran Tuan.
Mat cau Rac moi truoc day la mot lan xe theo huong Bac - Nam, nay tam thoi chia lam 2 lan xe cho cac phuong tien luu thong. Anh: Tran Tuan.
The new Garbage Bridge surface was previously a traffic lane in the North - South direction, now temporarily divided into 2 lanes for traffic. Photo: Tran Tuan.

A representative of the Project Management Board said that the construction measures for damaged expansion joints will be eliminated and a new expansion joints will be replaced.

Damaged concrete beams will be chiseled, replaced and added horizontal beams to increase links for the bridge. The wooden planks under the abutment to reduce shock vibration are also removed to build the concrete layer covering the new girder.

Nhung tam van go truoc do duoc chen duoi cau. Anh: Tran Tuan.
The wooden planks were previously installed under the bridge. Photo: Tran Tuan.

The bridge surface has also been scraped and re-paved with a new 7cm thick layer of asphalt concrete to ensure safety and smooth traffic when traveling here.

The project to repair the old Garbage Bridge has a total investment of 3.3 billion VND, of which the construction value is 2.95 billion VND, invested by Road Management Area II (Vietnam Road Administration).

126 Investment and Construction Consulting Joint Stock Company is the construction unit. The project implementation period is within 3 months, from April 17 to July 16.

Because the old Garbage Bridge is located on National Highway 1 with a large number of vehicles, the investor and the construction unit set a goal of focusing on speeding up the construction progress as quickly as possible, while paying special attention to ensuring safety during the construction process.

Cau Rac thoi diem chua sua chua. Anh: Tran Tuan.
the Garbage Bridge at a time when it had not been repaired. Photo: Tran Tuan.

Previously, Lao Dong Newspaper reported the damage and deterioration of the old Garbage Bridge, so the road management unit had to use many planks under the southern part of the bridge with broken concrete in the girder to reduce shock and avoid widespread damage.

TRẦN TUẤN
RELATED NEWS

Focus on repairing coastal roads full of potholes in Ha Tinh

|

Ha Tinh - With favorable weather, contractors are focusing on the construction of the Ha Tinh coastal road repair project in degraded locations, full of potholes and unsafe potholes.

Agree to repair and upgrade Ha Tinh Provincial Stadium

|

Ha Tinh - The Provincial People's Committee has just agreed in principle to repair and upgrade the provincial stadium according to the proposal of the Department of Culture, Sports and Tourism.

Businesses bring gifts to cars, workers feel warm in the days leading up to Tet

|

Can Tho - Tet gifts are meticulously tied and fixed onto cars by businesses and trade unions, making workers feel warm before the New Year.

Notable forecasts for gold prices at the end of 2026

|

Gold prices are forecast to reach 5,900 USD/ounce by the end of 2026 thanks to Fed interest rate cuts and buying power from central banks.

Family reunion thanks to free train tickets from the Trade Union

|

Ha Tinh - Landing at Yen Trung station with a pair of free tickets to return to their hometown for reunion, many workers thanked the Trade Union organization for this meaningful program.

9th Hour No. 188: When the Heart Goes Away - Part 1

|

Hour 9 - A happy family, the husband suddenly gets lost with a karaoke girl and secretly builds his own "home". Where will this marriage go?

Chairman of the Vietnam General Confederation of Labor presents 200 Tet gifts to workers in difficult circumstances in Dak Lak

|

Dak Lak - Chairman of the Vietnam General Confederation of Labor has presented 200 Tet gifts to union members and workers, contributing to helping them celebrate Tet more fully.

Hanoi Party Secretary inspects the construction progress of Hong Ha bridge

|

Politburo member, Secretary of the Hanoi Party Committee Nguyen Duy Ngoc highly appreciated the efforts of the forces working at the Hong Ha bridge construction site.

Focus on repairing coastal roads full of potholes in Ha Tinh

TRẦN TUẤN |

Ha Tinh - With favorable weather, contractors are focusing on the construction of the Ha Tinh coastal road repair project in degraded locations, full of potholes and unsafe potholes.

Agree to repair and upgrade Ha Tinh Provincial Stadium

TRẦN TUẤN |

Ha Tinh - The Provincial People's Committee has just agreed in principle to repair and upgrade the provincial stadium according to the proposal of the Department of Culture, Sports and Tourism.

Sửa chữa tuyến đường mới làm đã hỏng sau phản ánh của Lao Động

Lam Thanh |

Hà Giang - Qua kiểm tra, tuyến đường liên thôn trị giá 6,5 tỉ đồng tại huyện Quản Bạ có hơn 10 vị trí hư hỏng, hiện đang được đục, cào bóc để đổ bê tông mới.