The project to dredge and reinforce Suoi Cai has a length of nearly 19km, originating from the intersection with DT 742 road to Dong Nai river. The project has a total initial approved investment capital of more than 4,900 billion VND.
The project will build a reinforced channel with precast reinforced concrete panels placed on a reinforced concrete beam and pile frame system. The bottom of the canal is reinforced with 30cm thick carpet. The canal bank is 17m wide (road surface is 7.5m wide), and the canal sidewalk is 5m wide.
This is a project that people are interested in because it has a large amount of investment capital in Binh Duong. The project has a very important meaning in drainage, landscape creation, and urban beautification of a large area of land. The project was assigned to the Project Management Board of Agriculture and Rural Development as the investor.
Regarding site clearance progress, the Project Management Board of Agriculture and Rural Development said that there are 919 cases affected by the project. To date, a total compensation budget of 2,119 billion VND has been approved, and over 520 households have received money and handed over the premises.
Regarding construction, the project includes 10 construction packages. By the end of 2023, after receiving qualified premises, the investor has organized the selection of contractors for 2 construction packages (2A, 2B). ) belongs to the section from Tho Ut bridge to Ben San bridge, 5.8km long and construction will start in early 2024.
To date, the value of the volume of implementation of these two bidding packages has reached 25% of the signed contract and is expected to complete both bidding packages on May 25, 2025.

Focus on site clearance
The Project Management Board of Agriculture and Rural Development said that in the last 6 months of 2024, the unit will not open more construction bidding packages and focus on directing the implementation of compensation and site clearance. for the entire project. Besides, focusing on constructing prefabricated structures, clearing and dredging the flow. When entering the dry season, we will organize additional machinery, equipment, and human resources to work overtime and speed up the construction progress of items serving drainage.