The appearance of 226 billion dong connected to the largest irrigation lake in Bac Kan

Nguyễn Hoàn |

Bac Kan - After nearly 2 years of implementation, the hundred billion dong road project connecting the city to Lake Lake has gradually revealed, expected to be completed in 2025.

As one of the three key projects of Bac Kan City and subject to a special supervision of the province, the road project to Nam Cut Lake (project) has been identified as an essential infrastructure works, serving urban development and people's connection.

The project was started in December 2023, invested by Bac Kan City Project and Investment Board, with a total capital of about VND 226 billion, of which the central budget supported VND 90 billion, the rest from the city budget and other legal capital sources.

The route has a total length of about 6km, divided into 3 sections. In particular, the section 1 is about 1.4km long, built according to urban road standards, with a road surface of 10.5m wide and sidewalks on both sides of 3m wide.

Section 2 is about 1.5km long, built according to the scale of level IV, 7m wide road surface, sidewalk on each side 3m.

Paragraph 3 is the lake around the lake, about 3.1km long. The road surface is 7.5m wide, the sidewalk on each side is 1.25m, in accordance with the standard level IV road.

Toan canh tuyen duong tram ti dong noi TP Bac Kan vao ho Nam Cat. Anh: Nguyen Hoan.
Overview of the hundred billion dong route connecting Bac Kan City to Nam Cut Lake. Photo: Nguyen Hoan.

On April 16, the recognition of PV, after nearly 2 years of implementation, the shape of the road project to Lu Chua Lake gradually revealed.

In the area of ​​paragraph 1, paragraph 3 investors are creating ground, luem, taking the land from high position to low position, spreading rocks ...

On the construction site, workers and machines are mobilized to level, complete steps, grooves, talks and some other auxiliary items.

As a household with a house near the project, Mr. Nguyen Van Toan (Bac Kan City) said that when the project information was implemented, he and the people of the area were very happy and expected the project to be put into operation soon.

"Previously, the way from Bac Kan City to Lake is not easy. If the project is completed, people will travel conveniently, transport more faster goods, save time," Toan said.

Mr. Tran Cong Hoa - Director of the Department of Finance said that the road project to Lu Chua Lake will be completed in 2025.

In the process of implementing the project, the unit also faces some difficulties in terms of premises, but still ensures the schedule as well as planned as well as ensuring the time of capital arrangement.

The route when completed will contribute to improving technical infrastructure in Nam Cut Lake area, and at the same time create favorable conditions for socio -economic development in the area.

Some images recorded:

1
After nearly 2 years of implementation, the largest road to Bac Kan hydroelectric lake has been revealed. Photo: Nguyen Hoan.
2
Some road sections have been constructed and scattered. Photo: Nguyen Hoan.
3
Taluy area on both sides of the road is gradually completed. Photo: Nguyen Hoan.
4
The workers and machines are urgently completing the level and grooves. Photo: Nguyen Hoan.
Nguyễn Hoàn
RELATED NEWS

Accelerating the construction of a hundred-billion-dong road in the mountainous district of Thai Nguyen

|

The hundred-billion-dong road connecting National Highway 3 with Provincial Road 269B with a total investment of 222 billion VND, implemented in Phu Binh district is about to be completed.

Hundred-billion-dong road connecting war zones speeds up for Tet

|

The hundred-billion-dong road project connecting the Thai Nguyen war zone is being rushed to completion near Tet, helping to upgrade traffic infrastructure and promote local tourism.

Northwest at the end of the day: Hundred billion dong road in mountainous district

|

Hundred billion VND road in mountainous district of Thai Nguyen; more than 13 billion VND for lighting up A1 Hill relic; People wrap cakes to give to fans in Viet Tri...

Enrollment 2026: Series of notable adjustments from universities

|

Many universities have announced their enrollment plans for 2026, with some adjustments to admission methods and supplementing training programs.

Trillion-VND coastal road through Thanh Hoa: Completed section, unfinished section

|

Thanh Hoa - After many years of implementing the coastal road project, many sections have been completed, but many sections are still "motionless".

Cuba turns to Chinese energy amid US oil cuts

|

Cuba accelerates solar power development with strong backing from China as the US tightens oil sanctions against this island nation.

Russian Northern army defeats more than 50 Ukrainian strongholds in a day

|

The Russian Northern Army destroyed more than 50 targets of Ukrainian armed forces in the Kharkov region in the past 24 hours.

Lunar New Year Festival in Ho Chi Minh City: People get to take motorbike taxis and distribute free food

|

Ho Chi Minh City - People going to the full moon festival in Thu Dau Mot ward are transported by motorbike taxi, receiving free food and drinks.

Accelerating the construction of a hundred-billion-dong road in the mountainous district of Thai Nguyen

Nguyễn Hoàn |

The hundred-billion-dong road connecting National Highway 3 with Provincial Road 269B with a total investment of 222 billion VND, implemented in Phu Binh district is about to be completed.

Hundred-billion-dong road connecting war zones speeds up for Tet

Nguyễn Hoàn |

The hundred-billion-dong road project connecting the Thai Nguyen war zone is being rushed to completion near Tet, helping to upgrade traffic infrastructure and promote local tourism.

Northwest at the end of the day: Hundred billion dong road in mountainous district

Nhóm PV |

Hundred billion VND road in mountainous district of Thai Nguyen; more than 13 billion VND for lighting up A1 Hill relic; People wrap cakes to give to fans in Viet Tri...