Adjusting Gia Nghia - Chon Thanh Expressway reduces 1,000 billion VND

BẢO LÂM |

Dak Nong - The center of the Gia Nghia (Dak Nong) - Chon Thanh (Binh Phuoc) expressway will move nearly 8km west compared to the pre-feasibility plan.

On the afternoon of December 31, information from the Dak Nong Provincial Party Committee Office said that the unit had just announced the direction of the Provincial Party Committee Standing Committee on selecting a plan to implement the investment project to build the North-South Expressway in the West, Gia Nghia (Dak Nong) - Chon Thanh (Binh Phuoc) section.

The Standing Committee of Dak Nong Provincial Party Committee agreed to choose option 2. Accordingly, the centerline of the expressway will move nearly 8km west compared to the pre-feasibility plan.

The starting point of the route is expected to intersect with Ho Chi Minh road at Km1923+750, in Kien Thanh commune, Dak R'lap district.

This route is suitable for the planning of the North-South Expressway in the West, has favorable terrain, does not affect the Nhan Co Alumina project complex and helps save more than 1,000 billion VND compared to the pre-feasibility plan.

However, this route will pass through the Nhan Co bauxite mine area, so it is necessary to request permission to adjust exploitation and assess environmental impact.

The Gia Nghia - Chon Thanh Expressway project has a total length of 128.8km, passing through Dak Nong and Binh Phuoc provinces, with a total investment of VND25,540 billion. The project is expected to be basically completed in 2026 and put into operation in 2027.

Dak Nong Provincial People's Committee has allocated 250 billion VND for site clearance and construction of the service road. The Provincial Construction Investment Project Management Board was assigned as the investor of the service road project. Dak R'lap District People's Committee is in charge of site clearance.

Previously, on December 27, Dak Nong province requested Binh Phuoc province to direct investors to promptly complete the feasibility study report for approval, ensuring the overall progress of the project.

BẢO LÂM
TIN LIÊN QUAN

Busy construction of North-South expressway in Ha Tinh

|

Ha Tinh - December 31 is the last day of the 2024 calendar year. At the construction site of the North-South expressway through Ha Tinh province, workers are still busy speeding up construction progress.

Racing progress at the Western highway construction site

|

In the last days of 2024, at the two North-South expressway construction sites, Can Tho - Ca Mau and Chau Doc - Can Tho - Soc Trang sections, the labor pace is urgent and bustling towards the goal of reaching the finish line on time.

Trucks carrying construction materials for the highway destroyed many roads in Binh Dinh

|

Through inspection, many residential roads and provincial roads in Binh Dinh province were seriously damaged by vehicles carrying construction materials for the highway.

Soil and rocks suddenly collapsed in Lai Chau, husband was swept away, wife got out of a car and escaped

|

Lai Chau - A serious landslide from the positive slope to the surface of National Highway 4D killed one person.

Recklessly overtaking in the middle of traffic jam, a passenger bus hit a male student in Lam Dong and killed him

|

Lam Dong - Recklessly overtaking while National Highway 20 was congested, a passenger bus crashed head-on into a motorbike, causing an 11th grade male student in Ward 3, Bao Loc to die on the spot.

The Ministry of Public Security promotes the rank of Traffic Police Captain who sacrificed his life in Lai Chau

|

Lai Chau - Captain Ha Van Minh - Traffic Police Department, Provincial Police - died while on duty in Muong So commune.

Tho Xuan Airport sets up additional barriers to prevent illegal access

|

Thanh Hoa - After the appearance of consecutive unmanned aerial vehicles illegally encroaching, Tho Xuan airport has set up barriers to prevent them.

Tight control from the border to prevent smuggled goods from entering the country

|

Quang Tri - The smugglers are sophisticated, finding every way to smuggle smuggled and banned goods from the border area into the inland for consumption.

Busy construction of North-South expressway in Ha Tinh

TRẦN TUẤN |

Ha Tinh - December 31 is the last day of the 2024 calendar year. At the construction site of the North-South expressway through Ha Tinh province, workers are still busy speeding up construction progress.

Racing progress at the Western highway construction site

TẠ QUANG - YẾN PHƯƠNG |

In the last days of 2024, at the two North-South expressway construction sites, Can Tho - Ca Mau and Chau Doc - Can Tho - Soc Trang sections, the labor pace is urgent and bustling towards the goal of reaching the finish line on time.

Trucks carrying construction materials for the highway destroyed many roads in Binh Dinh

Hoài Phương |

Through inspection, many residential roads and provincial roads in Binh Dinh province were seriously damaged by vehicles carrying construction materials for the highway.